Final PMP TVTC Exam

Frage 1 von 60

60

You are the project manager of a Pharmaceutical company responsible for releasing anew drug in the market. While managing the project, you have created several documents (e.g., project management plan; risk registers and other registers; project calendars; change management documentation; etc.). All these documents should be stored in:

Wähle eine der folgenden:

  • Historical information

  • Project or phase closure documents

  • Project documents

  • Configuration management system

Erklärung

Frage 2 von 60

60

The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables. Which of the following would be the BEST choice for getting your project better organized?

Wähle eine der folgenden:

  • Develop lessons learned for each phase.

  • Develop specific work plans for each work package.

  • Adopt a life cycle approach to the project.

  • Develop a description of the product of the project.

Erklärung

Frage 3 von 60

60

A company is making an effort to improve its project performance and create historical records of past projects. What is the BEST way to accomplish this?

Wähle eine der folgenden:

  • Create project management plans

  • Create network diagrams

  • Create status reports

  • Create lessons learned.

Erklärung

Frage 4 von 60

60

Which of the following is part of the integration management process?

Wähle eine der folgenden:

  • Create WBS

  • Manage Stakeholder Engagement

  • Define Activities

  • Monitor and Control Project Work

Erklärung

Frage 5 von 60

60

You are preparing a document using project statement of work, business case, agreements, enterprise environmental factors, and organizational process assets. These are valid inputs for:

Wähle eine der folgenden:

  • Develop Project Management Plan

  • Direct and Manage Project Work

  • Develop Project Charter

  • Perform Integrated Change Control

Erklärung

Frage 6 von 60

60

The director (information systems) in your company is in the process of creating a project charter to formally authorize a new project in your company. In this context, what should be done FIRST?

Wähle eine der folgenden:

  • Develop Project Management Plan

  • Assign a project manager for the project

  • Acquire Project Team

  • Integrate the work of the project with the ongoing operations of the performing

Erklärung

Frage 7 von 60

60

All of the following are purposes of the project charter EXCEPT:

Wähle eine der folgenden:

  • It gives the project manager authority.

  • It identifies the project acceptance criteria.

  • It identifies high-level risks and constraints.

  • It establishes the project.

Erklärung

Frage 8 von 60

60

Which of the following BEST describes the project manager's role during project planning?

Wähle eine der folgenden:

  • Creating a bar chart and getting management to approve it

  • Determining what can get in the way and how to prevent it

  • Managing the creation of a document that can be used to guide the project

  • Making a list of activities the team members are required to perform

Erklärung

Frage 9 von 60

60

A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of:

Wähle eine der folgenden:

  • A project expediter position.

  • Management attention to scope management.

  • Management planning.

  • A change control system.

Erklärung

Frage 10 von 60

60

Lessons learned are BEST gathered from:

Wähle eine der folgenden:

  • The team.

  • The stakeholders.

  • The sponsor.

  • The project manager.

Erklärung

Frage 11 von 60

60

During the creation of lessons learned for a project, the team determines that the project would have been better if they had a change control board. Which of the following is the BEST description of what a change control board helps the team to do?

Wähle eine der folgenden:

  • Create procedures

  • Formulate the change

  • Approve or reject changes

  • Create change requests

Erklärung

Frage 12 von 60

60

In which of the following structures can managers plan and evaluate project implementation but not have any actual authority over the workers?

Wähle eine der folgenden:

  • Strong matrix

  • Traceability matrix

  • Weak matrix

  • Coverage matrix

Erklärung

Frage 13 von 60

60

In your project, you are in the process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project`s objectives. This is done during:

Wähle eine der folgenden:

  • Develop Project Management Plan

  • Direct and Manage Project Work

  • Monitor and Control Project Work

  • Create Deliverables

Erklärung

Frage 14 von 60

60

Consideration of ongoing operations and maintenance is crucially important to products of projects. Ongoing operations and maintenance should:

Wähle eine der folgenden:

  • Be viewed as a separate project.

  • Be included as activities to be performed during project closure.

  • Have a separate phase in the project life cycle, because a large portion of life cycle costs is devoted to maintenance and operations.

  • Not be viewed as part of a project. A project is temporary with a definite beginning and end.

Erklärung

Frage 15 von 60

60

A software development project has been suffering through many major project changes. Because of this, the project manager has not been able to do much but complete change request forms. Which statement BEST describes the other activities the project manager should be doing?

Wähle eine der folgenden:

  • Determine that a change has occurred. Notify all stakeholders affected by the change, and list all the changes in the scope management plan.

  • Determine if a change is needed. Determine whether that change is beneficial, and notify stakeholders affected by the change.

  • Determine that changes have been made and whether the changes are beneficial. List all of them in the scope management plan.

  • List all changes in the project charter, notify stakeholders affected by changes, and ensure the team signs off on all changes.

Erklärung

Frage 16 von 60

60

Which of the following is included in a project charter?

Wähle eine der folgenden:

  • Work package estimates

  • Detailed resource estimates

  • The business case for the project

  • A risk management strategy

Erklärung

Frage 17 von 60

60

Which of the following BEST describes the project manager's role regarding project changes?

Wähle eine der folgenden:

  • Prevent the addition of profit in sellers' changes.

  • Discover changes as early as possible.

  • Have the sponsor approve all changes.

  • Prevent changes that affect the project scope.

Erklärung

Frage 18 von 60

60

Adhering to legal requirements, satisfying competing needs, providing accurate and truthful representations, and disclosing conflicts of interest are all:

Wähle eine der folgenden:

  • Examples of the intellectual property requirements of subcontractors.

  • Examples of scope management.

  • Examples of the professional and social responsibility of the project manager.

  • Examples of project closure activities.

Erklärung

Frage 19 von 60

60

The high-level project schedule constraints have just been determined. What project management process group are you in?

Wähle eine der folgenden:

  • Initiating

  • Monitoring and controlling

  • Executing

  • Planning

Erklärung

Frage 20 von 60

60

What is the benefit of the closing process if the project has been terminated?

Wähle eine der folgenden:

  • The benefit of the closing process is to gather lessons learned for the benefit of future projects.

  • The benefit of the closing process is to document how much work the project manager did.

  • The benefit of the closing process is to get everyone together and acknowledge that the team did a good job, even though the project was terminated.

  • There is no benefit to closing a project if the project has been terminated.

Erklärung

Frage 21 von 60

60

During a team meeting, a team member asks about the measurements that will be used on the project to judge performance. The team member feels that some of the measures related to activities assigned to him are not valid measurements. The project is BEST considered in what part of the project management process?

Wähle eine der folgenden:

  • Closing

  • Executing

  • Monitoring and controlling

  • Initiating

Erklärung

Frage 22 von 60

60

Management by objectives works only if:

Wähle eine der folgenden:

  • The rules are written down.

  • It is supported by management.

  • The project does not impact the objectives.

  • The project includes the objectives in the project charter.

Erklärung

Frage 23 von 60

60

All of the following must be performed during project initiating EXCEPT:

Wähle eine der folgenden:

  • Divide a large project into phases.

  • Accumulate and evaluate historical information.

  • Create a project scope statement.

  • Identify and document business needs.

Erklärung

Frage 24 von 60

60

Company procedures require the creation of a lessons learned document. Which of the following is the BEST use of lessons learned?

Wähle eine der folgenden:

  • Informing the team about what the project manager has done

  • Planning record for the current project

  • Historical records for future projects

  • Informing the team about the project management plan

Erklärung

Frage 25 von 60

60

Which of the following is a time-phased budget that is used to measure and monitor cost performance throughout the project life cycle?

Wähle eine der folgenden:

  • Cost estimating

  • Cost variance

  • Change control

  • Cost baseline

Erklärung

Frage 26 von 60

60

The project kick-off meeting should ideally occur when?

Wähle eine der folgenden:

  • After the project scope statement is completed

  • Once the scope management plan is approved

  • Before you begin creating the WBS

  • After the project charter is signed

Erklärung

Frage 27 von 60

60

Which process groups must be included in every project?

Wähle eine der folgenden:

  • Planning, executing, and closing

  • Initiating, planning, and executing

  • Initiating, planning, executing, monitoring and controlling, and closing

  • Planning, executing, and monitoring and controlling

Erklärung

Frage 28 von 60

60

A project manager receives a change request from the customer. The change requires adding a new filtration system to the project in place of a cleaner bag. When the project manager evaluates the change, it is MOST important that she consider the impact on the:

Wähle eine der folgenden:

  • Subsequent work packages.

  • Communications management plan.

  • Sponsor.

  • All Project aspects.

Erklärung

Frage 29 von 60

60

The ongoing definition of a project as more information becomes available to the team is called:

Wähle eine der folgenden:

  • Quantitative elaboration.

  • Strategic planning.

  • Scope validation.

  • Progressive elaboration.

Erklärung

Frage 30 von 60

60

A project manager gets a call from a team member notifying him that there is a variance between the speed of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning. If the project manager then evaluates whether the variance warrants a response, he is in what project management process?

Wähle eine der folgenden:

  • Initiating

  • Executing

  • Monitoring and controlling

  • Closing

Erklärung

Frage 31 von 60

60

The person who should be in control of the project during project planning is the:

Wähle eine der folgenden:

  • Team member.

  • Project manager.

  • Functional manager.

  • Sponsor.

Erklärung

Frage 32 von 60

60

Who issues the project charter?

Wähle eine der folgenden:

  • Sponsor

  • Project team

  • Project manager

  • Stakeholders

Erklärung

Frage 33 von 60

60

Which of the following BEST describes formal acceptance of a project?

Wähle eine der folgenden:

  • Final deliverables are sent to the customer.

  • Customer sign-off of the product is documented.

  • Final payment is made.

  • Substantial completion is reached.

Erklärung

Frage 34 von 60

60

Which of the following is the MOST appropriate thing to do in the monitoring and controlling process group?

Wähle eine der folgenden:

  • Obtain sign-off of the product of the project.

  • Create work performance reports.

  • Keep everyone focused on completing the project to the charter.

  • Implement recognition and reward systems.

Erklärung

Frage 35 von 60

60

Project management can be thought of as a start-_______-do-check-act cycle.

Wähle eine der folgenden:

  • Plan

  • Initiate

  • Control

  • Execute

Erklärung

Frage 36 von 60

60

A detailed project schedule can be created only after creating the:

Wähle eine der folgenden:

  • Project budget.

  • Project management plan.

  • Work breakdown structure.

  • Detailed risk assessment.

Erklärung

Frage 37 von 60

60

The work on the first phase of your project has come to an end. What should you ensure is done BEFORE beginning the next phase?

Wähle eine der folgenden:

  • Verify that the resources are available for the next phase

  • Check the project's progress compared to its baselines

  • Confirm that the phase has reached its objectives, and have its deliverables formally accepted

  • Recommend corrective action to bring the project results in line with project expectations

Erklärung

Frage 38 von 60

60

Who has the MOST power in a projectized organization?

Wähle eine der folgenden:

  • The project manager

  • The functional manager

  • The team

  • They all share power

Erklärung

Frage 39 von 60

60

A project team member is talking to another team member and complaining that many people are asking him to do things. If he works in a functional organization, who has the power to give direction to the team member?

Wähle eine der folgenden:

  • The project manager

  • The team

  • Tight matrix

  • The functional manager

Erklärung

Frage 40 von 60

60

Closure includes all of the following EXCEPT:

Wähle eine der folgenden:

  • Determining performance measures

  • Turning over the product of the project

  • Documenting the degree to which each project phase was properly closed after its completion

  • Updating the company's organizational assets

Erklärung

Frage 41 von 60

60

A project manager has very little project experience, but he has been assigned as the project manager of a new project. Because he will be working in a matrix organization to complete his project, he can expect communications to be:

Wähle eine der folgenden:

  • Complex

  • Simple

  • Open and accurate

  • Hard to automate

Erklärung

Frage 42 von 60

60

A project manager is trying to complete a software development project, but cannot get enough attention for the project. Resources are focused on completing process-related work and the project manager has little authority to properly assign resources. What form of organization must the project manager be working in?

Wähle eine der folgenden:

  • Matrix

  • Coordinator

  • Expediter

  • Functional

Erklärung

Frage 43 von 60

60

A market demand, a business need, and/or legal requirement are examples of:

Wähle eine der folgenden:

  • Reasons projects are initiated.

  • Reasons people or businesses become stakeholders.

  • Reasons to sponsor a project.

  • Reasons to hire a project manager.

Erklärung

Frage 44 von 60

60

Operational work is different from project work in that it is:

Wähle eine der folgenden:

  • Temporary.

  • A part of every project activity.

  • Unique.

  • On-going and repetitive.

Erklärung

Frage 45 von 60

60

A project manager is managing his second project. It started one month after the first and both are ongoing. Though his first project is small, this one seems to be growing in size every day. As each day passes, the project manager is beginning to feel more and more in need of help. The project manager has recently heard that there was another project in the company last year that is similar to his second project. What should he do?

Wähle eine der folgenden:

  • Obtain historical records and guidance from the project management office (PMO).

  • Contact the other project manager and ask for assistance.

  • Make sure the scope for the project is agreed to by all the stakeholders.

  • Wait to see if the project is impacted by the growth in scope.

Erklärung

Frage 46 von 60

60

All of the following are characteristics of a project EXCEPT:

Wähle eine der folgenden:

  • Temporary

  • Interrelated activities

  • Definite beginning and end

  • Repeats itself every month

Erklärung

Frage 47 von 60

60

All of the following are parts of the team's stakeholder management effort EXCEPT:

Wähle eine der folgenden:

  • Identifying stakeholders.

  • Managing stakeholders' expectations.

  • Giving stakeholders extras.

  • Determining stakeholders' needs.

Erklärung

Frage 48 von 60

60

In a projectized organization, the project team:

Wähle eine der folgenden:

  • Reports to many bosses.

  • Has no loyalty to the project.

  • Will not always have a home.

  • Reports to the functional manager.

Erklärung

Frage 49 von 60

60

Two project managers have just realized that they are in a weak matrix organization and that their power as project managers is quite limited. One figures out that he is really a project expediter and the other realizes he is really a project coordinator. How is a project expediter different from a project coordinator?

Wähle eine der folgenden:

  • The project expediter can make more decisions.

  • The project expediter cannot make decisions.

  • The project expediter reports to a higher-level manager.

  • The project expediter has some authority.

Erklärung

Frage 50 von 60

60

One of your team members informs you that he does not know which of the many projects he is working on is the most important. Who should determine the priorities among projects in a company?

Wähle eine der folgenden:

  • The project manager

  • The project management team

  • The project management office

  • The team

Erklärung

Frage 51 von 60

60

Four project managers are having lunch together and discussing their projects. Most of the time they are just complaining about how hard projects are to manage in their company. Some complain about the stakeholders and the number of changes they cause. Others talk about how hard it is to get people to cooperate and perform. One project manager wants to focus on the advantages of the matrix-type organization they all work in for their projects. Which of the following would he mention?

Wähle eine der folgenden:

  • More than one boss for project teams

  • Communications are easier

  • Improved project manager control over resources

  • Reporting is easier

Erklärung

Frage 52 von 60

60

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process?

Wähle eine der folgenden:

  • Integrated change control

  • Monitoring and controlling

  • Project closing

  • Corrective action

Erklärung

Frage 53 von 60

60

Which process group focuses on completing the requirements of the project?

Wähle eine der folgenden:

  • Planning

  • Executing

  • Initiating

  • Closing

Erklärung

Frage 54 von 60

60

Which of the following is the MOST appropriate thing to do in project closing?

Wähle eine der folgenden:

  • Collect historical information from previous projects.

  • Confirm all the requirements in the project have been met.

  • Gain formal approval of the management plans.

  • Work with the customer to determine acceptance criteria.

Erklärung

Frage 55 von 60

60

Which of the following would be the MOST appropriate thing to do during the initiating process group?

Wähle eine der folgenden:

  • Create a detailed description of the project deliverables

  • Ensure all project management processes are complete.

  • Identify the root cause of problems

  • Get familiar with the company culture and structure as it relates to the project

Erklärung

Frage 56 von 60

60

The BEST time to assign a project manager to a project is during:

Wähle eine der folgenden:

  • Initiating

  • Planning

  • Executing

  • Closing

Erklärung

Frage 57 von 60

60

In which project management process group is the detailed project budget created?

Wähle eine der folgenden:

  • Initiating

  • Planning

  • Executing

  • Monitoring and controlling

Erklärung

Frage 58 von 60

60

What is a program?

Wähle eine der folgenden:

  • A means to gain benefits and control of related projects

  • A group of unrelated projects managed in a coordinated way

  • A government regulation

  • An initiative set up by management

Erklärung

Frage 59 von 60

60

Which of the following is a characteristic of project management processes?

Wähle eine der folgenden:

  • Standardized

  • Unnecessary

  • Unique

  • Iterative

Erklärung

Frage 60 von 60

60

Lessons learned are BEST completed by:

Wähle eine der folgenden:

  • The team.

  • The stakeholders.

  • The project manager.

  • The sponsor.

Erklärung