SAB8#130 Risk vs Workarounds
  1. Workaround
    1. A workaround is not a planned response because the problems being addressed were not anticipated ahead of time. Per the name, a “workaround” let’s you “work around” the problem. As soon as it is determined that there is an unanticipated problem, it needs to be addressed, researched and incorporated into the documentation of the project plan
    2. Risk
      1. Contingency plans are developed around those possible issues and they are completed before the threat takes place. These contingency plans should address the objective of the plan, the criteria for activating the contingency plan, the people and responsibilities involved, and the additional details required for implementation.
      Zusammenfassung anzeigen Zusammenfassung ausblenden

      ähnlicher Inhalt

      Unregelmäßige Verben Englisch
      Janine Egli
      Einstufungstest Italienisch Niveau A1.1
      SprachschuleAktiv
      Deutsche Redewendungen und Umgangssprache / Quiz 02 / deutschlernerblog.de
      deutschlernerblog.de
      Stimmungen in Englisch lernen
      Michelle Eichinger
      Epochen und Literaturströmungen für das Abitur 2016
      Laura Overhoff
      Sachversicherungen
      Christine Zehnder
      Anatomie - Begriffe
      Angela Peier
      Euro-FH // Zusammenfassung PEPS1
      Robert Paul
      Kommunikationssoziologie (KSOZ) Grimm 2017/18
      Benedikt Zöchling
      Vetie - Probefragen+Klausur Tierhaltung
      E. König
      Vetie Viro 2018
      Anna Nie