SAB9# 63 Analysis Diagram Red

Beschreibung

pm Curso PM Mindmap am SAB9# 63 Analysis Diagram Red, erstellt von Juan Garcia am 25/02/2016.
Juan Garcia
Mindmap von Juan Garcia, aktualisiert more than 1 year ago
Juan Garcia
Erstellt von Juan Garcia vor fast 9 Jahre
30
0

Zusammenfassung der Ressource

SAB9# 63 Analysis Diagram Red
  1. Definition
    1. A diagramming technique to visualize the dependencies of the activities and calculate the total duration of the project.
    2. Dependence
      1. • (FS) Finish to Start: The start of the activity thus successor to the completion of the predecessor activity
        1. • (FF) Final Final: The completion of the successor activity depends upon the completion of the predecessor activity.
          1. • (SS) Star to Start The initiation of the successor activity depends upon the initiation of the predecessor activity.
            1. • (SF) Start to Finish: The completion of the successor activity depends upon the initiation of the predecessor activity.
            2. Characteristics:
              1. Each activity is represented by a box and only one
                1. Each frame has a number of unique activities
                  1. The activities are arranged in the order of the presidency to know when you start first
                    1. You can start an activity to finish the preceding
                      1. There may be concurrent activities
                      2. Concepts
                        1. • Predecessor Activity: Activity that precedes the successor activity
                          1. • successor Activity: Activity happens predecessor activities
                            1. • Critical Path: Path or going from start to finish and also takes longer compared to other routes
                              1. • Full Clearance: The additional time available to complete an activity, if all the above activities as early as possible and start the following latest
                                1. • free float; Is the additional time that may extend an activity without affecting the next start of any subsequent activity
                                  1. the critical chain is the sequence of precedences and dependent on resources that prevent a project, which is given limited resources, can be completed in less time terminal elements . If the resources of a project were always available in unlimited quantities , then the critical chain of a project would be equal to its critical path.
                                  2. Steps
                                    1. Define the project and prepare the work breakdown structure
                                      1. Development of relations between activities
                                        1. Draw the network connecting all activities
                                          1. Calculate the time of the longest path
                                            1. Using the network to help plan your schedule, you supervise and control the project
                                    2. Activities list
                                      Zusammenfassung anzeigen Zusammenfassung ausblenden

                                      ähnlicher Inhalt

                                      Einkaufsmarketing (Instrumente)
                                      Budd9r
                                      ABSOLUTISMUS - LUDWIG XIV
                                      Julian 1108
                                      Aufklärung und Sturm & Drang
                                      Cassibodua
                                      SMART Lernziele
                                      barbara91
                                      Unsere Erde - Sonnensystem, Klima, Erdschichten etc.
                                      rezension1
                                      EVA - Vorbereitung MC Teil
                                      hans urst
                                      Vetie - Pathologie Fragen aus dem A-Skript
                                      Fioras Hu
                                      PuKW - GESKO WERB
                                      Salome Jeong
                                      Vetie Radiologie VL-Fragen
                                      Carolina Heide
                                      Chirurgie Kleintiere Vetie
                                      Anne Käfer
                                      Factores de tensión y estrategias de potenciación
                                      NURY PAOLA DUEÑAS SIERRA