Anthony Schulmeister
Quiz von , erstellt am more than 1 year ago

Contains all questions and answers from the previous chapter exams (CH 1-10)

1728
1
0
Anthony Schulmeister
Erstellt von Anthony Schulmeister vor fast 7 Jahre
Schließen

Project Management Final CH 1-10

Frage 1 von 200

1

Identify the example that would not usually be considered a project.

Wähle eine der folgenden:

  • building a house

  • developing a computer software application program

  • hosting a wedding reception

  • assembly line manufacturing of automobiles

Erklärung

Frage 2 von 200

1

According to the authors, the prime objectives of project management are

Wähle eine der folgenden:

  • scope, cost, time

  • quality, scope, schedule

  • customer satisfaction, budget, schedule

  • cost, quality, customer satisfaction

Erklärung

Frage 3 von 200

1

In a conventional project lifecycle, as work progresses, uncertainty about the expected outcome should

Wähle eine der folgenden:

  • become a constant

  • decrease

  • increase

  • be fully removed

Erklärung

Frage 4 von 200

1

The attributes that characterize a project are

Wähle eine der folgenden:

  • purpose, repetition, inter-dependencies, consistency, uncertainty, conflict, and one¬time occurrence

  • life cycle, schedule, cost, uncertainty, independence, uniqueness, and purpose

  • resources, uniqueness, conflict, inter-dependencies, one-time occurrence, and finite duration,

  • purpose, life cycle, conflict, certainty, independence, performance, and finite duration

Erklärung

Frage 5 von 200

1

The "stretched-5" pattern observed during the project lifecycle, for the most part, is a result of the

Wähle eine der folgenden:

  • changing levels of resources used during successive stages of the project lifecycle

  • changing attitudes of the people who work in the project

  • difficulty in performing the individual activities of a project

  • principle that work expands to fill the allotted time

Erklärung

Frage 6 von 200

1

The desired outcomes or results of a project are called

Wähle eine der folgenden:

  • subgroups

  • work packages

  • subprojects

  • deliverables

Erklärung

Frage 7 von 200

1

Earned value is based on the concept that the percentage of project completion is closely correlated with

Wähle eine der folgenden:

  • the number of levels in the project

  • relevance of the project

  • cost or the use of resources

  • final assembly of the output

Erklärung

Frage 8 von 200

1

Which of the following is not one of the four dimensions of project success?

Wähle eine der folgenden:

  • opening new opportunities for the future

  • number of people working on the project

  • impact on the customer

  • business impact on the organization

Erklärung

Frage 9 von 200

1

The project to construct a highway is unique because

Wähle eine der folgenden:

  • the characteristics of terrain will be different for different segments

  • consistency of the concrete will vary for different segments

  • different types of laborers will be used to build various segments of the highway

  • different people manage different sections of the highway

Erklärung

Frage 10 von 200

1

Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources between project. This is an example of project

Wähle eine der folgenden:

  • bottleneck

  • breakdown

  • interdependencies

  • malfunctioning

Erklärung

Frage 11 von 200

1

When done properly, project management begins with

Wähle eine der folgenden:

  • stakeholder interviews

  • scope definition

  • the initial concept for the project

  • budget estimation

Erklärung

Frage 12 von 200

1

The chance that project processes or outcomes will not turn out as planned is called

Wähle eine der folgenden:

  • risk

  • projecting

  • effort

  • negative outcome

Erklärung

Frage 13 von 200

1

Having only partial or no information about the situation or outcomes is called

Wähle eine der folgenden:

  • uncertainty

  • risk

  • effort

  • cluelessness

Erklärung

Frage 14 von 200

1

Relations between organizational functions, where one function or task is dependent on others, are known as

Wähle eine der folgenden:

  • interdependencies

  • links

  • projects

  • tasks

Erklärung

Frage 15 von 200

1

The of the project team is a crucial but unstated element of ancillary trade-
offs that the project manager must consider.

Wähle eine der folgenden:

  • health

  • plan

  • task

  • effort

Erklärung

Frage 16 von 200

1

The project is generally credited with beginning the era of modern project
management

Wähle eine der folgenden:

  • Manhattan

  • Chicago

  • Great Wall of China

  • Egyptian pyramids

Erklärung

Frage 17 von 200

1

is a subset of a project consisting of work packages

Wähle eine der folgenden:

  • task

  • program

  • project

  • process

Erklärung

Frage 18 von 200

1

Projects are bound by the three objectives of scope, time, and cost. These are collectively referred to as the

Wähle eine der folgenden:

  • Triple Constraint

  • Triple Factors

  • Three Constraints

  • Triple Play

Erklärung

Frage 19 von 200

1

Individuals or groups with a special interest in a project are called

Wähle eine der folgenden:

  • stakeholders

  • project managers

  • leaders

  • directors

Erklärung

Frage 20 von 200

1

The production of weekly employment reports or the delivery of mail could be considered a

Wähle eine der folgenden:

  • project

  • non-project

  • quasi-projects

  • triple projects

Erklärung

Frage 21 von 200

1

Which of the following demonstrates the quality of flexibility required of a project selection model?

Wähle eine der folgenden:

  • It does not require special interpretation, data that are difficult to acquire, or excessive personnel.

  • It gives valid results within the range of conditions that the firm might experience.

  • It reflects the multiple objectives of both the firm and its managers.

  • It deals with situations both internal and external to the project.

Erklärung

Frage 22 von 200

1

The two basic types of project selection models identified in the text are

Wähle eine der folgenden:

  • biased and unbiased

  • numeric and nonnumeric

  • active and passive

  • numeric and qualitative

Erklärung

Frage 23 von 200

1

If a system is being updated due to operating necessity, the project was selected because

Wähle eine der folgenden:

  • the system is worth saving at any cost

  • the system is worth saving at the estimated cost of the project

  • the dimension of cost is not relevant to execution of the project

  • the cost overruns can be hidden in someone else's budget

Erklärung

Frage 24 von 200

1

The drawback of the ___________ model is that it fails to consider cash flows obtained once the initial investment has been recovered.

Wähle eine der folgenden:

  • payback period

  • average rate of return

  • discounted cash flow

  • profitability index

Erklärung

Frage 25 von 200

1

If the NPV for a project is < 0, it indicates that the project will

Wähle eine der folgenden:

  • report a profit loss

  • report a profit gain

  • fail to cover its required rate of return

  • fail to generate cash inflows

Erklärung

Frage 26 von 200

1

Scoring models are most often used to overcome this disadvantage of profitability models.

Wähle eine der folgenden:

  • The inability to account for the time value of money

  • The inability to account for project results beyond the payback period

  • The inability to account for multiple decision criteria

  • The inability to account for cash flow

Erklärung

Frage 27 von 200

1

Firms usually have two or more projects and this collection of projects is referred to as

Wähle eine der folgenden:

  • a portfolio

  • an initiation

  • a program

  • a stochastic model

Erklärung

Frage 28 von 200

1

A technique useful for developing numeric values that are equivalent to subjective, verbal measures of relative value is the

Wähle eine der folgenden:

  • Delphi system

  • expert system

  • portfolio

  • simulation

Erklärung

Frage 29 von 200

1

Which of the following is a type of numeric model?

Wähle eine der folgenden:

  • the sacred cow

  • the operating necessity

  • payback period

  • the product line extension

Erklärung

Frage 30 von 200

1

The _________ is the value of an opportunity foregone

Wähle eine der folgenden:

  • real option

  • profit

  • opportunity cost

  • revenue

Erklärung

Frage 31 von 200

1

The _________ is the interest rate set by an organization as the minimum acceptable rate of return for a project

Wähle eine der folgenden:

  • hurdle rate

  • acceptable rate

  • internal rate of return

  • net present value

Erklärung

Frage 32 von 200

1

In a project portfolio, _______________ projects have objectives or deliverables that are only
incrementally different in both product and process from existing offerings.

Wähle eine der folgenden:

  • breakthrough

  • R&D

  • platform

  • derivative

Erklärung

Frage 33 von 200

1

In a project portfolio, a project that involves a new technology or even a disruptive technology that is known to the industry would serve as an example of a project

Wähle eine der folgenden:

  • breakthrough

  • R&D

  • platform

  • derivitive

Erklärung

Frage 34 von 200

1

The set of documents submitted when evaluating a project is referred to as the

Wähle eine der folgenden:

  • project proposal

  • evaluation set

  • evaluation criteria

  • project manual

Erklärung

Frage 35 von 200

1

When the decision maker's information is not complete, he/she will have to make a decision under conditions of

Wähle eine der folgenden:

  • proof

  • uncertainty

  • management

  • risk mitigation

Erklärung

Frage 36 von 200

1

The discounted cash flow method determines the net present value of all cash flows by discounting them by the

Wähle eine der folgenden:

  • hurdle rate

  • acceptable rate

  • internal rate of return

  • net present value

Erklärung

Frage 37 von 200

1

Financial forecasts are reported as __________ financial statements.

Wähle eine der folgenden:

  • final

  • initial

  • pro forma

  • hypothetical

Erklärung

Frage 38 von 200

1

A project selection criteria that focuses on how well new products would fit the firm's existing product line would be

Wähle eine der folgenden:

  • sustainability

  • comparative benefit model

  • production line extension

  • operating necessity

Erklärung

Frage 39 von 200

1

According to research by Sanchez and Robert (2010), which of the following is not a reason why strategic benefits may be difficult to appraise?

Wähle eine der folgenden:

  • Not immediately realized

  • Difficult to quantify

  • May be confounded with other factors

  • Easy to plan for when they occur

Erklärung

Frage 40 von 200

1

________ is a modeling technique for emulating a process, usually conducted a
considerable number of times to understand the process better and measure its outcomes under different policies.

Wähle eine der folgenden:

  • Simulation

  • Project management

  • Projectizing

  • Modeling

Erklärung

Frage 41 von 200

1

According to the authors, the analytic method, when applied to systems, focuses on

Wähle eine der folgenden:

  • assembling the components of a system into an integrated package

  • building an array of individually designed and manufactured components

  • calculating the cost and schedule requirements

  • dividing the components of a system into smaller and smaller elements

Erklärung

Frage 42 von 200

1

The ideal project manager should be

Wähle eine der folgenden:

  • a direct, technical supervisor knowledgeable in the technology of the process being used

  • both generalist/facilitator and have a high level of technical competence in the science of the project

  • a facilitator and specialist with technical credibility

  • a technical specialist competent in principles of robust design

Erklärung

Frage 43 von 200

1

The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the _______ functions.

Wähle eine der folgenden:

  • technical and managerial

  • schedule and cost

  • performance and schedule

  • cost and performance

Erklärung

Frage 44 von 200

1

According to the authors the project manager should be more skilled at

Wähle eine der folgenden:

  • general management

  • technology

  • synthesis

  • analysis

Erklärung

Frage 45 von 200

1

The project manager needs _______ credibility.

Wähle eine der folgenden:

  • technical and personal

  • administrative and personal

  • technical and administrative

  • technical and financial

Erklärung

Frage 46 von 200

1

Projects are conducted in four important environments. They are

Wähle eine der folgenden:

  • economic, political, legal, and sociotechnical

  • internal, external, transitional, and multicultural

  • routine, unique, fast-paced, and complex

  • profit, not for profit, government, and industry

Erklärung

Frage 47 von 200

1

According to the authors, the key to coping with uncertainty at the end of a project (a common obstacle for project managers) is

Wähle eine der folgenden:

  • discipline

  • communication

  • planning

  • supervision

Erklärung

Frage 48 von 200

1

During the buildup phase, the project goals, in order of importance, are

Wähle eine der folgenden:

  • schedule, scope, cost

  • cost, schedule, scope

  • schedule, cost, scope

  • cost, scope, schedule

Erklärung

Frage 49 von 200

1

Resources initially budgeted for a project are frequently _________ for the task, partly because of natural optimism by the proposer about how many resources are needed.

Wähle eine der folgenden:

  • sufficient

  • delayed

  • insufficient

  • hindrances

Erklärung

Frage 50 von 200

1

Most of the time spent by a project manager is spent

Wähle eine der folgenden:

  • attending technical workshops

  • overseeing the workforce

  • filing paperwork

  • coordinating and communicating

Erklärung

Frage 51 von 200

1

11. The functional manager uses the ________ approach and the PM uses the ________ approach

Wähle eine der folgenden:

  • systems; analytic

  • numerical; nonnumeric

  • analytic; systems

  • nonnumeric; numerical

Erklärung

Frage 52 von 200

1

The project manager's responsibility to the project and to the client is met by ensuring that the _______ of the project is preserved in spite of conflicting demands made by stakeholders.

Wähle eine der folgenden:

  • management

  • integrity

  • analysis

  • synthesis

Erklärung

Frage 53 von 200

1

During the final or phaseout stage of the project lifecycle, ___________ is the dominant goal of many project managers.

Wähle eine der folgenden:

  • schedule

  • cost

  • scope

  • quality

Erklärung

Frage 54 von 200

1

The structure of a society is determined by its

Wähle eine der folgenden:

  • institutions

  • wages

  • jobs

  • enemies

Erklärung

Frage 55 von 200

1

Which of the following is not a phase in the Tuckman ladder?

Wähle eine der folgenden:

  • forming

  • defining

  • norming

  • mourning

Erklärung

Frage 56 von 200

1

The _________ is a person who spearheads an idea or action and sells it throughout the organization.

Wähle eine der folgenden:

  • stakeholder

  • champion

  • interviewer

  • coach

Erklärung

Frage 57 von 200

1

The ______________ is an alternative action if the expected result fails to materialize.

Wähle eine der folgenden:

  • trade-off

  • system plan

  • feedback

  • contingency plan

Erklärung

Frage 58 von 200

1

The __________ represents everything outside the system that delivers inputs or
receives outputs from the system.

Wähle eine der folgenden:

  • environment

  • feedback

  • culture

  • system

Erklärung

Frage 59 von 200

1

The __________ is the "corporate culture" within the organization, or even within the
project

Wähle eine der folgenden:

  • cultural anomaly

  • microculture

  • multiculture

  • interfirm culture

Erklärung

Frage 60 von 200

1

The project manager makes a ___________ by allowing one aspect of the project to get
worse in return for allowing another aspect of the project to get better.

Wähle eine der folgenden:

  • decision

  • turnaround

  • trade-off

  • chart

Erklärung

Frage 61 von 200

1

A party to a conflict will usually be satisfied when the level of frustration has been

Wähle eine der folgenden:

  • increased by the domination of the other party

  • lowered to the point where no action against the other party is contemplated

  • lowered because the party realizes the hopelessness of continuing the conflict

  • eliminated because the party has surrendered to the other party

Erklärung

Frage 62 von 200

1

Most of the conflicts that involve the organization and outsiders have to do with

Wähle eine der folgenden:

  • interpersonal differences

  • cultural differences and status differences

  • technical differences

  • property rights and contractual obligations

Erklärung

Frage 63 von 200

1

During project formation, the organizational structure selected will have a major impact on the ways in which conflicts are handled. Lack of clarity about the relative power/influence/authority of the PM and the functional managers is a major component of all conflicts involving

Wähle eine der folgenden:

  • contractual obligations

  • property rights

  • budgeting

  • resource allocation, and scheduling

Erklärung

Frage 64 von 200

1

If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the

Wähle eine der folgenden:

  • earliest due date

  • fastest completion time

  • biggest revenue stream

  • lowest cost to complete

Erklärung

Frage 65 von 200

1

During project build-up, the project should move from a general concept to

Wähle eine der folgenden:

  • implementation of plans

  • a highly detailed set of plans

  • a project charter

  • a project contract

Erklärung

Frage 66 von 200

1

During project build-up, if the project is independent and standalone, the project manager seeks a commitment of __________ from the functional departments.

Wähle eine der folgenden:

  • work

  • materials

  • people

  • budgets

Erklärung

Frage 67 von 200

1

During project build-up, if the project is functionally tied down, the project manager seeks a commitment of _________ from the functional departments.

Wähle eine der folgenden:

  • work

  • materials

  • people

  • budgets

Erklärung

Frage 68 von 200

1

Personality conflicts during project phase-out are often caused by

Wähle eine der folgenden:

  • the absence of deadlines

  • the influx of newer technology

  • pressure to complete the project and anxiety about leaving the project

  • distribution of expenses charged to the project

Erklärung

Frage 69 von 200

1

According to the authors, the nature of negotiation as it applies to project management is the realization that few of the conflicts arising in projects have to do with

Wähle eine der folgenden:

  • whether or not the task will be done

  • the precise design of the deliverable

  • how the design will be achieved

  • who will do the work, when, and at what cost

Erklärung

Frage 70 von 200

1

When dealing with conflict between parties, it is recommended that one _______ in order to avoid the conflict becoming interpersonal.

Wähle eine der folgenden:

  • avoid the situation

  • define the substantive problem

  • leisurely discuss the issue

  • focus on interests

Erklärung

Frage 71 von 200

1

Partnering is an attempt to _________ the risk associated with sub-contracting.

Wähle eine der folgenden:

  • mitigate

  • Increase

  • absorb

  • allow

Erklärung

Frage 72 von 200

1

_________ is the process which begins when one party perceives that the other has frustrated, or is about to frustrate, some concern of his.

Wähle eine der folgenden:

  • conflict

  • happiness

  • contentment

  • utility

Erklärung

Frage 73 von 200

1

According to the authors, the favored technique for resolving conflict is

Wähle eine der folgenden:

  • negotiation

  • mitigation

  • avoidance

  • collaboration

Erklärung

Frage 74 von 200

1

The process through which two or more parties seek an acceptable rate of exchange for items they own or control is called

Wähle eine der folgenden:

  • negotiation

  • mitigation

  • compromising

  • collaboration

Erklärung

Frage 75 von 200

1

During the early program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to

Wähle eine der folgenden:

  • cost

  • schedules

  • scope

  • quality

Erklärung

Frage 76 von 200

1

During the main program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to

Wähle eine der folgenden:

  • cost

  • schedules

  • scope

  • quality

Erklärung

Frage 77 von 200

1

Toward the end of the project lifecycle, Thamhain et at say that conflict intensity is the greatest with respect to

Wähle eine der folgenden:

  • cost

  • schedules

  • scope

  • quality

Erklärung

Frage 78 von 200

1

Negotiating to a(n) __________ solution is the key to conflict resolution in project management.

Wähle eine der folgenden:

  • win-lose

  • win-win

  • avoidance

  • confrontation

Erklärung

Frage 79 von 200

1

The total level of conflict in the project lifecycle is highest during the _________ stage

Wähle eine der folgenden:

  • closing

  • main program

  • project build-up

  • project formation

Erklärung

Frage 80 von 200

1

The ___________ approach to negotiation aims to achieve a win-win result.

Wähle eine der folgenden:

  • principled

  • posititional

  • stakeholder

  • paretto

Erklärung

Frage 81 von 200

1

If the project manager controls when and what people do while the functional managers control who will be assigned to the project and what technology will be used, the ______organizational form is probably being used.

Wähle eine der folgenden:

  • projectized

  • pure project

  • matrix

  • weak project

Erklärung

Frage 82 von 200

1

In the systems approach to design, one organization would have to take responsibility for

Wähle eine der folgenden:

  • manufacturing everything in the system

  • the integrity of the project design

  • the integrity of the subcontractors

  • product warranties

Erklärung

Frage 83 von 200

1

The process of dealing with uncertainties in projects that may affect the project for better or for worse has come to be known as

Wähle eine der folgenden:

  • scope management

  • risk management

  • quality management

  • procurement management

Erklärung

Frage 84 von 200

1

A common objective of an organization's PM is often created by organizations to

Wähle eine der folgenden:

  • establish consistent project management standards and methods

  • deal with technological obsolescence

  • train process managers

  • administer application software

Erklärung

Frage 85 von 200

1

A major purpose of the project management office should be to serve as

Wähle eine der folgenden:

  • the central location for all clerical support

  • the critical disaster recovery support

  • a link between strategic management and project management

  • maintenance for the project management library

Erklärung

Frage 86 von 200

1

This member of the project team is in charge of product design and development and is responsible for functional analysis, specifications, drawings, cost estimates, quality/reliability, engineering changes, and documentation

Wähle eine der folgenden:

  • systems architect

  • manufacturing engineer

  • project controller

  • support services manager

Erklärung

Frage 87 von 200

1

This member of the project team is responsible for the efficient production of the product of the process, including the manufacturing engineering, design and production of tooling, production scheduling, and other production tasks

Wähle eine der folgenden:

  • project engineer

  • development engineer

  • contract administrator

  • support services manager

Erklärung

Frage 88 von 200

1

This person is responsible for the installation, testing, and support of the product (process) once its engineering is complete.

Wähle eine der folgenden:

  • development engineer

  • systems architect

  • test engineer

  • project controller

Erklärung

Frage 89 von 200

1

One of the main technical problems faced by the project manager is meeting ________ without compromising performance.

Wähle eine der folgenden:

  • supplier's targets

  • schedule and cost goals

  • technical specifications

  • cost and conflict goals

Erklärung

Frage 90 von 200

1

A major advantage of using a _________ placement for a project is that individual
experts can be utilized by many different projects.

Wähle eine der folgenden:

  • standard

  • virtual

  • projectized

  • functional

Erklärung

Frage 91 von 200

1

Virtual teams, when composed, should consist of "boundary spanners" who number about one in every _________ team members

Wähle eine der folgenden:

  • 6-7

  • 8-12

  • 10-20

  • 25-30

Erklärung

Frage 92 von 200

1

When a firm engages in a large number of similar projects, the ___________ organizational form is apt to be preferred.

Wähle eine der folgenden:

  • pure project

  • partial matrix

  • functional

  • mixed matrix

Erklärung

Frage 93 von 200

1

When the standard departments of the organization represent individual disciplines such as engineering, marketing, purchasing, and so on, the organization follows

Wähle eine der folgenden:

  • projectized management

  • matrixed management

  • functional management

  • mixed management

Erklärung

Frage 94 von 200

1

The firm or organization within which the project is being conducted is known as the

Wähle eine der folgenden:

  • parent organization

  • consulting firm

  • project team

  • stakeholder company

Erklärung

Frage 95 von 200

1

______________ engineering refers to the use of a design team that includes design and manufacturing engineers as well as staff from other relevant areas of the business.

Wähle eine der folgenden:

  • Concurrent

  • Alignment

  • Matrix

  • Social

Erklärung

Frage 96 von 200

1

The _________ is a basic project document that describes all the work that must be done to complete the project and forms the basis for costing, scheduling, and work

Wähle eine der folgenden:

  • WBS

  • OBS

  • PMO

  • project charter

Erklärung

Frage 97 von 200

1

The approach to organizing that includes both functions (disciplines) and projects in its hierarchy is known as the

Wähle eine der folgenden:

  • mixed organization

  • functional organization

  • projectized organization

  • matrix organization

Erklärung

Frage 98 von 200

1

This person's task is the efficient production of the product or process the project engineer has designed, including responsibility for manufacturing engineering, design and production of code, unit testing, production scheduling, and other production tasks.

Wähle eine der folgenden:

  • test engineer

  • contract administrator

  • development engineer

  • systems architect

Erklärung

Frage 99 von 200

1

TQM and Six Sigma are good examples of ____________ programs

Wähle eine der folgenden:

  • participative

  • exclusive

  • frequency

  • inclusive

Erklärung

Frage 100 von 200

1

If both functional and projectized divisions coexist in a firm, this would result in the __________ organizational structure.

Wähle eine der folgenden:

  • composite

  • objective

  • encompassing

  • free-form

Erklärung

Frage 101 von 200

1

The _________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task.

Wähle eine der folgenden:

  • resource histogram

  • linear responsibility chart

  • project team directory

  • scope management plan

Erklärung

Frage 102 von 200

1

The success of the project launch meeting is dependent on the existence of

Wähle eine der folgenden:

  • a project charter

  • the project's scope statement

  • a well-defined set of objectives for the project

  • project planning templates

Erklärung

Frage 103 von 200

1

This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.

Wähle eine der folgenden:

  • overview

  • objectives

  • general approach

  • contractual aspects

Erklärung

Frage 104 von 200

1

This project plan element should include profit and competitive goals as well as technical goals.

Wähle eine der folgenden:

  • overview

  • objectives

  • general approach

  • contractual aspects

Erklärung

Frage 105 von 200

1

The _______ of a project includes the objectives of the project as well as the time and cost required to complete the project to the customer's satisfaction.

Wähle eine der folgenden:

  • scope

  • change order

  • outcome

  • purpose

Erklärung

Frage 106 von 200

1

RACI stands for

Wähle eine der folgenden:

  • responsive, accountable, consult, inform

  • responsible, accountable, consult, inform

  • responsive, accountable, consult, integrate

  • responsible, admissible, consult, integrate

Erklärung

Frage 107 von 200

1

The set of physical elements required to build a project is called the

Wähle eine der folgenden:

  • bill of materials

  • deliverable

  • milestone list

  • work statement

Erklärung

Frage 108 von 200

1

___________ is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization. Typically, the upper level sets the objectives for the next lower level.

Wähle eine der folgenden:

  • Strategic planning

  • Organizational planning

  • Hierarchical planning

  • Agile planning

Erklärung

Frage 109 von 200

1

The major tool that a project manager uses during the planning phase is called the

Wähle eine der folgenden:

  • WBS

  • change request

  • scope statement

  • project plan

Erklärung

Frage 110 von 200

1

___________is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project

Wähle eine der folgenden:

  • Scope reference

  • Scope creep

  • Effectiveness

  • Hierarchical planning

Erklärung

Frage 111 von 200

1

_______________ is a visual approach that closely mirrors how the human brain records and stores information that can help tap the creative potential of the entire project team

Wähle eine der folgenden:

  • WBS generation

  • Project planning

  • Risk response planning

  • Mind mapping

Erklärung

Frage 112 von 200

1

When using a WBS, all of the work should roll up to the next level such that no extra work is required. This is referred to as the

Wähle eine der folgenden:

  • Development rule

  • All-inclusive rule

  • 100% rule

  • WBS rule

Erklärung

Frage 113 von 200

1

For projects that are constantly changing, the __________ methodology is recommended

Wähle eine der folgenden:

  • waterfall

  • agile

  • adaptable

  • organic

Erklärung

Frage 114 von 200

1

Having key stakeholders involved early in the project tends to

Wähle eine der folgenden:

  • increase communication errors

  • increase project risk

  • create buy-in

  • create more problems than it is worth

Erklärung

Frage 115 von 200

1

When using the mind mapping process, you should designate one team member as the ___________ to ensure that all team members are involved and contributing, and to ensure that team members are focusing on the work that must be done.

Wähle eine der folgenden:

  • planner

  • facilitator

  • contractor

  • manager

Erklärung

Frage 116 von 200

1

A useful tool for facilitating the management of changes to a project's scope is the

Wähle eine der folgenden:

  • requirements traceability matrix

  • WBS

  • project charter

  • mind map

Erklärung

Frage 117 von 200

1

A project manager must ___________ as a type of risk response planning in order to soften the danger of a threat by reducing the likelihood that it will occur or by reducing its impact if it does occur.

Wähle eine der folgenden:

  • avoid

  • transfer

  • accept

  • mitigate

Erklärung

Frage 118 von 200

1

The ____________ is a list of the project activities with major activities broken down into subactivities.

Wähle eine der folgenden:

  • linear responsibility chart

  • PCMCIA

  • activity prioritization

  • WBS

Erklärung

Frage 119 von 200

1

The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called

Wähle eine der folgenden:

  • procurement management

  • integration management

  • vertical management

  • matrix management

Erklärung

Frage 120 von 200

1

This element of the project plan contains a brief description of the procedure to be followed in monitoring, collecting, storing, and evaluating the history of the project

Wähle eine der folgenden:

  • schedule

  • resources

  • personnel

  • evaluation methods

Erklärung

Frage 121 von 200

1

If a project budget is under funded, it will often

Wähle eine der folgenden:

  • stimulate increased performance

  • improve utilization of resources

  • frustrate committed stakeholders

  • reduce costs

Erklärung

Frage 122 von 200

1

The project's budget should

Wähle eine der folgenden:

  • associate resource use with the achievement of organizational goals

  • allow funds to be spent without linkage to achievement

  • not reflect the timing of expenses associated with the use of resources

  • never be changed during project execution

Erklärung

Frage 123 von 200

1

In order to develop a budget, the PM must forecast

Wähle eine der folgenden:

  • the resources required

  • when resources will be needed

  • the cost of resources

  • All of the above

Erklärung

Frage 124 von 200

1

A work element whose cost is fully developed would

Wähle eine der folgenden:

  • exclude the cost of labor and resources

  • include only the profit and direct costs

  • exclude the cost of special machinery and overheads

  • include direct costs plus overhead and G&A charges

Erklärung

Frage 125 von 200

1

The traditional organizational budget is

Wähle eine der folgenden:

  • category-oriented

  • project-oriented

  • program-oriented

  • project-oriented or program-oriented

Erklärung

Frage 126 von 200

1

__________ budgeting allows income and expenditures to be aggregated across projects.

Wähle eine der folgenden:

  • Category-oriented

  • Activity-oriented

  • Project-oriented

  • Expense-oriented

Erklärung

Frage 127 von 200

1

The authors identify ____________ estimation errors as the two types of generic estimation errors.

Wähle eine der folgenden:

  • small and large

  • random and planned

  • certain and uncertain

  • random and biased

Erklärung

Frage 128 von 200

1

The pattern of deviations in cost and usage used for exception reporting to management is called

Wähle eine der folgenden:

  • simulations

  • assumptions

  • variances

  • summaries

Erklärung

Frage 129 von 200

1

___________ costs vary with output.

Wähle eine der folgenden:

  • general and administrative

  • overhead

  • direct

  • indirect

Erklärung

Frage 130 von 200

1

Unless the project manager is familiar with the firm's ______________ it will be very difficult to exercise budget control.

Wähle eine der folgenden:

  • accounting system

  • budget plans

  • marketing procedure

  • cost accounting

Erklärung

Frage 131 von 200

1

The __________ form of budgeting has the advantage of using individuals closer to the work to provide estimates of resource requirements.

Wähle eine der folgenden:

  • top-down budgeting

  • work element costing

  • bottom-up budgeting

  • iterative budgeting

Erklärung

Frage 132 von 200

1

The ___________ charge is composed of the costs of senior management, the various data functions, and any other expenses not included in overhead. Often, these charges are a fixed percentage of either the direct costs or the total of all direct and indirect costs.

Wähle eine der folgenden:

  • salary

  • project management

  • ethical

  • G&A

Erklärung

Frage 133 von 200

1

Each time the output doubles, the worker hours per unit decrease to a fixed percentage of their previous value. That percentage is called the ___________ rate.

Wähle eine der folgenden:

  • inflation

  • hurdle

  • interest

  • learning

Erklärung

Frage 134 von 200

1

Suppose that a person requires 60 minutes to complete a work element on the first attempt. On the second attempt, the work element is completed in 48 minutes. The learning rate for this person is _________% for this work element

Wähle eine der folgenden:

  • 80

  • 60

  • 70

  • 120

Erklärung

Frage 135 von 200

1

_____________ relies on well-known statistical correlations between various factors such as the total cost of a house relative to the square feet of living area.

Wähle eine der folgenden:

  • Parametric estimating

  • Statistical equivalence

  • Bottom-up estimating

  • Top-down estimating

Erklärung

Frage 136 von 200

1

A budget strategy that is based on collecting the judgments and experiences of top and middle managers is referred to as the ___________ approach or method.

Wähle eine der folgenden:

  • parametric estimating

  • statistical equivalence

  • bottom-up estimating

  • top-down estimating

Erklärung

Frage 137 von 200

1

________________ are where the defined responses to the risks are detailed, but their amounts are not
yet precisely known.

Wähle eine der folgenden:

  • Known-unknowns

  • Unknown-knowns

  • Known-knowns

  • Unknown-unknowns

Erklärung

Frage 138 von 200

1

Unknown-unknowns are not part of the baseline budget and are referred to as

Wähle eine der folgenden:

  • management reserves

  • contingency reserves

  • PMBOK reserves

  • Buffered reserves

Erklärung

Frage 139 von 200

1

The advantage of the ____________ process is that it is generally associated with participative management

Wähle eine der folgenden:

  • bottom-up

  • top-down

  • Murphy's

  • Efficient

Erklärung

Frage 140 von 200

1

______________ issues are present when bidders "low-ball" a bid or when some bidders get a "last look."

Wähle eine der folgenden:

  • Ethical

  • Strategic

  • Efficient

  • Effective

Erklärung

Frage 141 von 200

1

The authors recommend preparing a schedule for each

Wähle eine der folgenden:

  • work package in the WBS

  • task in the WBS

  • major task level in the WBS

  • project that has a WBS

Erklärung

Frage 142 von 200

1

In the AOA network, circles depict

Wähle eine der folgenden:

  • networks

  • events

  • logical dependencies

  • dummy activities

Erklärung

Frage 143 von 200

1

The shortest time in which the entire network can be completed is referred to as the

Wähle eine der folgenden:

  • critical time of the network

  • real duration of the network

  • elapsed time of the network

  • slack time of the network

Erklärung

Frage 144 von 200

1

A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a

Wähle eine der folgenden:

  • start to finish dependency

  • finish to start dependency

  • finish to finish dependency

  • start to start dependency

Erklärung

Frage 145 von 200

1

A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a

Wähle eine der folgenden:

  • start to finish dependency

  • finish to start dependency

  • finish to finish dependency

  • start to start dependency

Erklärung

Frage 146 von 200

1

The difference between the late start and early start for an activity is called its

Wähle eine der folgenden:

  • critical path

  • task

  • progress

  • float

Erklärung

Frage 147 von 200

1

A(n) __________ is the conversion of the project work breakdown structure into an operating timetable.

Wähle eine der folgenden:

  • chart

  • application

  • crash

  • schedule

Erklärung

Frage 148 von 200

1

A(n) _________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete

Wähle eine der folgenden:

  • milestone

  • activity

  • node

  • path

Erklärung

Frage 149 von 200

1

The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical sequence and represented by arcs and nodes is called a

Wähle eine der folgenden:

  • network

  • critical path

  • path

  • crashed path

Erklärung

Frage 150 von 200

1

In a network, if the delay of an activity will delay completion of the project, the activity is called a(n)

Wähle eine der folgenden:

  • valuable

  • efficient

  • critical

  • noteworthy

Erklärung

Frage 151 von 200

1

In AOA networks, an activity of zero duration is called a(n)

Wähle eine der folgenden:

  • dummy activity

  • critical

  • important

  • critical activity

Erklärung

Frage 152 von 200

1

The _____________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.

Wähle eine der folgenden:

  • PERT

  • timeline

  • critical

  • Gantt

Erklärung

Frage 153 von 200

1

A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n)

Wähle eine der folgenden:

  • milestone

  • anniversary

  • node

  • dummy activity

Erklärung

Frage 154 von 200

1

In AON diagrams, a(n) ________________ is a point where one or more lines (arrows) begin or terminate, commonly used for depicting an event or activity.

Wähle eine der folgenden:

  • activity

  • path

  • node

  • arc

Erklärung

Frage 155 von 200

1

______________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.

Wähle eine der folgenden:

  • trade-off

  • synergy

  • barter limit

  • limiting quantity

Erklärung

Frage 156 von 200

1

A _____________ is a combination of interrelated activities and events depicted with arcs and nodes.

Wähle eine der folgenden:

  • linked plan

  • chain of events

  • critical chain

  • network

Erklärung

Frage 157 von 200

1

____________ law suggests that work expands to fill the allotted time.

Wähle eine der folgenden:

  • Parkinson's

  • Murphy's

  • Brooks'

  • Federal

Erklärung

Frage 158 von 200

1

In application, PERT has primarily been used for

Wähle eine der folgenden:

  • construction projects

  • manufacturing projects

  • industrial projects

  • research and development projects

Erklärung

Frage 159 von 200

1

The authors define _________ as the time an activity can be delayed without affecting the start time of any successor activity

Wähle eine der folgenden:

  • free slack

  • total slack

  • project slack

  • overhead slack

Erklärung

Frage 160 von 200

1

__________ is one possible way to check the nature and impacts of interactions between probabilistic paths in a network.

Wähle eine der folgenden:

  • simulation

  • extrapolation

  • guessing

  • probabilistic time estimates

Erklärung

Frage 161 von 200

1

If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will

Wähle eine der folgenden:

  • not be necessary to crash any activities in projects

  • be necessary to crash the last few activities of most projects

  • be completed on time and within budget

  • be completed as per schedule

Erklärung

Frage 162 von 200

1

Assume two activities, printing and binding. Printing is a predecessor of binding. If printing is _______, then binding will start late by whatever amount of lateness is bequeathed to it by printing.

Wähle eine der folgenden:

  • necessary

  • early

  • late

  • time-neutral

Erklärung

Frage 163 von 200

1

________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.

Wähle eine der folgenden:

  • Resource loading

  • Resource leveling

  • Scope loading

  • Resource succeeding

Erklärung

Frage 164 von 200

1

A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources

Wähle eine der folgenden:

  • scope constrained

  • time constrained

  • resource constrained

  • system constrained

Erklärung

Frage 165 von 200

1

One of the problems that Goldratt observed was that if an activity has slack time, the task might become delayed until the slack is removed. This is referred to as

Wähle eine der folgenden:

  • Goldratt's Law

  • Murphy's Law

  • the delay game

  • the student syndrome

Erklärung

Frage 166 von 200

1

The points between the extreme points of the relationship between time use and resource use represent

Wähle eine der folgenden:

  • time constrained projects

  • resource constrained projects

  • alternative trade-offs between time and resources

  • a non-feasible solution space of trade-off alternatives related to time and resource use

Erklärung

Frage 167 von 200

1

The _________ technique overlaps the design and build phases of a project to expedite its completion.

Wähle eine der folgenden:

  • crashing

  • fast-tracking

  • leading

  • blitzing

Erklärung

Frage 168 von 200

1

Most heuristic solution methods start with the _____________ and analyze resource usage period by period, resource by resource.

Wähle eine der folgenden:

  • GERT schedule

  • Gantt chart

  • PERT/CPM schedule

  • Master schedule

Erklärung

Frage 169 von 200

1

The use of ______________ activity time estimates may reduce the chance that crashing the
project will be needed.

Wähle eine der folgenden:

  • one probabilistic

  • two probabilistic

  • three probabilistic

  • four probabilistic

Erklärung

Frage 170 von 200

1

The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are

Wähle eine der folgenden:

  • probabillistic

  • crashed

  • normal

  • dynamic

Erklärung

Frage 171 von 200

1

With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.

Wähle eine der folgenden:

  • in-process inventory

  • schedule slippage

  • resource utilization

  • management delay

Erklärung

Frage 172 von 200

1

If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are

Wähle eine der folgenden:

  • D = 6w

  • W = 6d

  • D = 8d

  • W = 8d

Erklärung

Frage 173 von 200

1

The principal reason why a project manager is surprised by resource constraints on a project is the failure to include _________ in risk identification activities.

Wähle eine der folgenden:

  • resource availability

  • resource cost

  • resource mobility

  • resource skill

Erklärung

Frage 174 von 200

1

Which of the following describes a situation where priorities are assigned to activities according to some rule not associated with task length, slack, or resource requirements?

Wähle eine der folgenden:

  • student's syndrome

  • arbitrary

  • most successors

  • most resources

Erklärung

Frage 175 von 200

1

The two fundamental approaches to constrained allocation problems are

Wähle eine der folgenden:

  • heuristic approaches and rules of thumb

  • linear programming approaches and optimization models

  • heuristic approaches and optimization models

  • goal programming and trial and error

Erklärung

Frage 176 von 200

1

When crashing a project, our first task is to develop

Wähle eine der folgenden:

  • a table or graph of the cost of a project as a function of the project's possible completion dates

  • a schedule that shows the risks associated with each activity in the project

  • a list that shows the activities and the events of a project without referring to the costs

  • a table showing the noncritical activities and the cost associated with each of those activities

Erklärung

Frage 177 von 200

1

In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual

Wähle eine der folgenden:

  • duration

  • slack

  • float

  • buffer

Erklärung

Frage 178 von 200

1

The two principles to follow when crashing a project focuses on the

Wähle eine der folgenden:

  • critical path and selects the least expensive alternative

  • critical path and selects the most expensive alternative

  • shortest path and selects the least expensive alternative

  • shortest path and selects the most expensive alternative

Erklärung

Frage 179 von 200

1

Using Goldratt's meaning of the word "dependent," the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements. The longest of these paths of sequentially time-dependent activities is known as the

Wähle eine der folgenden:

  • priority chain

  • critical chain

  • dependency path

  • heuristic path

Erklärung

Frage 180 von 200

1

The ___________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.

Wähle eine der folgenden:

  • as soon as possible

  • as late as possible

  • minimum slack first

  • shortest task first

Erklärung

Frage 181 von 200

1

Monitoring, as an activity, should be kept distinct from __________, which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

Wähle eine der folgenden:

  • recording

  • controlling

  • collecting

  • reporting

Erklärung

Frage 182 von 200

1

An appropriate and common secondary user for monitoring includes

Wähle eine der folgenden:

  • auditing, learning from mistakes, and reporting progress and status

  • exercising effective control over the project

  • evaluating current status of the project

  • fixing the blame when things go wrong

Erklärung

Frage 183 von 200

1

According to the authors, the key items to be planned, monitored, and controlled are

Wähle eine der folgenden:

  • schedule, budget, and financial stability

  • schedule, quality, performance, and customer satisfaction

  • schedule, budget, and feasibility

  • schedule, budget, and performance

Erklärung

Frage 184 von 200

1

According to the authors, in the planning - monitoring - controlling cycle, the directions of the flows indicate that

Wähle eine der folgenden:

  • information flows from the top to bottom and authority flows from the bottom to the top

  • information flows from the bottom to the top and authority flows from the top to the bottom

  • authority flows from the bottom to the top

  • information flows from the top to the bottom

Erklärung

Frage 185 von 200

1

The first step in setting up a monitoring system is to

Wähle eine der folgenden:

  • collect existing data to see what data is relevant and available

  • collect every available piece of information so it can be analyzed

  • use whatever information is available

  • identify the key factors to be controlled

Erklärung

Frage 186 von 200

1

In earned value analysis, the 50-50 rule assumes that

Wähle eine der folgenden:

  • 50 percent is earned when the task is half done and 50 percent is earned at completion

  • 50 percent is earned when the task begins and 50 percent is earned at completion

  • 50 percent is earned when the task begins and 50 percent is earned at the halfway stage

  • 50 percent is earned when the project is planned and 50 percent is earned when the project is over

Erklärung

Frage 187 von 200

1

In earned value analysis, if the cost variance is (-$10,000),

Wähle eine der folgenden:

  • the cost variance is favorable

  • the cost variance is unfavorable

  • the scheduled variance is favorable

  • the scheduled cost avoidance is unfavorable

Erklärung

Frage 188 von 200

1

One of the most common errors when collecting data is

Wähle eine der folgenden:

  • collecting rapidly changing data frequently

  • collecting data infrequently because data collection is so time consuming

  • collecting data that rarely changes

  • reporting to management after collecting data

Erklärung

Frage 189 von 200

1

Reports for ______________ have a need for detailed information about individual tasks and the factors affecting such tasks.

Wähle eine der folgenden:

  • top executives

  • lower-level personnel

  • all the stakeholders

  • project managers

Erklärung

Frage 190 von 200

1

The project control process should be viewed as a(n) ________________, with revised plans
and schedules (if warranted) following corrective actions. The project control process should run continuously until the project is completed.

Wähle eine der folgenden:

  • closed loop system

  • open loop system

  • open environment

  • earned value plan

Erklärung

Frage 191 von 200

1

Ordinal rankings of performance are examples of a _________ type of measure.

Wähle eine der folgenden:

  • frequency count

  • raw number

  • verbal measure

  • subjective numeric rating

Erklärung

Frage 192 von 200

1

____________ are used when some aspect of system performance cannot be measured
directly

Wähle eine der folgenden:

  • Indicators

  • Frequency counts

  • Raw numbers

  • Verbal measures

Erklärung

Frage 193 von 200

1

____________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.

Wähle eine der folgenden:

  • Detailed and timely reports

  • Executive summaries

  • Scope change reports

  • The WBS

Erklärung

Frage 194 von 200

1

The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the _________ rule.

Wähle eine der folgenden:

  • 50-50

  • 0-100 percent

  • critical input use

  • proportionality

Erklärung

Frage 195 von 200

1

In earned value analysis, EAC refers to the

Wähle eine der folgenden:

  • estimated cost at completion

  • estimated actual cost

  • eliminated annual cost

  • estimated annual cost

Erklärung

Frage 196 von 200

1

In earned value analysis, BAC refers to the

Wähle eine der folgenden:

  • budgeted annual cost

  • budget at completion

  • budget at close-out

  • big annual cost

Erklärung

Frage 197 von 200

1

If EV= $500, AC = $475, PV = $450; SV =

Wähle eine der folgenden:

  • $50

  • $25

  • 90%

  • 95%

Erklärung

Frage 198 von 200

1

If CSI is less than 1, it is indicative of a(n)

Wähle eine der folgenden:

  • problem

  • good project

  • efficient project

  • budget error

Erklärung

Frage 199 von 200

1

Conceptually, EAC represents the amount spent to date

Wähle eine der folgenden:

  • plus the delay costs

  • BAC

  • CV

  • ETC

Erklärung

Frage 200 von 200

1

In earned value analysis, the 0 - 100 percent rule allows

Wähle eine der folgenden:

  • 100 percent credit before starting work and 0 percent credit after the completion

  • 0 percent credit when work begins and 100 percent credit when the project is complete

  • 0 percent credit when work begins and 100 percent credit at completion of the activity

  • 0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification

Erklärung