Frage 1

Frage
You and your team are analyzing information about the results of the activities executed last week. You are organizing
Antworten
  • a. The formal communication channels
  • b. The communication infrastructure
  • c. The project Scope Statement
  • d. Work performance information

Frage 2

Frage
What type of report would the Project Manager use to show what is expected to be in the next month on the project?
Antworten
  • a. Earned Value Report
  • b. Status Report
  • c. Forecast Report
  • d. Progress Report

Frage 3

Frage
Which of the following would a Project Manager need to create to prepare a project progress report?
Antworten
  • a. Work results
  • b. Change Request
  • c. Project archives
  • d. Status reports

Frage 4

Frage
At the beginning of planning, you identify a important stakeholder who are not supporting the project. During a communication planning session you recommend use:
Antworten
  • a. The support of management to change this stakeholder because he is not supporting the project team
  • b. The job description of this stakeholder to explain him the importance of his support
  • c. A communication style assessment to identify the preferred communication method, format and content for communication activities with this stakeholder
  • d. The avoiding style of conflict management.

Frage 5

Frage
What type of report would the Project Manager use to compare what has been completed to what was scheduled to be done?
Antworten
  • a. Earned Value Report
  • b. Status Report
  • c. Variance Report
  • d. Progress Report

Frage 6

Frage
When a project manager is engaged in negotiations, nonverbal communication skill are of:
Antworten
  • a. Little importance
  • b. Major importance
  • c. Importance only when cost and schedule objectives are involved
  • d. Importance to ensure he wins the negotiation.

Frage 7

Frage
In the communication model, who validates that the receiver has received and understood the message from the sender correctly? PMBOK p371
Antworten
  • a. Both the sender and receiver
  • b. Project Manager
  • c. Receiver
  • d. Sender

Frage 8

Frage
The Charter on a project would be viewed as what type of communication?
Antworten
  • a. Formal
  • b. Formal Written
  • c. Contract
  • d. Verbal

Frage 9

Frage
Which of the following aspects of leadership is MOST important for a project manager?
Antworten
  • a. Communication
  • b. Team building
  • c. Technical expertise
  • d. Project control

Frage 10

Frage
Which of the following is a result of the Executing process group?
Antworten
  • a. Plan Communications Management.
  • b. Issue log
  • c. Monitor Communications
  • d. Manage Stakeholders Engagement.
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Gedichtanalyse
AntonS
03_Offene Handelsgesellschaft
Stefan Kurtenbach
Projektmanagement
zok42.com
Grundbegriffe der Kunst
K Gal
Vetie - Allgemeine Pathologie
Fioras Hu
Vetie Immunologie - Klausur 2016
Janneke Bosse
Steop Hist Fragen
Adrienne Tschaudi
Vetie-Chirurgie 2017
Ju Pi
Quiz MS-4.2 Foliensatz II_Teil 1
Bernd Leisen