Zusammenfassung der Ressource
Contract Practice -
principles of contract law
- Types of FIDIC forms of
contract?
- Red Book
- Civils - Architect/ Emp. design
- Traditional
- Yellow Book
- M&E
- D&B
- e.g. water treat. plant
- Silver Book
- Turn key
- EPC
- e.g. pharmaceutical, Oil & Gas etc.
- Green Book
- Minor Wks
- Short Form
- Pink Book
- Multilateral Dev. Banks (MDB)
- Gold Book
- Design Build Operate (DBO)
- Orange Book
- Cond. for D&B & Turnkey
- White Book
- Consultancy services agreement
- Basic principle
- eng. employed as EA + Representative.
- Provisions
- Nom Subbies
- Settlement of disputes
- EOT
- LD's
- Contract split into 2 parts
- Part 1
- General applicability
- Part 2
- Optional Clauses specific 2 each project
- Different types of Stand. form
of contract
- FIDC
- International Federation of
Consulting Engineers
- JCT
- Joints Contract Tribunal
- NEC/ ECC
- New Engineering Contract/
Engineering & Construction
Contract
- ICE 7
- Institution of Civil Engineers
- PPC 2000
- Project partnering contract
- DOMI
- IChemE
- Institution of Chemical Engineers
- PPC 2000 & TPC 2005
- PPC 2000
- Implemented by Assoc.
Consulting Arch (ACA)
- 1st cont. 2 make partnering
a contractual framework.
- Sets out formal procedures
- Each member of
team becomes party
2 cont.
- Contract. obligations
- Multi-party contract
- Project Partnering Contract
- Born from Egan report
2000 (construction task
force)
- Used in single projects
- TPC 2005
- Term Partnering Contract
- procurement for term wks & services
- Differences between PPC & other Stnd form of contracts
- Team based approach
- integrated design/ supply & construction process (collaboration)
- Incentives - pain & gain
- Non adversarial problem resolution
- VE & VM - PPC recognises
- Core Group - operate early warning
systems 4 prob & review issues
early
- Legal Requirement of a
contract
- 1. offer & acceptance
- There must b an offfer and it must be accepted
- 2. Acceptance by the other party
- showing acceptance e.g. orally, writing or implied through conduct
- 3. Consideration of the offer
- is the feat. that distinguishes a bargain from a gift. it is the price that each party ask of the
other in return for entering into an agreement. Contract has to show that a price was paid
- 4. Intent to form a contract
- 5. Legality of contract
- 6. Capacity to make an agreement
- Assumptions in a
building Cont.
- contract is entire in legal sense
- contract with a 'break-clause' is not standard.
- Only one MC
- Contract price is more important than period.
- Client is contractually passive during construction
- Major UK Acts on construction sector
- Housing, Grants, Construction,
Regeneration Act 1996
- Updated: Local Democracy, Economic
Development and Construction Act 2009
- Scheme for Construction
Contracts Regulations 1998
- if the contrcact between 2 parties does not
comply with all req of HGCRA Act/no adj
provision agreed = Scheme 4 construction
contract default
- Contracts (right of 3rd party)
Act 1999
- Civil Procedural Rules 1999
- Arbitration Act 1996
- The Construction (Design and Management)
regulations - CDM 1994
- The Latent Damage Act 1986
- Unfair Contract Terms Act 1977
- Defective premises Act 1972
- Letter of Intent (LOI)
- Definition
- the expression in writing of a party's
present intention to enter into contract at
a future date.
- can be binding or non-binding
- Why is a LOI issued?
- obtain necessary approvals & permissions
- Anticipate delay in prep of a contract
- Need 2 obtain long lead in times for plant & equipment
- Common contract documents
- Conditions of Contract + amendments 2 stnd. forms
- Prelims
- Contract Sum analysis/ BQ/ Sch of wrks
- Dwgs, Spec, Sch, reports
- ext. building info.
- Any CDP elements
- ICE Conditions of Contract
- 7th form published in 1999
- Maj civils projects
- re-measure contract
- paid for actual work done
- no reference to contract sum
- rather tender price then contract price
- there is an ICE Minor Works
- Less than £100k & 6mths
- Contract between promoter & contractor
- Engineer has own contract
- no obligations/ rights in main
contract
- engineer performs
function of CA + QS
- Known as
Engineers
representative
- JCT
- Widely used and well know
- Main parts of JCT Contract
- Recitals
- Articles
- Contract Particulars
- Attestation
- Conditions - divided into 9 parts
- Schedules
- main types of JCT contracts
- SBC
- SBC/XQ
- Traditional
- Lump sum
- SBC/Q
- Traditional
- Adjustable
- SBC/AQ
- Traditional
- Re-measureable
- IFC
- Traditional
- Adjustable
- MW
- Traditional
- short duration, small , simple
- up to £150k
- short & easy
- Limited claim provisions
- no fluctuations
- Dwg/Spec & /or Work Sch
- When is it not suitable?
- client wants BQs
- Wks require named specialists
- Adjustable
- D&B
- D&B
- Lump Sum
- use?
- contractor resp. 4 D&B
- CDP form basis of project
- no mention of Architect or QS - EA
- IFC(D)
- D&B
- Lump Sum
- SBC (D)
- MW(D)
- D&B
- Lump Sum
- MPC
- D&B
- Lump Sum
- Use?
- significant in size & complexity
- Measured term contract
- use?
- maintainence/ minor wks undertaken reg basis
- agreed on sch of rates
- let on fixed or fluctuating basis
- break provisions for terminating early
- Agreement for Named/ Nominated Subbies
- management contract
- Construction Management Contract
- Roles and Responsibilities of parties
- Client
- different roles for different procurement routes
- Generally
- responsible 4 deciding what he wants as the finished product
- setting budget limits
- briefing consultants
- make sure design meets requirements
- Traditional Procurement
- contractually passive as most things rest with CA
- D&B procurement
- the client team is placed with the contractor
- gets advice from a EA
- Enter text here