Erstellt von miguelabascal
vor mehr als 11 Jahre
|
||
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
6.7 Control Schedule
A schedule model is
Some of the better known scheduling methods
include
Work packages are typically decomposed into smaller components called
Rolling wave planning is
Activities, distinct from milestones, have
A milestone is a
Every activity and milestone except the first and last should be
Logical relationships should be designed to
The precedence diagramming method (PDM) is a
Activity-on-node (AON) is one
Finish-to-start (FS).
Finish-to-finish (FF).
Start-to-start (SS).
Start-to-finish (SF).
In PDM, finish-to-start is the most
Mandatory dependencies are
Mandatory dependencies are also sometimes referred to
Discretionary dependencies are
External dependencies involve a
Internal dependencies involve a
A lead is the amount of
A lag is the amount of
A project schedule network diagram is a
The Estimate Activity Resources process is closely coordinated with
Bottom-up estimating is a
Analogous estimating is a
Parametric estimating is
Schedule network analysis is a
The critical path is
The critical path method is used to
The critical chain method (CCM) is a
The critical chain method adds
• Resource leveling.
Resource Smoothing.
• What-If Scenario Analysis
Crashing.
Fast tracking.
A schedule baseline is the