schiggy98
Quiz von , erstellt am more than 1 year ago

Quiz am quiz 12, erstellt von schiggy98 am 26/01/2016.

125
0
0
Keine Merkmale angegeben
schiggy98
Erstellt von schiggy98 vor fast 9 Jahre
Schließen

quiz 12

Frage 1 von 20

1

The three types of project control processes are:

Wähle eine der folgenden:

  • Easily understood because they have stayed the same for many years

  • Easily understood by all levels in the project team.

  • Cybernetic, go/no-go, and postcontrol

  • Not well-understood.

Erklärung

Frage 2 von 20

1

The project manager’s primary function includes managing human resources and:

Wähle eine der folgenden:

  • Following orders from top management.

  • Project Management software.

  • Guarding physical and financial assets of the company

  • Charting and graphing project task completion.

Erklärung

Frage 3 von 20

1

Because project milestones may not occur at periodic intervals, go/no-go controls
should be linked to the __________; not simply to the calendar.

Wähle eine der folgenden:

  • corporate budgeting process

  • actual plans and to the occurrence of real events

  • capital budgeting process

  • portfolio management review process

Erklärung

Frage 4 von 20

1

Go/no-go controls operate __________.

Wähle eine der folgenden:

  • only at phase gate reviews

  • only when exceptions are detected

  • only when and if the controller uses them

  • continuously

Erklärung

Frage 5 von 20

1

Identify the item that is NOT one of the three types of control processes described by
the authors.

Wähle eine der folgenden:

  • cybernetic control

  • robotic control

  • postcontrol

  • go/no-go control

Erklärung

Frage 6 von 20

1

In order to control creative projects the project manager must adopt one or some
combination of three general approaches to the problem. Which of the following is NOT
one of these approaches?

Wähle eine der folgenden:

  • creativity check

  • personnel reassignments

  • process review

  • control of input resources

Erklärung

Frage 7 von 20

1

Control is focused on three elements of a project. They are __________.

Wähle eine der folgenden:

  • scope, quality, and customer satisfaction

  • scope, cost, and time

  • cost, time, and customer satisfaction

  • performance, delivery, and cost

Erklärung

Frage 8 von 20

1

The two fundamental objectives of control are the regulation of results and the
__________.

Wähle eine der folgenden:

  • refurbishing of organizational assets

  • distribution of organizational assets

  • procurement of organizational assets

  • stewardship of organizational assets

Erklärung

Frage 9 von 20

1

An automatic control system containing a negative feedback loop is referred to as

Wähle eine der folgenden:

  • cybernetic

  • postcontrol

  • go/no-go

  • critical ratio

Erklärung

Frage 10 von 20

1

Cybernetic control is reported to be the most common type of control system, and
consists of:

Wähle eine der folgenden:

  • Upper management weekly approvals

  • Automated reports to top management when the project goes out of control

  • An automatic adjustment of processes when deviations are detected

  • Cybernetic loops of feedback to the PM.

Erklärung

Frage 11 von 20

1

Project control systems are very valuable to successful projects, and the typical cost of
the control systems is in the range of _________ percent of total project cost.

Wähle eine der folgenden:

  • 10 to 15%

  • 5 to 10%

  • 15-20%

  • 1 – 5%

Erklärung

Frage 12 von 20

1

Cybernetic control systems are:

Wähle eine der folgenden:

  • Positive feedback loops

  • Negative feedback loops

  • Very difficult to implement

  • Relatively expensive and difficult to use.

Erklärung

Frage 13 von 20

1

The stewardship of human resources requires __________ the growth and
development of people.

Wähle eine der folgenden:

  • mandating

  • controlling and maintaining

  • demolition

  • flattening

Erklärung

Frage 14 von 20

1

When a client wants to increase the scope or functionality of a project, what should the
project design engineer reply?

Wähle eine der folgenden:

  • Of course it’s OK. The client is always right.

  • Upper management will decide.

  • We can probably do that for you, and I can prepare a new schedule and cost
    analysis to fit your new plan/goals.

  • OK and it will not cost you any more.

Erklärung

Frage 15 von 20

1

The most common reason for scope creep is:

Wähle eine der folgenden:

  • Natural tendency of the client and project team to try to improve the original plan.

  • Engineering’s natural tendency to be perfectionists

  • Client’s unrealistic expectations for the design

  • Errors and omissions in the original project design

Erklärung

Frage 16 von 20

1

Project Management control of physical assets includes

Wähle eine der folgenden:

  • Scheduling of maintenance and repair of all project equipment

  • PMs do not control physical assets, they schedule work.

  • Scheduling of maintenance, repair, and/or replacement of project equipment

  • Planning, scheduling, and graphing of project tasks & equipment

Erklärung

Frage 17 von 20

1

Control systems commonly become out of balance because of:

Wähle eine der folgenden:

  • Too many project managers

  • Too few workers

  • Putting too much weight on easy-to-measure factors

  • Overemphasizing the seriousness of cost overruns

Erklärung

Frage 18 von 20

1

In a cybernetic control system using a negative feedback loop, the speed or force with
which the control operates is, in general, __________ to the size of the deviation from
standard

Wähle eine der folgenden:

  • double

  • customary

  • reciprocal

  • proportional

Erklärung

Frage 19 von 20

1

In order to gain user acceptance, the control system should appear to be __________.

Wähle eine der folgenden:

  • sensible

  • firm

  • enforced with sanctions

  • lenient

Erklärung

Frage 20 von 20

1

When performing control, project managers need to be attentive to __________.

Wähle eine der folgenden:

  • avoiding directive behaviors

  • regulation and conservation equally

  • regulation more than conservation

  • maintaining laissez faire leadership

Erklärung