Cal 2

Description

Cal 2
Enrique Gomez
Quiz by Enrique Gomez, updated more than 1 year ago
Enrique Gomez
Created by Enrique Gomez over 5 years ago
11
0

Resource summary

Question 1

Question
Quality audits are an important part of quality management because:
Answer
  • a. They allow for quantification of the risk
  • b. They randomly audit product results to see if they are meeting quality standards
  • c. They check it to see if the quality process is being followed
  • d. They are conducted without prior notice and do not allow team members time to cover up defects

Question 2

Question
The e-commerce project is in the middle of Control Quality. Which of the following is a tool that the Project Manager will use in this area?
Answer
  • a. Inspection
  • b. Quality management plan
  • c. Rework
  • d. Acceptance decisions

Question 3

Question
Which quality process is performed first?
Answer
  • a. Quality Definition
  • b. Manage Quality
  • c. Plan Quality management
  • d. Control Quality

Question 4

Question
Which of the following is most representative of the Total Quality Management philosophy?
Answer
  • a. Decreasing inventory to zero or near zero levels
  • b. Everyone can contribute to quality
  • c. Zero defects
  • d. Continuous improvement is preferred over disruptive change

Question 5

Question
The BEST tool to use to look for results that are out of control is?
Answer
  • a. Pareto chart
  • b. Control chart
  • c. Ishikawa diagram
  • d. Statistical sampling

Question 6

Question
Which process identifies the ways to eliminate causes of unsatisfactory performance?
Answer
  • a. Project Quality Management.
  • b. Control Quality.
  • c. Manage Quality.
  • d. Perform Quality Performance.

Question 7

Question
Which of these quality standards is the highest?
Answer
  • a. Three sigma quality
  • b. 99% quality
  • c. Six sigma quality
  • d. It is impossible to determine without further information Six sigma quality

Question 8

Question
The project is going through Manage Quality. Which of the following is a key tool that the Project Manager will use in performing this work on the project?
Answer
  • a. Quality Audits
  • b. Quality improvement
  • c. Quality Management Plan
  • d. Quality testing

Question 9

Question
Which of the following is NOT a part of the Plan Quality Management process?
Answer
  • a. Benchmarking
  • b. Audits
  • c. Cost-benefit analysis
  • d. Design of experiments

Question 10

Question
The Project Manager and a software developer are discussing quality. The Project Manager explains he just got back from PMP training based on the PMBOK Guide. How will he define quality?
Answer
  • a. Meeting the customers needs
  • b. Scope Verification
  • c. The degree to which a set of inherent characteristics fulfill requirements
  • d. Conformance to Use and Fitness of Requirements

Question 11

Question
Who was the founder of Total Quality Management?
Answer
  • a. Deming
  • b. Herzberg
  • c. Ansoff
  • d. Johnson

Question 12

Question
You are the project manager of a project and have come up with a bar graph of problems and their frequencies. This kind of chart is called a :?
Answer
  • a. Deming chart
  • b. Pareto chart
  • c. Ishikawa diagram
  • d. Control chart

Question 13

Question
Plan Quality includes all of the following outputs EXCEPT:
Answer
  • a. Quality management plan
  • b. Acceptance
  • c. Quality metrics
  • d. Scope baseline updates

Question 14

Question
What is an histogram?
Answer
  • a. An Histogram is the same as a Pareto chart and shows the aggregation of defects
  • b. An Histogram is a pie chart that shows the distribution of inspections during the execution phase
  • c. An Histogram is a bar graph that shows data out of control
  • d. An Histogram can show the number of defects by source or by component.

Question 15

Question
The technique of comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance is known as:?
Answer
  • a. Workbench
  • b. Benchmarking
  • c. Quality Control
  • d. Best Practices

Question 16

Question
Which of the following tools is used during Plan Quality?
Answer
  • a. Control Charts
  • b. Scatter Diagram
  • c. Mind maping
  • d. Cause and Effect Diagram

Question 17

Question
That following are the goals of Manage Quality EXCEPT:
Answer
  • a. Confirm that project quality activities conform to quality policies and procedures.
  • b. Continuous quality improvement.
  • c. Verify project results comply with relevant quality standards.
  • d. Ensure appropriate quality standards have been setup for the project.

Question 18

Question
Which of the following relates to Root Cause Analysis?
Answer
  • a. Process Analysis
  • b. Performance Measurements
  • c. Quality Audits
  • d. Quality control measurements

Question 19

Question
Reduced quality on a project would MOST likely lead to which of the following:
Answer
  • a. Rework and increased cost risk.
  • b. Absenteeism and decreased cost.
  • c. Increased inspections and decreased cost.
  • d. Reduced quality limits.

Question 20

Question
Which of these is an input to the Control Quality Process?
Answer
  • a. Manage Quality
  • b. Validated changes.
  • c. Deliverables
  • d. Change request.
Show full summary Hide full summary

Similar

The Flowering Plant and Photosynthesis
lalalucy13
Biology 1 Keeping Healthy Core GCSE
Chloe Roberts
Geography A2 case studies
A K
P4: Explaining motion
thegeekymushroom
Advanced Vocabulary Test for Creative Writing
ElliseG
Key Biology Definitions/Terms
jane zulu
GCSE REVISION TIMETABLE
rebekahanne11
Edexcel Additional Science Chemistry Topics 1+2
El Smith
Ancient China - Glossary of Terms
Ms M
OP doplnovaci otazky
Helen Phamova
BM 13 - COMENIUS, HERBART, DEWEY, HÖNIGSWALD
christoph wimmer