Project Management Final CH 11-13

Beschreibung

Contains all questions and answers from the previous chapter exams (CH 11-13)
Anthony Schulmeister
Quiz von Anthony Schulmeister, aktualisiert more than 1 year ago
Anthony Schulmeister
Erstellt von Anthony Schulmeister vor fast 7 Jahre
423
1

Zusammenfassung der Ressource

Frage 1

Frage
Control is focused on three elements of a project. They are
Antworten
  • scope, quality, and customer satisfaction
  • performance, delivery, and cost
  • scope, cost, and time
  • cost, time, and customer satisfaction

Frage 2

Frage
Which of the following is the key feature of cybernetic control systems?
Antworten
  • Manual operations
  • Directional controls
  • Automatic operation
  • Specific preconditions

Frage 3

Frage
Most control systems used in project management today fall into this category of control system.
Antworten
  • cybernetic control
  • robotic control
  • go/no-go control
  • postcontrol

Frage 4

Frage
Because project milestones may not occur at periodic intervals, go/no-go controls should be linked to the ____________; not simply to the calendar.
Antworten
  • actual plans and to the occurrence of real events
  • corporate budgeting process
  • portfolio management review process
  • capital budgeting process

Frage 5

Frage
The critical ratio control chart uses a ratio made up of two parts -- the ratio of actual progress to scheduled progress, and the
Antworten
  • ratio of earned value to planned cost
  • ratio of budgeted cost to actual cost
  • ratio of actual cost to budgeted cost
  • ratio of planned cost to earned value

Frage 6

Frage
The two fundamental objectives of control are the regulation of results and the
Antworten
  • procurement of organizational assets
  • distribution of organizational assets
  • stewardship of organizational assets
  • refurbishing of organizational assets

Frage 7

Frage
The __________ process controls the project at various points in the life cycle to make sure that the project remains on course. This is opposed to waiting until the project is completed and then finding out it doesn't meet the objectives of the organization
Antworten
  • portfolio
  • phased-step
  • phased-gate
  • overarching

Frage 8

Frage
The ___________ controls take the form of testing to see if some specific precondition has been met.
Antworten
  • postcontrol
  • go/no-go
  • cybernetic
  • monitoring

Frage 9

Frage
______________ are directed towards improving chances for future projects to meet their goals.
Antworten
  • postcontrols
  • Go/no-go decisions
  • cybernetics
  • negative feedback loops

Frage 10

Frage
___________ controls are usually viewed as helpful rather than as a source of unwelcome pressure if the controlees perceive themselves as able to perform inside the prescribed limits.
Antworten
  • steering
  • negative feedback
  • postcontrols
  • cybernetic

Frage 11

Frage
Change control systems, in some industries, are part of a firm's
Antworten
  • configuration management system
  • internal IDC system
  • cybernetic system
  • early warning system

Frage 12

Frage
A majority of uncertainty has its source in systems that lie outside the project, in its
Antworten
  • environment
  • stakeholder area
  • sourcing model
  • control zone

Frage 13

Frage
The _____________ is calculated as (actual progress/scheduled progress) x (budgeted cost/actual cost)
Antworten
  • critical ratio
  • highlighted ratio
  • cybernetic ratio
  • efficiency ratio

Frage 14

Frage
Scope creep can be caused by the
Antworten
  • customer
  • team members
  • audit team
  • customer and team members

Frage 15

Frage
_______________ is a management approach that may be used to make comparisons to "best in class" practices across organizations
Antworten
  • processing
  • benchmarking
  • leveling
  • standardizing

Frage 16

Frage
Thamhain (2013) found that ___________ was/were not only the most frequent risk class but also had the most impact on project performance.
Antworten
  • increasing stakeholder involvement
  • changing leadership
  • decreasing costs
  • changing project requirements

Frage 17

Frage
A(n) _______________ is a monitoring system that forewarns the project manager if trouble arises.
Antworten
  • configuration management system
  • internal IDC system
  • cybernetic system
  • early warning system

Frage 18

Frage
______________ are seen as much the same as a report card.
Antworten
  • postcontrols
  • WBSs
  • cybernetics
  • critical ratios

Frage 19

Frage
The cybernetic control system that acts to reduce deviations from standard is called a
Antworten
  • nonautomatic modification
  • critical ratio
  • positive feedback loop
  • negative feedback loop

Frage 20

Frage
20. For all but __________changes, a risk identification and analysis should be performed.
Antworten
  • minor
  • major
  • most
  • few

Frage 21

Frage
The project audit covers
Antworten
  • only financial matters
  • everything except operating matters
  • only ethical and financial matters
  • any specified scope of importance to management

Frage 22

Frage
The dimension of project success includes the obvious factors of meeting the project's technical and operational specifications. It also includes factors relating to loyalty and repurchase.
Antworten
  • project efficiency
  • customer impact/satisfaction
  • business/direct success
  • future potential

Frage 23

Frage
The __________ dimension of project success includes factors relating to opening a new market, developing a new line of products or services. Alternatively, if an internal project, success factors include developing new technologies, skills, or competencies
Antworten
  • project efficiency
  • customer impact/satisfaction
  • business/direct success
  • future potential

Frage 24

Frage
Identification of the direct goals of a project requires
Antworten
  • a reading of the project structure
  • a reading of the project proposal
  • a reading of the budget
  • a reading of the WBS

Frage 25

Frage
Two of the most common limits on the depth of an investigation and level of detail presented in an audit report are
Antworten
  • the personality of the auditor and cooperation received
  • scope and objectives
  • word processing support and existing documentation
  • money and time

Frage 26

Frage
The accumulation, storage, and maintenance of auditable data are important cost elements. Such storage may be critically important in meeting the legal test of
Antworten
  • completeness
  • accuracy
  • due diligence
  • capacity

Frage 27

Frage
Audits done early in the project lifecycle are often focused on
Antworten
  • technical issues
  • management issues
  • financial issues
  • personnel issues

Frage 28

Frage
For audits made late in the project's life, ____________ are major matters of interest
Antworten
  • technical issues
  • management issues
  • financial issues
  • personnel issues

Frage 29

Frage
In the audit report, negative comments about individuals or groups associated with the project should be
Antworten
  • avoided
  • included
  • highlighted
  • disguised

Frage 30

Frage
An evaluation of the likely outcomes of a policy and their probability of occurrence, usually conducted to compare two or more scenarios or policies is known as
Antworten
  • technical evaluation
  • project evaluation
  • risk analysis
  • profit estimation

Frage 31

Frage
___________ is defined as a standard for performance, commonly established early on for later comparisons
Antworten
  • audit
  • baseline
  • evaluation
  • summary

Frage 32

Frage
____________tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.
Antworten
  • auditing
  • postcontrols
  • baselining
  • ruling

Frage 33

Frage
The most immediate dimension of project success is the project's _____________ in meeting both budget and schedule
Antworten
  • timing
  • delay
  • totality
  • effectiveness

Frage 34

Frage
A typical detailed audit is conducted when _______________ is required
Antworten
  • a follow-up to the general audit
  • effectiveness
  • an ethical audit
  • full disclosure

Frage 35

Frage
The stated project objectives, including customer satisfaction, are part of the project's ________ goals
Antworten
  • indirect
  • ancilliary
  • secondary
  • direct

Frage 36

Frage
The ____________ section of an audit report contains a description of the project to provide a framework of understanding for the reader. Project objectives are clearly delineated.
Antworten
  • current status
  • future project status
  • introduction
  • risk management

Frage 37

Frage
In the current status section of an audit report, the subheading labeled ____________ will compare the work completed with the resources expended.
Antworten
  • scope
  • cost
  • schedule
  • quality

Frage 38

Frage
The _______________ section of the audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach, schedule, or budget that should be made in the remaining tasks
Antworten
  • introduction
  • current project status
  • future project status
  • risk management

Frage 39

Frage
In the Future Project Status section of the audit report, no assumptions should be made about _________ that are still under investigation at the time of the audit.
Antworten
  • financial problems
  • ethical problems
  • efficiency problems
  • technical problems

Frage 40

Frage
Contact between the a/e team and the _______________ are not made without clearance from senior management
Antworten
  • CIO
  • ethics board
  • customer
  • project manager

Frage 41

Frage
The termination stage of the project rarely has much impact on
Antworten
  • residual attitudes of the client towards the project
  • technical success or failure of the project
  • residual attitudes of senior management towards the project
  • the preparedness of the project team for the project

Frage 42

Frage
When a decision is made to terminate a project by extinction, the most noticeable event is that
Antworten
  • all activity on the substance of the project ceases
  • all organizational activity related to the project ceases
  • all further expenditures related to the project are immediately blocked
  • all activity on the project ceases

Frage 43

Frage
In termination by addition, project assets are
Antworten
  • transferred from a dying project to a new division
  • assumed to have been exhausted
  • liquidated
  • retained in the existing project

Frage 44

Frage
When an in-house project is a major success and it is terminated by institutionalizing it as a formal part of the parent organization; this is termination by
Antworten
  • addition
  • starvation
  • integration
  • extinction

Frage 45

Frage
According to research by Pinto, the two most important critical success factors are
Antworten
  • project mission and top-management support
  • trouble-shooting and communication
  • communication and personnel
  • project mission and communication

Frage 46

Frage
The fundamental purpose of the final project report is to
Antworten
  • devote more resources to the project
  • finish the work so that payment can be collected
  • improve future projects
  • document the errors in the project

Frage 47

Frage
A common mistake in project management is to appoint as project manager an individual with excellent ________ skills but weak ___________ skills.
Antworten
  • technical; managerial
  • managerial; technical
  • technical; social
  • social; managerial

Frage 48

Frage
Most studies have shown that the factors associated with project success or failure
Antworten
  • are similar across different industries and the various types of projects
  • are different across different industries and the various types of projects
  • are similar across different industries but different for the various types of projects
  • are different across different industries but similar for the various types of projects

Frage 49

Frage
The project performance section of the final report
Antworten
  • analyzes the impact of organizational structure on the project
  • offers solutions to technical problems that may have occurred
  • reviews the administrative practices used during the project
  • compares what the project achieved with what it aimed for

Frage 50

Frage
The techniques of project management section of the final report
Antworten
  • analyzes the impact of organizational structure on the project
  • offers solutions to technical problems that may have occurred
  • reviews the administrative practices used during the project
  • scrutinizes the methods of planning, control, and risk management

Frage 51

Frage
The special case of termination by extinction wherein the project experiences a sudden demise even though it was lacking obvious signals that death was imminent is known as
Antworten
  • termination by integration
  • termination by addition
  • termination by murder
  • termination by starvation

Frage 52

Frage
Special ___________ managers are sometimes useful in completing the long and involved process of shutting down the project.
Antworten
  • close-out
  • starvation
  • shut-down
  • termination

Frage 53

Frage
The ___________ section of the final project report is a comparison of what the project achieved with what the project tried to achieve.
Antworten
  • project performance
  • administrative performance
  • organizational structure
  • personnel suggestions

Frage 54

Frage
Cutting a project's budget sufficiently to stop progress without actually killing the project is referred to as
Antworten
  • termination by addition
  • termination by extinction
  • termination by starvation
  • termination by subtraction

Frage 55

Frage
The primary criterion for project _____________ is whether or not the organization is willing to invest the estimated time and cost required to complete the project, given the project's current status and current expected outcome.
Antworten
  • continuance
  • termination
  • continuance or termination
  • extinction

Frage 56

Frage
Bringing the project into the organization as a separate, ongoing entity is called
Antworten
  • termination by starvation
  • termination by integration
  • termination by extinction
  • termination by addition

Frage 57

Frage
According to the text, a _________ cost is generally not relevant to current investment decisions. Rather, decision-makers should focus on the time and cost required to complete the project.
Antworten
  • high
  • fixed
  • sunk
  • variable

Frage 58

Frage
If a project is a major success and it is terminated, by institutionalizing it as a formal part of the parent organization, this is an example of termination by
Antworten
  • termination by integration
  • termination by addition
  • termination by murder
  • termination by starvation

Frage 59

Frage
Which of the following is not a common task for a termination manager?
Antworten
  • ensuring completion of the work
  • redistributing personnel materials, and equipment
  • communicating with all stakeholders why the project was terminated
  • overseeing the closing of the project's books

Frage 60

Frage
In termination by integration, project assets are
Antworten
  • liquidated
  • reassigned to another project
  • transferred from the dying project to the newly born division
  • distributed among the existing elements of the parent organization
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

2D alte Klausurfragen
Anni T-Pünktchen
Aufbau Quellenanalyse
barbara91
Zivilrecht - Streitigkeiten BGB AT
myJurazone
Analytische Geometrie
sonnenblume1997
Evolution des Menschen (bioloos)
sonja.loos
Raumfahrt 1
Jen H
Französisch Grund- und Aufbauwirtschaft A1-B2 Teil 1
Chiara Braun
WERB Univie
Sandra S.
Vetie Mibi 2012
Tropsi B
Chirurgie Rind Vetie
Anne Käfer
AVO & Klinische Pharmakologie 2013
Birte Schulz