Sahara D
Quiz von , erstellt am more than 1 year ago

Certificado PMP (Dirección de Proyectos) Inglés Quiz am PM Management Processes, erstellt von Sahara D am 12/10/2016.

228
0
0
Sahara D
Erstellt von Sahara D vor fast 8 Jahre
Schließen

PM Management Processes

Frage 1 von 26

1

In which project management process group is the detailed project budget created?

Wähle eine der folgenden:

  • Initiating

  • Before the project management process

  • Planning

  • Executing

Erklärung

Frage 2 von 26

1

The project charter is created in which project management process group?

Wähle eine der folgenden:

  • Executing

  • Planning

  • Closing

  • Initiating

Erklärung

Frage 3 von 26

1

The project team has just completed the initial project schedule and budget. The next thing to do is to:

Wähle eine der folgenden:

  • Identify risks

  • Begin iterations

  • Determine communications requirements

  • Create a bar (Grantt) chart

Erklärung

Frage 4 von 26

1

A detailed project schedule can be created only after creating the :

Wähle eine der folgenden:

  • Project budget

  • Work breakdown structure

  • Project management plan

  • Detailed risk assessment

Erklärung

Frage 5 von 26

1

The person who should be in control of the project during project planning is the:

Wähle eine der folgenden:

  • Project manager

  • Team member

  • Functional manager

  • Sponsor

Erklärung

Frage 6 von 26

1

Which of the following is not an input to the initiating process group

Wähle eine der folgenden:

  • Company processes

  • Company culture

  • Historical WBs

  • Project scope statement

Erklärung

Frage 7 von 26

1

The project sponsor has just signed the project charter. What is the next thing to do?

Wähle eine der folgenden:

  • Begin a complete work packages

  • Validate scope

  • Start integrated change control

  • Start to create management plans

Erklärung

Frage 8 von 26

1

The high-level project schedule constraits have just been determined. What project management process group are you in?

Wähle eine der folgenden:

  • Initiating

  • Planning

  • Executing

  • Monitor and Controlling

Erklärung

Frage 9 von 26

1

The WBS and WBS dictionary are completed. The project team has begun working on identifying risks. The sponsor contacts the project manager, requesting that the responsability assignment matrix be issued. The project has a budget of US $100,000 and is taking place in three countries using 14 human resources. There is a little risk expected for the project, and teh project manager has managed many projects similar to this one. What is the next thing to do?

Wähle eine der folgenden:

  • Understand the experience of the sponsor on similar projects

  • Create an activity list

  • Make sure the project scope is defined

  • Complete risk management and issue the responsability assigment matrix

Erklärung

Frage 10 von 26

1

A project manager does not have much time to spend on planning before the mandatory start date arrives. He therefore wants to move through planning as effectively as possible. What advice would you offer?

Wähle eine der folgenden:

  • Make sure you have a signed project charter and then start the WBS

  • Create an activity list before creating a network diagram

  • Document all the known risks before you document the high-level assumptions

  • Finalize the quality management plan before you determine quality metrics

Erklärung

Frage 11 von 26

1

The best time assign a project manager to a project is during:

Wähle eine der folgenden:

  • Integration

  • Project selection

  • Initiating

  • Planning

Erklärung

Frage 12 von 26

1

A project manager gest a call from a team member notifying him that there is a variance between the spend of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning. If the project manager then evalutes wheter the variance warrants a response, he is in which part of the project management process.

Wähle eine der folgenden:

  • Initiating

  • Executing

  • Monitoring and Controlling

  • Closing

Erklärung

Frage 13 von 26

1

A team member notifies the project manager that the activities comprising a work package are no longer appropiate. It would be best for the project manager to be in what part of the project management process.

Wähle eine der folgenden:

  • Corrective action

  • Integrated change control

  • Monitoring and Controlling

  • Project closing

Erklärung

Frage 14 von 26

1

During the team meeting, a team member asks about the measurements that will be used on the project to assess performance. The team member feels that some of the measures related to acctivies assigned to him are not valid measurements. The project is best considered to be in what part of the project management process?

Wähle eine der folgenden:

  • Closing

  • Monitoring and Controlling

  • Executing

  • Initiating

Erklärung

Frage 15 von 26

1

Which of the following is the most appropiate thing to do during the project initiating process group?

Wähle eine der folgenden:

  • Create a detailed description of the project deliverables

  • Get familiar with the company culture and structure as they relate to the project

  • Identify the root cause of problems

  • Ensure all project management process are complete

Erklärung

Frage 16 von 26

1

Which of the following is a characteric of project management processes?

Wähle eine der folgenden:

  • Iterative

  • Unique

  • Unnecessary

  • Standardized

Erklärung

Frage 17 von 26

1

Which project management process group generally takes the most project time and resources?

Wähle eine der folgenden:

  • Planning

  • Design

  • Integration

  • Executing

Erklärung

Frage 18 von 26

1

All of the following must be performed during project initiating except:

Wähle eine der folgenden:

  • Identify and document business need

  • Create a project scope statement

  • Divide a large project into phases

  • Accumulate and evaluate historical information

Erklärung

Frage 19 von 26

1

Closure includes all of the following except:

Wähle eine der folgenden:

  • Determining performance measures

  • Turning over the product of the project

  • Documenting the degree to which each project phase was properly closed after its completion

  • Updating the company's organization process assets

Erklärung

Frage 20 von 26

1

The first phase of your project has come to an end. What is the most important thing to ensure is done before beginning the next phase?

Wähle eine der folgenden:

  • Verify that the resources are available for the next phase

  • Check the project's progress compared to its baselines

  • Confirm that the phase has reached its objectives, and have its deliverables formally accepted.

  • Recommend corrective action to bring the project results in line with project expectations

Erklärung

Frage 21 von 26

1

During twhich process group does the team measure and analyze the work being done on the project?

Wähle eine der folgenden:

  • Initiating

  • Executing

  • Monitoring and Controlling

  • Closing

Erklärung

Frage 22 von 26

1

Which process groups must be included in every project?

Wähle eine der folgenden:

  • Planning, executing, and closing

  • Initiating, planning, and executing

  • Initiating, planning, executing, monitoring and controlling, and closing

  • Planning, executing, and monitoring and controlling

Erklärung

Frage 23 von 26

1

Which of the following is the most appropiate thing to do in project closing?

Wähle eine der folgenden:

  • Work with the customer to determine acceptance criteria

  • Collect historical information from previous projects

  • Confirm all the requirements in the project have been met

  • Gain formal approval of the management plans

Erklärung

Frage 24 von 26

1

Which process group focuses on completing the requirements of the project?

Wähle eine der folgenden:

  • Initiating

  • Planning

  • Executing

  • Closing

Erklärung

Frage 25 von 26

1

All of the following occur during the planning process group except

Wähle eine der folgenden:

  • Develop project charter

  • Create WBS

  • Estimate costs

  • Sequence activities

Erklärung

Frage 26 von 26

1

A market demand, a business need, and/or legal requirement are examples of:

Wähle eine der folgenden:

  • Reason to hire a project manager

  • Reasons projects are initiated

  • Reasons people or businesses become stakeholders

  • Reasons to sponsor a project

Erklärung