Frage 1
Frage
Which is a recommenced quality review team role?
Antworten
-
Senior User
-
Presenter
-
Project Support
-
Project Assurance
Frage 2
Frage
Which is a purpose of the Communication Management Strategy?
Antworten
-
Identify how and by whom the project's products will be controlled and protected
-
Define the method of communication between the project and its stakeholders
-
Define the structure of responsibilities and accountabilities in support of effective decision making in a project
-
Identify the communication required from the Team Manager(s) to the Project Board
Frage 3
Frage
Identify the missing words in the following sentence.
Any requests for change, which require Project Board approval,should be recorded in the [?] and monitored by the Project Manager
Frage 4
Frage
If a product fails its quality check, what product should always be updated?
Antworten
-
Risk Register
-
Issue Register
-
Quality Register
-
Lessons Log
Frage 5
Frage
In what product should the Project Manager enter the details of issues that are resolved without using the formal issue and the change control procedure?
Frage 6
Frage
Which of the PRINCE2 principles uses tolerances to establish the limits of delegated authority?
Frage 7
Frage
Which is a purpose of the Starting up a Project process?
Antworten
-
Ensuring that the prerequisites for initiating the project are in place.
-
Establishing that the Project Plan can meet the required target dates.
-
Creating the Project Initiation Documentation so the project can be initiated.
-
Confirming to corporate or programme management that quality expectations will be met.
Frage 8
Frage
When should the project management team be reviewed?
Antworten
-
As and when new stakeholders are identified
-
When planning a quality review
-
When planning the next stage
-
During product creation
Frage 9
Frage
Which is NOT responsibility of the Project Board?
Antworten
-
Allocate tolerances to specialist teams
-
Transfer ownership of the Benefits Review Plan to corporate or programme management
-
Approve the Project Product Description
-
Confirm the required frequency of highlight reports.
Frage 10
Frage
Who sets the project tolerances?
Frage 11
Frage
PRINCE2 plans are carefully designed to meet the needs of the different levels in the project organisation. Why is this a benefit?
Antworten
-
Ensures stakeholders are properly represented
-
Improves communication and control
-
Ensures that one plan will meet eve
-
Reduces the levels of management required in the project organisation
Frage 12
Frage
What levels of plan are recommended by PRINCE2?
Antworten
-
Project Plan
-
Project Plan and Stage Plan
-
Project Plan, Stage Plan and Team Plan
-
Project Plan, Stage Plan, Team Plan and Exception Plan
Frage 13
Frage
Which one of the following are described in a Product Description?
1. The component parts of the product
2. The products that are derived from this product
3. The skills needed to create the product
4. The method required to check the product
Frage 14
Frage
Which of the following is funded from a change budget?
Antworten
-
All changes to base-line costs of the project
-
Increased tolerance required by the Project Manager to complete a stage
-
Changes to approved base-lined products
-
The correction of an off-specification
Frage 15
Frage
What is risk appetite?
Antworten
-
Part of the project budget, used to pay for any additional activities required to manage risks
-
The funds the Project Board is willing to spend on the management of risk
-
Permissible deviation from planned expenditure without the need to escalate to the next higher authority.
-
An organisation's attitude towards risk-taking
Frage 16
Frage
Which role represents the 'delivering' level on the project management team?
Antworten
-
Project Board
-
Project Manager
-
Team Manager
-
Project Support
Frage 17
Frage
Which is a purpose of the Benefit Review Plan?
Antworten
-
Document the justification for the undertaking of a project.
-
Describe only residual benefits and those that could not be achieved during the lifecycle of the project
-
Provide a schedule for measuring the achievement of benefits
-
Provide the reasons for the project, for entry into the Business Case
Frage 18
Frage
Which is the purpose of the Configuration Item Record?
Antworten
-
Provide a summary of the status of all products at any one time
-
Provide any details of important links between Configuration Item
-
Support the creation of the project product breakdown structure
-
Include an analysis of an issue or risk which caused the product to change
Frage 19
Frage
Which is NOT a purpose of the Controlling a Stage process?
Antworten
-
Take corrective actions to control deviations from the Stage Plan
-
Recommend the tolerances for the next stage
-
Report progress to the Project Board
-
Assign work to be done
Frage 20
Frage
Which is a true statement regarding stages?
Antworten
-
A project can be scheduled without management stages
-
There can be several management stages within a technical stage
-
Several management stages can be scheduled to run concurrently
-
Technical stages and management stages should always end together
Frage 21
Frage
Which is a purpose of the Risk Management Strategy?
Antworten
-
Defines the techniques to be used when assessing project risks
-
Summarizes exposure to strategic, programme, project and operational risks
-
Recommends responses for each of the project risks
-
Identifies suitable risk owners for each of the projects risks
Frage 22
Frage
Which role can the Project Manager also perform?
Antworten
-
Executive
-
Project Assurance
-
Change Authority
-
Senior User
Frage 23
Frage
What are the three recommended types of issue?
Antworten
-
Off-specification, request for change and concession
-
Off-specification, request for change and problem/concern
-
Request for change, problem/ concern and Issue Report
-
Request for change, Issue Report and Risk
Frage 24
Frage
Which of the following is established within the Initiating a Project Process?
Antworten
-
The various ways in which the project can be delivered
-
Those who require project information have been identified
-
All of the information to develop the Project Brief is available
-
Any constraints which could affect the project have been removed
Frage 25
Frage
What term is used to describe when a risk might occur?
Antworten
-
Impact
-
Proximity
-
Probability
-
Evaluate
Frage 26
Frage
Within what process are Team Plans produced?
Frage 27
Frage
Identify the missing words in the following sentence.
If a Project Manager has the appropriate specialist skills and knowledge, they may also perform the role of [?] on the project.
Antworten
-
Senior Supplier(s)
-
Team Manager(s)
-
Project Assurance
-
Senior User(s)
Frage 28
Frage
Which statement is true for project stakeholders?
Antworten
-
Some have decision-making authority within the project environment
-
All are external to the corporate organisation
-
All are internal to the project management team structure
-
None have decision-making authority within the project environement
Frage 29
Frage
Which of the following is funded from a risk budget?
Antworten
-
Potential changes that may be required as the project progresses
-
Shortfall in estimating the development costs of the project's products
-
Additional activities to reduce, avoid, fall-back, transfer, share or enhance project risks
-
Production of a Risk Management Strategy
Frage 30
Frage
Which is NOT an objective of the Controlling a Stage process?
Antworten
-
Produce the Stage Plan for the next stage
-
Focus attention on delivery of the stage's products
-
Escalate threats to tolerances
-
Keep issues and risks under control
Frage 31
Frage
Which of the following describes an output?
Antworten
-
Any of the project's specialist products
-
The result of the change derived from using the project's products
-
The measurable improvement resulting from an outcome
-
A negative outcome
Frage 32
Frage
What is a purpose of the Quality theme?
Antworten
-
Defines the way in which the project will ensure that all products of the project are fit for purpose.
-
Define the procedures and responsibilities for the creation , maintenance and control of the project products.
-
Establish mechanisms to judge whether the project remains desirable and achievable
-
Enable the assessment of continuing project viability
Frage 33
Frage
Which factor should influence the length of a management stage?
Antworten
-
Frequency of Highlight Reports
-
The level of project risk
-
Availability of the Project Board
-
Requirement of a specialist team for an element of the development work
Frage 34
Frage
After the first stage, when are the Stage Plans for further stages produced?
Antworten
-
Near to the end of the current stage
-
After the completion of the current stage
-
When creating the Project Plan
-
At the start of the initiation stage
Frage 35
Frage
What is a risk cause?
Antworten
-
Negative consequence of a threat occurring
-
Explanation of the uncertainty which, should it occur, would create a problem
-
Positive consequence of an exploited opportunity
-
A known situation which creates uncertainty
Frage 36
Frage
Which product is a time driven control?
Antworten
-
End Stage Report
-
Exception Report
-
Checkpoint Report
-
Lessons report
Frage 37
Frage
Which is a purpose of the Project Product Description?
Antworten
-
Define the quality checks that will be used for the project's products.
-
Explain what the project must handover to achieve customer acceptance
-
Confirm the delivery time-scales for the project's products
-
Document the Project Manager's responsibilities for delivering the project's products
Frage 38
Frage
Which is a Purpose of the Change Authority?
Antworten
-
Determine the change budget for a project
-
Assess the impact of all requests for change
-
Reduce the number of requests for change that need to be escalated to the Project Board
-
Allow the Project Board to delegate the approval of all risks and Issue Reports
Frage 39
Frage
To which role does the Team Manager Report an exception situation?
Antworten
-
Project Manager
-
Project Board
-
Project Assurance
-
Project Support
Frage 40
Frage
What is the first step within a recommended risk management procedure?
Antworten
-
Assess
-
Identify
-
Implement
-
Plan
Frage 41
Frage
Which is the one of the six aspects of project performance that needs to be managed?
Antworten
-
Customers
-
People
-
Benefits
-
Processes
Frage 42
Frage
Which is a purpose of a Business Case theme?
Antworten
-
Establish mechanisms to monitor and compare actual achievements against those planned
-
Establish methods to judge whether the ongoing project is justified
-
Assess and control uncertain events or situations
-
Describe how, when and at what cost products can be delivered
Frage 43
Frage
What role is the responsible for creating a Team Plan in the Managing Product Delivery process?
Antworten
-
Project Manager
-
Team Manager
-
Project Support
-
Senior User
Frage 44
Frage
The incorporation of the primary stakeholders on the project management team supports what principle?
Frage 45
Frage
The incorporation of the primary stakeholders on the project management team supports what principle?
Frage 46
Frage
Which describe s risk appetite?
Antworten
-
An organisation's attitude towards risk-taking
-
Probable effect on the project delivering its objectives
-
Probable time-frame within which a risk may occur
-
Level of risk exposure that, when exceed, triggers an exception
Frage 47
Frage
Identify the missing word in the following sentence.
If the Project Manager needs to be know the results of a quality review, the [?] will provide a summary together with the date of any follow-up meeting.
Antworten
-
Stage Plan
-
Issue Register
-
Daily Log
-
Quality Register
Frage 48
Frage
How is the Project Initiation Documentation used during the Closing a Project Process?
Antworten
-
As the basis for comparing the original aim of the project against what was actually achieved
-
Provides the controls for the final stage of the project
-
Updated to include relevant lessons from previous projects
-
Provides the Project Product Description for approval by the Project Board
Frage 49
Frage
What role agrees the techniques, products and constraints for a Work Package with the Project Manager.
Antworten
-
Executive
-
Project Assurance
-
Senior Supplier
-
Team Manager
Frage 50
Frage
Identify the missing word in the following sentence?
PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
Antworten
-
product
-
activity
-
plan
-
benefit
Frage 51
Frage
Which is a purpose of a Configuration Item Record?
Antworten
-
Record quality issues found in quality test of the product.
-
Explain which procedure should be used for updating the Configuration Item Records of products completed in the stage
-
Explain which procedure should be used for transferring completed products into the operational and maintenance environment
-
Record the development status of a product in a completed Work Package
Frage 52
Frage
When authorizing a stage, in which product would the Project Board look for an explanation of any deviations from the approved plans that are within tolerance?
Frage 53
Frage
Which of the following are a purpose of the Benefits Review Plan?
1. Define how a measurement of the achievement of the Project's benefits can be made
2. Define what benefit assessment need to be undertaken
3. Define the project, in order to form the basis for its management and an assessment of its overall success
4. Define the activities required to measure the expected project's benefits
Frage 54
Frage
Which is a purpose of the Organisation theme?
Antworten
-
Define the total resource requirement of the project
-
Capture the project acceptance criteria
-
Define the responsibilities for managing teams
-
Establish mechanisms to judge whether the project is desirable and achievable
Frage 55
Frage
Which is a purpose of a Project Brief?
Antworten
-
Define how and when a measurement of the achievement of the project's benefits can be made
-
Define any lessons from previous projects and how they may affect this project
-
Communicate the quality techniques and standards to be applied to achieve the required quality levels
-
Provide sufficient information for the decision on whether to initiate the project
Frage 56
Frage
Which is a purpose of a Risk Management Strategy?
Antworten
-
Communicate how risk management will be implemented throughout the corporate organisation
-
Capture and maintain information on all identified risks relating to the project
-
Document specific actions for responding to risk
-
Describe the procedures and techniques for managing project risks
Frage 57
Frage
Which is not a purpose of the plans theme?
Antworten
-
Facilitate communication
-
Establish the project's structure of accountability
-
Define the means of delivering the products
-
Ensure targets are achievable
Frage 58
Frage
Which a purpose of the Directing a Project process?
Antworten
-
Enables the Project Board to exercise overall control of a project
-
Prepare a solid foundation for the project
-
Establish the prerequisites for the initiation of a project
-
Assign Work Packages
Frage 59
Frage
Which takes place within the Managing a Stage Boundary process?
Antworten
-
Periodic review of progress against the Stage Plan
-
Obtain approvals for all completed products
-
Escalation of Issue Reports created during the current stage
-
Review of the business justification for the project
Frage 60
Frage
Which is a type of Issue?
Frage 61
Frage
Which is a characteristic of a project?
Frage 62
Frage
Which is NOT a recommended response type to respond to a threat?
Antworten
-
Avoid
-
Reject
-
Share
-
Transfer
Frage 63
Frage
Which is an objective of the Managing a Stage Boundary process?
Antworten
-
Request authorisation to start the next stage
-
Ensure that all threats and opportunities for the current stage have been closed
-
Make certain that work on products allocated to the team for the next stage is authorised and agreed
-
Implement actions to resolve tolerance deviations from the Stage Plan
Frage 64
Frage
In what process are the project's risk management techniques and standards defined?
Frage 65
Frage
Which is a purpose of a Daily Log?
Antworten
-
Record the products and activities planned for the stage
-
Record informal issues
-
Record and track the status of all products produced during a stage
-
Update the Project Board on the progress of a stage
Frage 66
Frage
Which is an objective of the quality review technique?
Antworten
-
Determine whether a product has been created
-
Agree the quality method that will be applied to a product
-
Formulate ideas on how the product will be developed
-
Provide consultation with a range of interested parties on a product's fitness for purpose
Frage 67
Frage
When does the Directing a Project process start?
Antworten
-
On completion of the Starting up a Project process
-
On completion of the Initiating a Project process
-
When the Starting up a Project process commences
-
After the project has been authorised
Frage 68
Frage
What plan is mandatory?
Antworten
-
Team Plan
-
Exception Plan
-
Project Plan
-
Programme Plan
Frage 69
Frage
On which environment is PRINCE2 based?
Antworten
-
Information technology
-
Customer/Supplier
-
Procurement
-
Programmes
Frage 70
Frage
Which theme assesses and controls uncertainty within a project?
Antworten
-
Progress
-
Risk
-
Change
-
Plans
Frage 71
Frage
Which of the following is funded from a change budget?
Frage 72
Frage
Which is an aim of the Starting up a Project Process?
Antworten
-
Understand how and when the project's products will be delivered and at what cost
-
Ensure that there is authority to deliver the project's products
-
Do the minimum necessary in order to decide whether it is worthwhile to even initiate the project
-
Create the set of management products required to control the project
Frage 73
Frage
Which is a responsibility of the Project Manager?
Antworten
-
Delegating responsibility for changes to the Change Authority
-
Documenting the Communication Management Strategy
-
Approving Stage Tolerances
-
Approving the customer's quality expectation
Frage 74
Frage
Which is NOT a factor to consider when defining management stages?
Antworten
-
How long the project is
-
When Team Managers are available
-
Approving the customer's quality expectation
-
The amount of risk within the project
Frage 75
Frage
What process ensures that plans for achieving the expected benefits are managed and reviewed.