SAB9#64 Compression_Schedule_Project
  1. Fastracking
    1. This technique involves taking critical path activities that were originally planned in a series and doing them instead in parallel for some or all of their duration.
    2. Crashing
      1. This technique involves adding or adjusting resources in order to compress the schedule while maintaining the original project scope. Crasing, by definition, always results in increased costs, and may increase risk it trades time for money.
      Zusammenfassung anzeigen Zusammenfassung ausblenden

      ähnlicher Inhalt

      LEK 1-1
      tobifant
      Stochastik
      barbara91
      BKF C95 (Fragen der Ziffern 3a - 3g)
      Harald Koenig
      Ausgewählte Dramentheorien im Überblick
      Carolyn Li
      Oxford Academic Word List Sub1
      torsten fab
      MEWA
      Kathi P
      PR 2017/18
      Carmen Mai
      Vetie - Radiologie 2018 Teil 2
      Luca Russell
      AVO 2017
      steff Müller
      MS-1.3 Folienpaket 4
      Lukas Imwalle