Cos 1

Description

Cos 1
Enrique Gomez
Quiz by Enrique Gomez, updated more than 1 year ago
Enrique Gomez
Created by Enrique Gomez over 5 years ago
6
0

Resource summary

Question 1

Question
Earned Value Management(EVM) is commonly used to :
Answer
  • a. Analysis of the value of the equipment that has been installed as of the status date.
  • b. Analysis of the sum of the labor costs, which have been incurred on the project to date.
  • c. A method of project performance measurement.
  • d. A method of measuring the amount of money that has been spent to date.

Question 2

Question
An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) is known as:
Answer
  • a. Parametric Estimating
  • b. Analogous Estimating
  • c. Bottom-up Estimating
  • d. Historical Analysis

Question 3

Question
Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with:?
Answer
  • a. Inadequacies in the original estimate
  • b. Anticipated but not certain events
  • c. Unanticipated events
  • d. Anticipated and certain events

Question 4

Question
Activity cost estimates are used as an input into which process??
Answer
  • a. Estimate Costs
  • b. Determine Budget
  • c. Cost Analysis
  • d. Control Costs

Question 5

Question
As a project manager, your BEST use of the project cost baseline would be to:?
Answer
  • a. Measure and monitor cost performance on the project.
  • b. Track approved changes.
  • c. Calculate team performance bonuses.
  • d. Measure and report on variable project costs.

Question 6

Question
An activity cost estimate includes all of the following resource categories EXCEPT:?
Answer
  • a. Labor
  • b. Materials
  • c. Equipment
  • d. Time shortages.

Question 7

Question
All of the following are true about estimate costs, EXCEPT:?
Answer
  • a. Are generally expressed in units of currency (dollars, euro, yen, etc.), although in some instances other units of measure, such as staff hours or staff days ares used.
  • b. The costs are estimated for all resources that will be charged to the project.
  • c. Information in the risk register should not be used to adjust cost estimates.
  • d. Cost estimates are quantitative assessments of the likely costs for resources required to complete project activities.

Question 8

Question
The Project Manager is in the process of estimate costs. What will he get?
Answer
  • a. The budget of the project
  • b. Basis of estimates, cost estimates and project documents updates
  • c. Cost estimates of the work packages
  • d. Entire costs of the deliverables

Question 9

Question
Analogous estimating:?
Answer
  • a. Integrated bottom-up estimating techniques with relevant statistical relationship to estimate the cost of the current project
  • b. Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project.
  • c. Is used most frequently in the later stages of a project.
  • d. Summarizes estimates for individual work packages to estimate the cost of the current project.

Question 10

Question
All of the following are required to establish cost baseline EXCEPT:?
Answer
  • a. Plan Resources of everything xxxxxx
  • b. Control Cost
  • c. Estimate Cost
  • d. Determine Budget
Show full summary Hide full summary

Similar

GCSE Maths Quiz
Andrea Leyden
SAT Sample Essay - Failure/ Success
nedtuohy
Creative Writing
amberbob27
Maths Revision- end of year test
hannahsquires
Coastal Landscapes
Chima Power
Key word flashcards
I M Wilson
Maths GCSE - What to revise!
livvy_hurrell
GCSE Maths: Statistics & Probability
Andrea Leyden
Whole Number Glossary L1
Lee Holness
Basic Korean Verbs
ASHISH AWALGAONKAR
1PR101 2.test - Část 3.
Nikola Truong