T017 EOT

Beschreibung

T017 & T016 Mindmap am T017 EOT, erstellt von alison_patey0437 am 07/05/2013.
alison_patey0437
Mindmap von alison_patey0437, aktualisiert more than 1 year ago
alison_patey0437
Erstellt von alison_patey0437 vor mehr als 11 Jahre
143
0

Zusammenfassung der Ressource

T017 EOT
  1. DEFINITION
    1. Adjusts the completion date and relieves the contractors liability to pay liquidated damages for the period of the extension
    2. JCT
      1. JCT SBC Clauses 2.26 - 2.29
        1. PROCEDURE
          1. When delay is apparent/likely - MC write to CA to notify
            1. Notice should identify cause - related to RELEVANT EVENTS & length of delay
              1. Give any other info required from CA/arch
                1. CA/Arch must notify MC of decision in writing
                  1. either extending the completion date (stating the ampount if any i ddt form application) or confirming no EOT is granted
                  2. TIME PERIODS
                    1. CA/Arch has 12 wks from notification to decide on EOT
                      1. if less than 12wks to PC - CA should endevour to make a decision b4
                        1. CA/arch has 12wk after PC top review any previous EOT claims to award anything further
                      2. RELEVANT EVENTS
                        1. Events that entitle MC to EOT
                          1. 13 EVENTS
                            1. DIS SSA FSS VIA
                              1. Deferment of possession
                                1. Impediment by emp
                                  1. Suspension for non-payment
                                    1. Statutory Powers excercises from UK gov
                                      1. Adverse Weather
                                        1. Force majure
                                          1. Strike/ lock out
                                            1. Statutory Authority works
                                              1. Variations
                                                1. Instructions
                                                  1. Approx quants - inaccurate forecast
                                                2. REDUCTION IN EOT
                                                  1. RELEVANT OMISSION
                                                    1. you can reduce EOT if works have been omitted from the contract - notify the MC of each reduction
                                                    2. PRE-AGREE ADJUSTMENT
                                                      1. Agreement with emp and MC but Ca cannot fix a date earlier than the date for completion in contract particulars
                                                    3. ASSESMENT
                                                      1. CA has NO right to grant EOT for anything not related to RELEVANT EVENTS
                                                        1. Assess each delay on the contract date
                                                          1. CA can use contractors programme (not binding) the effect of progress is assessed in relation to the work being carried out at the time of the delaying event
                                                          2. CONCURRENT DELAYS
                                                            1. 2/more delaying events can happen simultaneously/overlap and its difficult to decide where the EOT award lies
                                                              1. where concurrent delays have two or more RELEVANT EVENTS it has be customary to grant the EOT to the dominant cause
                                                                1. judge each event on its merits
                                                                  1. tests for determining the prevailing Delay
                                                                    1. “but for”
                                                                      1. Devlin approach
                                                                        1. dominant cause
                                                                      2. PROGRAMME FLOAT
                                                                        1. No clear rule over who ow the programme float - generally belongs to the contractor
                                                                          1. The MC normally inc float in his programme 2 accommodate his risk items and also provide time for correcting mistakes THEREFORE the actual impact of delay should be considered
                                                                      3. ADVANTAGES OF EOT
                                                                        1. Relieves MC liability 4 LD 4 delay that they did not cause
                                                                          1. It enables another completion date to be set, which maintains thee employers ability to take liquidated damages if another delay occurs
                                                                          2. TIME IS AT LARGE
                                                                            1. No set completion date
                                                                              1. MC only obligation to finish the works in a reasonable time
                                                                                1. LD's cannot be levied
                                                                                  1. Emp would have to try and prove the MC had not completed in a reasonable time through courts
                                                                                  2. CULPABLE DELAY
                                                                                    1. MC delay is called 'culpable delay' when they go post the date for completion because they are culpably for LDS
                                                                                    Zusammenfassung anzeigen Zusammenfassung ausblenden

                                                                                    ähnlicher Inhalt

                                                                                    T017 Insurance
                                                                                    alison_patey0437
                                                                                    Contract Practice - Interim Valuations & Payment Privisions
                                                                                    alison_patey0437
                                                                                    Loss and Expense
                                                                                    alison_patey0437
                                                                                    Contract Practice JCT OVERVIEW
                                                                                    alison_patey0437
                                                                                    T017 Roles & Responsibilities of parties
                                                                                    alison_patey0437
                                                                                    T017 Termination & remedies for breaches outside the Contract
                                                                                    alison_patey0437
                                                                                    Changes to the Construction Act
                                                                                    alison_patey0437
                                                                                    Contract Practice - Performance security
                                                                                    alison_patey0437
                                                                                    T017 Letters of Intent
                                                                                    alison_patey0437
                                                                                    Conflict Avoidance
                                                                                    alison_patey0437
                                                                                    T017 L&AD
                                                                                    alison_patey0437