PMP Midterm 2 Second 20 Q

Frage 1 von 20

1

You have recently taken over a troubled automobile project which has gone out of control. The project team missed many deadlines and stakeholders were not happy with the project progress. As an experienced project manager, your first priority is to bring the schedule into alignment with the project plan. You would like to use what-if scenario analysis to see how various factors affected the project schedule so that you can develop a plan to reduce the impact of adverse conditions on the project schedule in future. What would be your next course of action once you determine the factors that created schedule overrun?

Wähle eine der folgenden:

  • Prepare a resource breakdown structure to identify resources used

  • Update activity lists to incorporate new activities into the schedule

  • Generate change requests for a corrective action

  • Develop project schedule network diagrams to determine the total slack

Erklärung

Frage 2 von 20

1

You are the project manager of a project and are about to conduct a risk identification exercise in a few days’ time. You would like to proactively remind the participants in the exercise of the various sources from which risk may arise in the project. What could you use to help you do this?

Wähle eine der folgenden:

  • A Risk Breakdown Structure (RBS)

  • A Risk Simulation Structure (RSS)

  • A Risk Register

  • An Impact Matrix

Erklärung

Frage 3 von 20

1

A buyer and seller are looking at getting into a long-term relationship spanning over 10 years. Both parties would like to be protected from the unstable financial conditions of the country that are beyond their control. What type of contract is appropriate for such a relationship?

Wähle eine der folgenden:

  • Fixed Price Incentive Fee (FPIF)

  • Firm Fixed Price (FPP)

  • Time & Material (T&M)

  • Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Erklärung

Frage 4 von 20

1

What term defines the work needed to complete a product, service, or result?

Wähle eine der folgenden:

  • Product scope

  • Scope creep

  • Scope verification

  • Project scope

Erklärung

Frage 5 von 20

1

Emily is managing the construction of a new office facility for her company. The project is half way through the execution. The project sponsor has asked Emily to ensure that all they key project stakeholders are still committed to the project. How can Emily assess the stakeholders’ current engagement levels?

Wähle eine der folgenden:

  • By analyzing the most recent issue register

  • By reviewing the Stakeholders Engagement Assessment Matrix last updated during the planning phase of the project

  • By requesting the key stakeholders to submit a signed declaration of commitment

  • By communicating and interacting with the key stakeholders

Erklärung

Frage 6 von 20

1

A team of engineers is reviewing the architecture diagram for a new ERP system being deployed at a large accounting firm. The engineers are discussing the impact of the failure of each node in the diagram on overall availability of the final product. The intent of the discussion is to minimize the likelihood of failure and the effects of any failure. What is this called?

Wähle eine der folgenden:

  • SWOT Analysis

  • Quantitative Analysis

  • Failure Mode and Effect Analysis

  • Deming Cycle

Erklärung

Frage 7 von 20

1

You are a certified PMP, and have been contact by PMI as part of an investigation they are conducting into allegations of improper conduct by your manager, also a PMP. A complaint has been filed stating that your manager has received bribes related to a large procurement contract on another project. PMI has asked if you would be able to provide information regarding this situation. What should you do?

Wähle eine der folgenden:

  • Confront your manager.

  • Send PMI project documentation and emails related to the allegations to assist with their investigation.

  • Notify the appropriate management immediately.

  • Do nothing, citing a conflict of interest.

Erklärung

Frage 8 von 20

1

You are the project manager managing a project to design a print head for dot matrix printers. In order to determine ideal settings for print quality, the quality manager of the company suggests trying out various scenarios for printing by varying certain parameters on the print head. Identifying such variables which influence the product or process under development is called:

Wähle eine der folgenden:

  • Benchmarking

  • Design of Experiments

  • Statistical Sampling

  • Brainstorming

Erklärung

Frage 9 von 20

1

Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied?

Wähle eine der folgenden:

  • Crashing

  • Reserve Analysis

  • Forecasting

  • Last Tracking

Erklärung

Frage 10 von 20

1

As a project manager, you are performing various project performance measurements to assess the magnitude of variation. You then attempt to determine the cause and decide whether corrective action is required. This would be known as:

Wähle eine der folgenden:

  • Scope Analysis

  • Variance Analysis

  • Performance Reporting

  • Configuration Management

Erklärung

Frage 11 von 20

1

A project manager is looking at a make-or-buy analysis as part of the Plan Procurement Management process. What type of costs should the project manager consider for this analysis?

Wähle eine der folgenden:

  • Direct costs

  • Indirect costs

  • Out-of-pocket costs

  • Both direct as well as indirect costs

Erklärung

Frage 12 von 20

1

Jane is the project manager for a healthcare facility construction project. She is currently holding a board briefing and updating the project’s current status to the board members. When Jane was presenting her project risks, the chairman suggested some preventive actions. What should Jane do first?

Wähle eine der folgenden:

  • Jane should politely deny the request

  • Jane should write a change request

  • Jane should directly update the project management plan as the request has come from the Chairman

  • Jane should escalate the issue to the project sponsor

Erklärung

Frage 13 von 20

1

During the course of the project, the project management team developed a forecast for the estimate at completion (EAC) based on the project performance. Which of the following statements about EAC is correct?

Wähle eine der folgenden:

  • The EAC forecast based on the Bottom-up estimate to complete (ETC) requires a new estimate.

  • The EAC forecast is best estimated using the estimate to complete (ETC) work performed considering both SPI and CPI factors.

  • The EAC forecast is best estimated using the estimate to complete (ETC) work performed at the present CPI.

  • The EAC forecast is best estimated using the estimate to complete (ETC) work performed at the budgeted rate

Erklärung

Frage 14 von 20

1

You are managing a medium sized construction project, and are reviewing some invoices from the electrical contractor. You see that materials not required for your project have been included on the invoice. After making a few phone calls it becomes clear that one of your project resources asked one of the vendor’s staff to add a few extra circuits to one part of the building. This change was never approved through the change management process. What do you do?

Wähle eine der folgenden:

  • Notify the manager of your project resource that he failed to follow proper processes.

  • Refuse to pay the charges.

  • Call a team meeting to determine how this will impact the project, then inform stakeholders of the impacts.

  • Immediately inform the project stakeholders of the unauthorized scope change. Then call a team meeting to determine the impact to the project.

Erklärung

Frage 15 von 20

1

The total planned value (PV) for a project was $ 150,000. During the course of the project, the actual cost incurred turned out to be $ 275,000. What is the limit that the project manager usually imposes on the actual cost (AC)?

Wähle eine der folgenden:

  • The AC is usually limited to twice the planned value.

  • The AC will not have an upper limit.

  • The AC is usually limited to thrice the planned value.

  • The AC is usually limited to 1.5 times the planned value

Erklärung

Frage 16 von 20

1

The selection of life cycle for the project, the processes to be applied to each phase, and the results of the tailoring by the project management team are usually found in the:

Wähle eine der folgenden:

  • Project scope statement

  • Project management plan

  • Project schedule

  • Project charter

Erklärung

Frage 17 von 20

1

A project consists of multiple phases. Which of the following is a valid statement and applies to each phase of the project?

Wähle eine der folgenden:

  • Each phase is generally concluded with a review of the work accomplished but is only closed if the next phase has already been started.

  • Each phase of the project is considered complete when the project sponsor signs off on that phase of the project.

  • Each phase of the project is generally concluded with a review of the work accomplished and deliverables to determine acceptance and whether the phase should be considered closed.

  • Each phase is generally concluded with a review of the work accomplished. A phase is never considered complete until the end of the project when the entire project can be deemed complete.

Erklärung

Frage 18 von 20

1

You are a project manager who is in charge of an important project for your company. The project is 40% complete after 3 months and has cost $350,000. The budget for the project is $950,000 and is scheduled to last 8 months. How is the project performing?

Wähle eine der folgenden:

  • The project is behind schedule and over budget.

  • The project is ahead of schedule and under budget

  • The project is behind schedule and under budget.

  • The project is ahead of schedule and over budget

Erklärung

Frage 19 von 20

1

The manager of a project, that your company is running in another country, is at the corporate headquarters for a company-wide project management meeting. During a break, you overhear the project manager discussing payments made to local municipal governments for construction permits for his project. Your company has a strict policy about paying or taking bribes. What should you do?

Wähle eine der folgenden:

  • Report him to PMI.

  • Report him to his manager.

  • Notify his project stakeholders.

  • Do nothing.

Erklärung

Frage 20 von 20

1

Many project managers have seen a graph which shows “Influence of Stakeholders” starting out high and declining as the project progresses. Conversely, it shows the “Cost of Changes” starting out low and increasing as the project progresses. What is the key message a project manager should obtain from this graph?

Wähle eine der folgenden:

  • Stakeholder influence is not important at the end of the project.

  • Changes should be made as early in the project as possible.

  • Money should be set aside for expected changes at the end of the project.

  • The project should be placed on hold until all changes are made

Erklärung