Frage 1
Frage
Herzberg's Theory focuses on ...
Antworten
-
hygiene factors and motivators
-
hygiene factors and esteem factors
-
motivators and safety factors
-
hygiene factors and social factors
Frage 2
Frage
Which of the following BEST describes a project management plan?
Frage 3
Frage
Which one of the following is NOT a conflict resoltion technique?
Antworten
-
Withdrawing
-
Smoothing
-
Compromising
-
Advertising
Frage 4
Frage
The pareto principle states that ___________ percent of the problems are due to 20 percent of the root causes
Frage 5
Frage
Which of the following is NOT a task of the process 'Close Project or Phase'?
Frage 6
Frage
A conflict in a project team is ...
Antworten
-
a problem, which reduces the ability to work
-
nothing important and will not reduce the ability to work
-
a situation that occurs at least once a day
-
a crisis, that could stop the work on the project
Frage 7
Frage
If earned value (EV) = 550, actual cost (AC) = 400, planned value (PV) = 350, what is the cost variance (CV)?
Frage 8
Frage
Which one of the following processes is NOT part of the Monitoring & Controlling Process Group?
Antworten
-
Control Schedule
-
Control Procurements
-
Close Procurements
-
Control Costs
Frage 9
Frage
The project charter is created in which project management process group?
Antworten
-
Planning
-
Executing
-
Closing
-
Initiating
Frage 10
Frage
What is the duration of a milestone?
Antworten
-
Same length as the activity it represents
-
Shorter than the activity it represents
-
Shorter than the duration of the longest activity
-
There is no duration
Frage 11
Frage
Conflict resolution techniques that may be used on a project include confronting, smoothing, forcing and:
Antworten
-
Directing
-
Organizing
-
Controlling
-
Withdrawing
Frage 12
Frage
When would a milestone chart be used instead of a bar chart?
Frage 13
Frage
If you make a prototype for a risky piece of equipment what type of risk response is this?
Antworten
-
Accept
-
Mitigate
-
Avoid
-
Transfer
Frage 14
Frage
Which project management process group generally takes the MOST project time and resources?
Antworten
-
Executing
-
Planning
-
Integration
-
Design
Frage 15
Frage
During which process group does the team measure and analyze the work being done on the project?
Frage 16
Frage
A project has three critical paths. Which of the following BEST describes how this affects the project?
Antworten
-
It increases the project risk.
-
It makes it easier to manage.
-
It makes it more expensive.
-
It requires more people.
Frage 17
Frage
The difference between the cost baseline and the cost budget can be BEST described as:
Frage 18
Frage
Which of the following explains why quality is planned in and not inspected in?
Antworten
-
It reduces quality and is less expensive.
-
It improves quality and is less expensive.
-
It reduces quality and is more expensive.
-
It improves quality and is more expensive.
Frage 19
Frage
Which of the following statements regarding the decision tree is correct?
Antworten
-
You should not upgrade to the new software version because the EMV is higher than the other option.
-
You should not upgrade to the new software version because these are additional costs for the project
-
You should upgrade to the new version of the software because the EMV is 15.000,- and this is less than the EMV of 25.000 (if you do not upgrade)
-
As the impact is the same, you can choose any of the options
Frage 20
Frage
Which one of the following is NOT a response strategy for negative risks or threats?
Antworten
-
Avoid
-
Mitigate
-
Exploit
-
Transfer
Frage 21
Frage
With which type of contract is the seller MOST concerned about project scope?
Frage 22
Frage
Which team development stages are included in the Tuckman Model?
Antworten
-
Forming, Storming, Norming, Performing and Solving
-
Forming, Warming, Storming, Performing and Adjourning
-
Forming, Storming, Norming, Performing and Adjourning
-
Forming, Storming, Norming, Adjourning and Resolving
Frage 23
Frage
Which of the following is a chief characteristic of the Delphi technique?
Frage 24
Frage
You have just identified the risks. What is the next process?
Frage 25
Frage
A schedule performance index (SPI) of 0.76 means:
Antworten
-
You are only progressing at 76 percent of the rate originally planned.
-
You are only progressing at 24 percent of the rate originally planned.
-
You are ahead of schedule.
-
You are over budget.
Frage 26
Frage
Cause-and-effect diagrams are also called?
Antworten
-
Control Charts
-
Pareto Charts
-
Fishbone diagram
-
Flow Charts
Frage 27
Frage
What conflict resolution technique is a project manager using when he says, "I cannot deal with this issue now!"
Antworten
-
Forcing
-
Problem solving
-
Withdrawing
-
Compromising
Frage 28
Frage
Budget at Completion (BAC) ...
Antworten
-
may be calculated based on performance to date or estimated by the project team
based on other factors.
-
is equal to the actual cost (AC) plus the estimate to complete (ETC) for all of the remaining work.
-
is the sum of all the budgets established for the work to be performed on a project or a work breakdown structure component or an activity.
-
is the value of work performed expressed in terms of the approved budget assigned to that work for an activity or work breakdown structure component.
Frage 29
Frage
How long is the critical path is this example?
Frage 30
Frage
The process 'Sequence Activities' belongs to which Knowledge Area?
Frage 31
Frage
If you have to shorten the project duration without reducing the scope you can do the following:
Frage 32
Frage
Secondary risks are
Antworten
-
The risks that remain after planned responses have been implementes
-
A direct outcome of risk responses
-
Risks with a low priority and therefore will not be considered in further plannings
-
Risks that are deliberately accepted
Frage 33
Frage
You are estimating activity durations and have got the following values:
Pessimistic: 12
Most likely: 5
Optimistic: 4
What is the expected duration when you are using Beta Distribution?
Frage 34
Frage
Which of the following is not a valid organizational structure?
Frage 35
Frage
Which of the following is included in a project charter?
Antworten
-
Detailed resource estimates
-
A risk management strategy
-
Work package estimates
-
The business need for the project
Frage 36
Frage
An organization is restructuring the way it does projects. In a shift from a strong matrix organization to a weak matrix organization, the power is shifted from the:
Antworten
-
Project manager to the functional manager.
-
Functional manager to the project manager.
-
Functional manager to the sponsor.
-
Expediter to the coordinator.
Frage 37
Frage
When a product or service completely meets a customer‘s requirements:
Antworten
-
The cost of quality is low.
-
Quality is achieved
-
The customer pays the minimum price.
-
The cost of quality is high.
Frage 38
Frage
The work breakdown structure is basis for all of the following EXCEPT:
Antworten
-
Network Diagram
-
Risk Management
-
Estimating
-
Project charter
Frage 39
Frage
Which of the following leadership traits is MOST important for a project manager?
Antworten
-
Project control
-
Communication
-
Technical expertise
-
Team building
Frage 40
Frage
The MOST important output of the process Plan Stakeholder Management is the ...
Frage 41
Frage
Which of the following regarding WBS is NOT correct?
Antworten
-
What is not in the WBS is not part of the project
-
WBS means - Work Best to meet Schedule
-
Is often structured by phases
-
Is best presented as a graph
Frage 42
Frage
Which of the following is not a contract type category?
Frage 43
Frage
The highest point of Maslow's hierarchy of needs is called:
Frage 44
Frage
Which of the following risks is the biggest threat to the project?
Frage 45
Frage
Which of the following is CORRECT?
Antworten
-
Critical path and near-critical path are the same
-
There can be only 1 critical path
-
Activities on the critical path have no buffer
-
A project can never have negative float