SAB9#64 Compression_Schedule_Project
  1. Fastracking
    1. This technique involves taking critical path activities that were originally planned in a series and doing them instead in parallel for some or all of their duration.
    2. Crashing
      1. This technique involves adding or adjusting resources in order to compress the schedule while maintaining the original project scope. Crasing, by definition, always results in increased costs, and may increase risk it trades time for money.
      Zusammenfassung anzeigen Zusammenfassung ausblenden

      ähnlicher Inhalt

      Règlement et relance - Phrases - Chapitre 5
      Gaelle Bourgeois
      Biologie Zellbiologie
      racheltschan89
      Psych
      Mona Les
      Globalization – global challenges
      ExamTime Bewerter
      Mathe Abiturvorbereitung
      JuliaSt
      AOW - Psych
      Aydan Altuner
      OEKO Marius Ultimativ 2
      Marius Goconqr
      Kommunikationssoziologie (KSOZ) Grimm 2017/18
      Benedikt Zöchling
      METH QUANTI SS 2019
      Caroline Hannah
      Vetie Histopatho 2014
      Ann-Kathrin Riedel