Frage 1
Frage
John is the Product Owner, during the Daily he realized that the work is delayed. What should he do?
Antworten
-
Nothing
-
Notify the CEO
-
Negotiate a reduction of the scope, guiding the team to focus on the goal
-
Cancel the sprint and change the team of developers
Frage 2
Frage
Frank is the Scrum Master and decided to cancel the Sprint. What should be the PO response?
Frage 3
Frage
Peter is a developer, tested in the user story and noticed a problem. Which action should Peter
Frage 4
Frage
Is Product owner and Scrum master possible in the same person for the same project?
Frage 5
Frage
According to the Scrum guide, can we use parts of Scrum?
Frage 6
Frage
Can we change the size of the sprint during its execution?
Frage 7
Frage
The best scenario for using Scrum is?
Frage 8
Frage
The maximum length of the Sprint Retrospective(its time box) is:
Antworten
-
3 hours for a monthly Sprint, proportionally less for shorter Sprints
-
4 hours for a monthly Sprint, proportionally less for shorter Sprints
-
As long as needed
-
1 day
Frage 9
Frage
How many meetings are defined in Scrum?
Frage 10
Frage
What is the purpose of the daily meeting?
Antworten
-
Team meeting for inspection and adaptation
-
A formality of Scrum
-
To inform the Product Owner
-
None of the given answers
Frage 11
Frage
When does the development team create the sprint backlog?
Antworten
-
daily
-
planning
-
review
-
retrospective
Frage 12
Frage
At the end of the sprint is a product increment that will go into production?
Frage 13
Frage
After the start of the sprint, what product owner will do?
Frage 14
Frage
Is it true that the Scrum Master is responsible for the ROI of the product?
Frage 15
Frage
What is the role of the project manager in the Scrum framework?
Frage 16
Frage
When to cancel a sprint?
Frage 17
Frage
Scrum master ensures that Scrum is being applied correctly?
Frage 18
Frage
How does the product owner help the development team?
Antworten
-
Detailed all product backlog
-
Clearing up doubts about backlog items
-
With the help of requirements analyst
-
He does not help the team.
Frage 19
Frage
When a backlog item was set to high priority, for what situation should it be considered?
Antworten
-
Definition of done
-
Definition of Timebox
-
Definition of ready
-
None of the answers
Frage 20
Frage
Does the development team need to be multifunctional?