Zusammenfassung der Ressource
SAB9#118Tipos_de_Riesgos
- Threats and
Opportunities
- Risks are identified and managed starting in initiating and are continually kept
up-to-date or added to while the project is underway.
- Uncertainty
- The work that needs to be done, the cost, the
time, the quality needs, the communications
needs, etc., can be uncertain. The investigation
of uncertainties may help identify risks
- Risk Factors
- how likely
- impact or amount at stake)
- when
- how often
- Risk Appetites Tolerances and
Thresholds
Anmerkungen:
- These three terms each refer to the level of risk an individual or group is willing to accept.
- Risk appetite is a general, high-level
description of the acceptable level of risk
- the sponsor is willing to accept little risk
to the schedule on this project
- The term risk tolerance is more specific, as it
refers to a measurable amount of
acceptable risk
- In this case, our sponsor might be said to
be willing to accept schedule risk of up to
14 days on this project.
- A risk threshold is the specific point at
which risk becomes unacceptable.
- the sponsor will not accept a risk of the
schedule being delayed 15 days or longer
- Risk Averse