PO - Test 2

Beschreibung

Para el examen de product owner
Willy Casana Saavedra
Quiz von Willy Casana Saavedra, aktualisiert more than 1 year ago
Willy Casana Saavedra
Erstellt von Willy Casana Saavedra vor fast 6 Jahre
73
0

Zusammenfassung der Ressource

Frage 1

Frage
1. Definition of “Done” is
Antworten
  • a) Initially defined per product by Scrum Team, but may change throughout the product development duration
  • b) Initially defined per Scrum Team, and doesn’t change
  • c) Defined after first Sprint based on the new insights obtained from first Sprint Review

Frage 2

Frage
2. Which of the following statements are true? Select all that apply
Antworten
  • a) After Sprint Planning, a sprint cannot proceed without complete requirement specification
  • b) After Sprint Planning, a sprint cannot proceed without a Sprint Goal
  • c) After Sprint Planning, a sprint can proceed without complete Sprint Backlog
  • d) After Sprint Planning, a sprint cannot proceed without complete architecture

Frage 3

Frage
3. A Development Team is self-organized and empowered. It is also the authority on deciding what business needs are required to be developed
Antworten
  • a) True
  • b) False

Frage 4

Frage
4. Who decides the duration of the Sprint?
Antworten
  • a) Product manager
  • b) Scrum Master
  • c) Development Team
  • d) Scrum Team

Frage 5

Frage
5. A Product Owner is not available for Scrum events and not supportive enough for Development Team. The next immediate accountability is with
Antworten
  • a) Development Team that needs to cancel the Sprint
  • b) Stakeholders that need to get a written commitment from Product Owner
  • c) Product Owner’s manager who needs to engage the Development Team and understand their problems
  • d) Scrum Master, who needs to educate Product Owner on his role

Frage 6

Frage
6. When a Product Backlog is retired?
Antworten
  • a) When the Product Owner retires
  • b) When all the Sprints are over
  • c) When the Product retires
  • d) When the Customer provides the sign-off on completion of the project

Frage 7

Frage
7. A Product Owner cannot send a representative (delegate) to the Sprint Review.
Antworten
  • a) True
  • b) False

Frage 8

Frage
8. A Product Owner is also knowledgeable on technology. In addition to product requirements, they also impose some technical conditions that the product should meet. These conditions must be added to
Antworten
  • a) Product Backlog
  • b) Sprint Backlog
  • c) Definition of “Done”

Frage 9

Frage
9. An increment is
Antworten
  • a) The sum of the value of all increments from previous iterations integrated with the Product Backlog Items “done” in latest Sprint
  • b) The sum of Product Backlog Items selected into Sprit Backlog
  • c) The sum of Product Backlog Items “done” in latest Sprint

Frage 10

Frage
10. What are the true statements?
Antworten
  • a) Scrum Team is responsible for formulating a Sprint Goal
  • b) When existing Product Backlog Items in the Sprint Backlog are modified, the Sprint Goal is bound to become invalid
  • c) The coherence between Product Backlog items is made transparent by Sprint Goal. Lack of coherence will lead to them working individually
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Metodología Scrum
DUVAN ARLEY CAÑON RAMIREZ
Scrum Fundamentals
Xentinel Romero Pérez
METODOLOGÍAS ÁGILES Y RUP
ANGELA SARAY BURBANO VALDIVIESO
Mis Diapositivas
Noelia Huamaní Tellez
Metodologías ágiles
Yesid Rangel