According to AIA documents, which of the following are NOT considered a part of the construction contract documents?

I. Specifications
II. Addenda
III. Shop Dwgs
IV. Owner-Architect Agreement
V. Supplementary Conditions

Wähle eine der folgenden:

  • A. IV only

  • B. II and III

  • C. I and V

  • D. III and IV

Erklärung

Frage 2 von 15

1

Fülle die Lücke, um den Text zu vervollständigen

A assures an owner that the contractor will execute the work in accordance with the contract.

Erklärung

Frage 3 von 15

1

During the course of construction, liability insurance should be maintained by which of the following?

I. The mortgagee
II. Trade unions
III. The surety company
IV. The owner
V. The contractor

Wähle eine der folgenden:

  • A. IV only

  • B. I and V

  • C. IV and V

  • D. II and III

Erklärung

Frage 4 von 15

1

Where would provisions for liquidated damages be found?

Wähle eine der folgenden:

  • A. Owner-Contractor Agreement

  • B. General Conditions of the Contract for Construction

  • C. Additive Alternates to the Contract

  • D. Proposal For and Instructions to Bidders

Erklärung

Frage 5 von 15

1

A change during construction in the location of underground lines from that shown on the site utilities plan should be reflected in

Wähle eine der folgenden:

  • A. record drawings.

  • B. architectural drawings.

  • C. field sketches.

  • D. shop drawings.

Erklärung

Frage 6 von 15

1

Architects are responsible for preparing which parts of a Project Manual?

I. Specifications
II. General Conditions
III. Supplementary Conditions
IV. Owner-Contractor Agreement

Wähle eine der folgenden:

  • A. I only

  • B. I and III

  • C. II and III

  • D. I, II, III, and IV

Erklärung

Frage 7 von 15

1

Which of the following are responsibilities of the owner under the provisions of the AIA General Conditions (remember to answer per the A201 as stated in the question, not your own experience.)?

I. Provide access to the construction site.
II. Make payment to the contractor.
III. Make payments to the subcontractors.
IV. Obtain necessary easements.
V. Provide necessary copies of the construction documents.

Wähle eine der folgenden:

  • A. II only

  • B. II and III

  • C. I and IV

  • D. II, IV, and V

Erklärung

Frage 8 von 15

1

Which of these statements is true? Contract time

Wähle eine der folgenden:

  • A. is measured in working days.

  • B. ends at substantial completion.

  • C. The general warranty period is one year.

  • D. Warranties are worthless without bonds to back them up.

Erklärung

Frage 9 von 15

1

Under the conditions of the A201 General Conditions, which of the following statements is true?

Wähle eine der folgenden:

  • A. Warranty periods begin at substantial completion.

  • B. Warranty periods begin at final completion.

  • C. The general warranty period is one year.

  • D. Warranties are worthless without bonds to back them up.

Erklärung

Frage 10 von 15

1

An architect issues certificates for payment for work performed by the contractor. For what reasons might an architect legitimately nullify all or party of a previously issued certificate for payment?

I. The architect discovers defective work.
II. The owner's lender refuses to release funds.
III. The contractor fails to pay subcontractors.
IV. A pedestrian walking past the project site is injured by a falling piece of lumber and sues the owner.
V. The contractor persistently fails to comply with the contract documents.

Wähle eine der folgenden:

  • A. I, II, III, IV, and V

  • B. I only

  • C. I, III, IV, and IV

  • D. III and V

Erklärung

Frage 11 von 15

1

Which of the following statements concerning payments to a contractor is FALSE?

Wähle eine der folgenden:

  • A. Payments are based on a schedule of values.

  • B. Title to materials and equipment passes to the owner upon payment.

  • C. The owner must pay the contractor within 21 days after the architect issues the certificate for payment.

  • D. Payments do not normally cover materials in transit.

Erklärung

Frage 12 von 15

1

Which of the following parties are responsible for workers' safety on a construction site?

I. The owner
II. The architect
III. The general contractor
IV. The contractor's surety company

Wähle eine der folgenden:

  • A. III only

  • B. I only

  • C. I, II, and III

  • D. I, II, III, and IV

Erklärung

Frage 13 von 15

1

An architect, under the provisions of the AIA documents, inspects a project how often during the construction phase?

Wähle eine der folgenden:

  • A. Never. The architect *observes* construction.

  • B. At intervals appropriate to the progress of the construction work.

  • C. Once, at final completion.

  • D. Twice, at substantial completion and at final completion.

Erklärung

Frage 14 von 15

1

Which of the following is NOT a prerequisite for final payment to the contractor?

Wähle eine der folgenden:

  • A. Final inspection by the architect.

  • B. Owner's receipt of the certificate of final completion from the architect.

  • C. Owner's receipt of the contractors affidavit or payment of debts.

  • D. Owner's receipt of consent of the contractor's surety company.

Erklärung

Frage 15 von 15

1

Which of the following parties must *approve* shop drawings according to the AIA General Conditions? Check all that apply.

Wähle eine oder mehr der folgenden:

  • A. Architect

  • B. Contractor

  • C. Owner

  • D. Engineers