Project Management Tools Quiz

Frage 1 von 10

1

A critical activity has...

Wähle eine der folgenden:

  • Negative slack time

  • Zero slack time

  • Positive slack time

Erklärung

Frage 2 von 10

1

Wähle von der Dropdown-Liste, um den Text zu vervollständigen.

Critical path: The path of activities which represent the ( longest, shortest ) total time required to complete the project. A delay in an activity on the critical path causes a delay in the ( entire project, preceding activity, parallel activities ).

Erklärung

Frage 3 von 10

1

Wähle von der Dropdown-Liste, um den Text zu vervollständigen.

Finish to start lag: The minimum amount of time that must pass between the ( finish, start ) of one activity and the ( finish, start ) of its successor(s)

Erklärung

Frage 4 von 10

1

Wähle von der Aufklappliste, um den Text zu vervollständigen.

The variance in the project completion time can be calculated by ( subtracting, summing, multiplying ) the variances in the completion times of the activities in the critical path

Erklärung

Frage 5 von 10

1

Fülle die Lücke, um den Text zu vervollständigen

The normal distribution assumption holds if the number of activities in the path is large enough for the to be applied.

Erklärung

Frage 6 von 10

1

Fülle die Lücke, um den Text zu vervollständigen

The following times for completion an activity have been estimated.
Optimistic time: 4 days
Most likely time: 7 days
Pessimistic time: 10 days.
The variance in the expected time is days.

Erklärung

Frage 7 von 10

1

Fülle die Lücken, um den Text zu vervollständigen.

When preparing a Work Breakdown Structure, continue to subdivide components until the lowest level component requires between and hours of work.

Erklärung

Frage 8 von 10

1

Fülle die Lücke, um den Text zu vervollständigen

When components of a WBS are defined in sufficient detail for management and planning purposes, they are known as .

Erklärung

Frage 9 von 10

1

Fülle die Lücke, um den Text zu vervollständigen

High level elements in the WBS should match, word for word, nouns used to describe outcomes in the .

Erklärung

Frage 10 von 10

1

Fülle die Lücke, um den Text zu vervollständigen

The current activity has an Early Start of March 1st and a duration of 3 days.
The succeeding activity has an Early Start of March 7th. Assuming everyday is a work day, then the free float is days.

Erklärung