PMP Prep quiz

Frage 1 von 10

1

Most common cause of conflicts in a project is:

Wähle eine der folgenden:

  • Schedules

  • Technical Opinions

  • Personal Issues

  • Project Priorities

Erklärung

Frage 2 von 10

1

You are the Project Manager of the XYZ project. You want to find the planned expenses for next month. Which document do you need to refer to?

Wähle eine der folgenden:

  • Cost Management Plan

  • Cost Baseline

  • Cost Control Plan

  • Cost Variance report

Erklärung

Frage 3 von 10

1

You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only after two days of completion of painting of walls. This is an example of :

Wähle eine der folgenden:

  • Lag

  • Lead

  • Slack

  • Float

Erklärung

Frage 4 von 10

1

Control Procurements is a process in the Project Procurement Management Knowledge area.

Wähle eins der folgenden:

  • WAHR
  • FALSCH

Erklärung

Frage 5 von 10

1

Which of the following theory was suggested by Deming?

Wähle eine der folgenden:

  • Apply continuous small improvements to reduce costs and ensure consistency.

  • Marginal Analysis

  • Expectancy theory - people expect to be rewarded for their efforts.

  • Plan-do-check-act to improve quality.

Erklärung

Frage 6 von 10

1

You are required to estimate the time to paint a large wall. You know it takes two hours to paint one square foot of wall. The wall has an area of 30 square foot. So you estimate that it will take 60 hours to paint the wall. Which estimation model are you using?

Wähle eine der folgenden:

  • Bottom-up

  • Parametric modeling

  • Analogous

  • Expert judgment

Erklärung

Frage 7 von 10

1

In which process of Project Risk Management knowledge area are numeric values assigned to probabilities and impact of risks?

Wähle eine der folgenden:

  • Perform Qualitative Risk Analysis

  • Perform Quantitative Risk Analysis

  • Perform Numeric Risk Analysis

  • Plan Risk Response

Erklärung

Frage 8 von 10

1

Which of the following is an output of the Identify Risks process.

Wähle eine der folgenden:

  • Lessons Learned

  • Checklists

  • Risk Register

  • SWOT Analysis

Erklärung

Frage 9 von 10

1

The process of Conduct Procurements is part of the planning phase.

Wähle eins der folgenden:

  • WAHR
  • FALSCH

Erklärung

Frage 10 von 10

1

Which process identifies the project manager?

Wähle eine der folgenden:

  • Develop Project Management Plan

  • Develop Project Charter

  • Define Scope

  • Select Project Process

Erklärung