DGPO04 Stakeholders

Frage 1 von 20

1

The stakeholder register contains details related to the identified stakeholders including all of the following EXCEPT:

Wähle eine der folgenden:

  • A Stakeholder location.

  • B Phase in the life cycle with the most interest.

  • C Classifications such as resister.

  • D Contract negotiations.

Erklärung

Frage 2 von 20

1

Your communications management plan assumed that all of your stakeholders would read their email to receive important project information. Since then, you have learned that executives' email is often read by their assistants. As a result, you changed your communications management plan to communicate important information in briefing meetings. Where else would you document the knowledge you gained?

Wähle eine der folgenden:

  • A Project charter

  • B Communications management plan

  • C Organizational process assets

  • D Enterprise environmental factors

Erklärung

Frage 3 von 20

1

Inputs to the Identify Stakeholders process include:

Wähle eine der folgenden:

  • A Procurement documents

  • B Work performance data

  • C Project management plan

  • D Issue log

Erklärung

Frage 4 von 20

1

The information from the project management plan that is used to control stakeholder engagement includes all of the following EXCEPT:

Wähle eine der folgenden:

  • A Addressing potential concerns that have not yet become issues need to be identified and discussed with stakeholders as soon as possible to assess associated project risks.

  • B How human resources requirements will be met, how roles and responsibilities, reporting relationships, and staffing management will be addressed and structured for the project.

  • C A change management plan that documents how changes will be monitored and controlled.

  • D How work will be executed to accomplish the project objectives.

Erklärung

Frage 5 von 20

1

__________ includes managing communications to satisfy the needs of, and resolve issues with, project stakeholders.

Wähle eine der folgenden:

  • A Manage Communications

  • B Plan Communications Management

  • C Manage Stakeholder Engagement

  • D Control Communications

Erklärung

Frage 6 von 20

1

General management skills related to harmonizing the group include __________.

Wähle eine der folgenden:

  • A Reporting on the work the team is doing and focusing on rewards and recognition

  • B Facilitating consensus, influencing people, negotiating agreements, modifying organizational behavior

  • C Documenting project status

  • D Tracking project progress

Erklärung

Frage 7 von 20

1

Project documents that will likely be updated during stakeholder planning include the:

Wähle eine der folgenden:

  • A Schedule baseline and process improvement plan.

  • B Stakeholder management plan and change management plan.

  • C Change management plan.

  • D Project schedule and stakeholder register.

Erklärung

Frage 8 von 20

1

All of the following are outputs of the Control Stakeholder Engagement process EXCEPT:

Wähle eine der folgenden:

  • A Work performance information.

  • B Change requests.

  • C Project management plan updates.

  • D Stakeholder register.

Erklärung

Frage 9 von 20

1

As the consultant for the ACME Bicycle Corporation, one of your responsibilities is to capture, store, and distribute information to stakeholders about the project cost, schedule progress, and performance. You want to be certain to meet the terms of your contract, so what tool will you use to assist you with this responsibility?

Wähle eine der folgenden:

  • A A integrated change control system

  • B A contract change control system

  • C An information management system

  • D A weighting system

Erklärung

Frage 10 von 20

1

Which of the following is an input to the Manage Stakeholder Engagement process?

Wähle eine der folgenden:

  • A Change log

  • B Project documents updates

  • C Change requests

  • D Organizational process assets updates

Erklärung

Frage 11 von 20

1

Classification models used with the Identify Stakeholder analysis include all the following EXCEPT:

Wähle eine der folgenden:

  • A Salience model.

  • B Influence/impact grid.

  • C Influence/expectations grid.

  • D Power/influence grid.

Erklärung

Frage 12 von 20

1

Jamie is a member of a project management team for a very large multinational development project. He is responsible for the Manage Stakeholder Engagement process for the project. Jamie will produce all of the following EXCEPT:

Wähle eine der folgenden:

  • A Change requests.

  • B Enterprise environmental factors.

  • C Organizational process assets updates.

  • D Project management plan updates.

Erklärung

Frage 13 von 20

1

Which of the following enterprise environmental factors should Sam focus on when planning stakeholder management?

Wähle eine der folgenden:

  • A Organizational culture

  • B Local politics

  • C Relationships

  • D Interpersonal skills

Erklärung

Frage 14 von 20

1

There are 23 communication channels in your project. You know how critical it is to engage stakeholders during the whole project and how important it is to understand engagement levels. Which of the following is NOT considered an engagement level classification?

Wähle eine der folgenden:

  • A Leading

  • B Unaware

  • C Clueless

  • D Resistant

Erklärung

Frage 15 von 20

1

Which of the following is NOT a Manage Stakeholder Engagement benefit?

Wähle eine der folgenden:

  • A Increases the likelihood of project acceptance

  • B Addresses concerns that have not become issues

  • C Clarifies and resolves issues that have been identified

  • D Maximizes stakeholder change requests

Erklärung

Frage 16 von 20

1

A grouping of stakeholders based on their level of authority and their active involvement is an example of a/an:

Wähle eine der folgenden:

  • A Power/interest grid.

  • B Power/influence grid.

  • C Influence/impact grid.

  • D Salience model.

Erklärung

Frage 17 von 20

1

All of the following are inputs to the Identify Stakeholders process EXCEPT:
.

Wähle eine der folgenden:

  • A Stakeholder management plan.

  • B Enterprise environmental factors.

  • C Procurement documents

  • D Project charter.

Erklärung

Frage 18 von 20

1

You are overwhelmed with all the organization process assets to consider when planning stakeholder management. You decide to start with the most powerful one. Which asset will you be focusing on?

Wähle eine der folgenden:

  • A Lessons learned

  • B Processes

  • C Policies

  • D Governing documents

Erklärung

Frage 19 von 20

1

The Plan Stakeholder Management process is important because:

Wähle eine der folgenden:

  • A It helps effectively engage stakeholders throughout the project.

  • B PMBOK® requires it.

  • C It is a component of the project management plan.

  • D The stakeholders asked for it.

Erklärung

Frage 20 von 20

1

The project stakeholder is:

Wähle eine der folgenden:

  • A The person or group of people assisting with matters such as project funding and clarifying scope questions.

  • B The person or group of people responsible for the project management activities.

  • C The person or group of people responsible for writing the project charter.

  • D The person or group of people actively involved in the project, or whose interests may be impacted by the project.

Erklärung