Rec 2

Description

Rec 2
Enrique Gomez
Quiz by Enrique Gomez, updated more than 1 year ago
Enrique Gomez
Created by Enrique Gomez over 5 years ago
8
0

Resource summary

Question 1

Question
Which of the following is NOT an input into Plan Resource Management??
Answer
  • a. Enterprise Environmental Factors
  • b. Roles and responsibilities
  • c. Organizational Process Assets
  • d. Project management plan

Question 2

Question
Which of the following is not a tool used in Develop Project Team??
Answer
  • a. Interpersonal and team skills.
  • b. Training.
  • c. Colocation
  • d. Empowerment.

Question 3

Question
The sponsor of a new strategic project ask you for an estimate of the total project budget for the corporate meeting next Friday. You collect some opinions from colleagues and a provider of a similar project developed last year. Which tool are you using?
Answer
  • a. Analogous estimating
  • b. Data analysis
  • c. Project Management Information System
  • d. Public databases

Question 4

Question
Which of the following is NOT a process of Resources Management??
Answer
  • a. Plan Resource Management.
  • b. Control Resources
  • c. Control Project team.
  • d. Develop Project Team.

Question 5

Question
Who manages the resources in a matrix organization??
Answer
  • a. Senior management
  • b. Functional managers
  • c. Project manager
  • d. Human resources

Question 6

Question
Which of the following is not true about a project’s ground rules??
Answer
  • a. Ground rules should be communicated to all team members.
  • b. Ground rules should be consistent across projects in an organization.
  • c. Ground rules should be clearly defined.
  • d. Ground rules define behavioral boundaries on a project.

Question 7

Question
Examples of experts judgment during Plan Resource Management are:
Answer
  • a. Evaluate the supplier performance.
  • b. Integrate the team with communication activities
  • c. Estimating lead times required for acquisition of wood and concrete, based on lesson learned and market conditions
  • d. Decide to change of a machine because it is non performing.

Question 8

Question
Which of the following is NOT true of team building??
Answer
  • a. Team agreement should be obtained on all major actions.
  • b. Team building requires role modeling on the part of the project manager.
  • c. Team building becomes less important as the project progresses.
  • d. Teamwork cannot be forced.

Question 9

Question
Which of the following is not likely a project resource for a software project??
Answer
  • a. Conference room near the team location
  • b. Project Manager
  • c. Maintenance operator
  • d. Computer programmer

Question 10

Question
Which of the following techniques produces the most lasting results??
Answer
  • a. Problem solve
  • b. Smooth
  • c. Compromise
  • d. Withdraw
Show full summary Hide full summary

Similar

Vocabulário Inglês Básico
miminoma
Causes, Practices, and Effects of World War 1
Emma Pettersen
GCSE Music (Edexcel) Quiz
corelledavis
Spanish connectives and a few key phrases
emdrakeley
Circle Theorems
I Turner
Cell Biology Chapter 2
Sheridyn11
AQA Biology B1 Questions
Bella Statham
Maths GCSE - What to revise!
livvy_hurrell
Innovative Uses of Technology
John Marttila
The Changing Natural Environment Part 2
R S