Zusammenfassung der Ressource
Frage 1
Frage
Earned Value Management(EVM) is commonly used to :
Antworten
-
a. Analysis of the value of the equipment that has been installed as of the status date.
-
b. Analysis of the sum of the labor costs, which have been incurred on the project to date.
-
c. A method of project performance measurement.
-
d. A method of measuring the amount of money that has been spent to date.
Frage 2
Frage
An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) is known as:
Antworten
-
a. Parametric Estimating
-
b. Analogous Estimating
-
c. Bottom-up Estimating
-
d. Historical Analysis
Frage 3
Frage
Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with:?
Antworten
-
a. Inadequacies in the original estimate
-
b. Anticipated but not certain events
-
c. Unanticipated events
-
d. Anticipated and certain events
Frage 4
Frage
Activity cost estimates are used as an input into which process??
Antworten
-
a. Estimate Costs
-
b. Determine Budget
-
c. Cost Analysis
-
d. Control Costs
Frage 5
Frage
As a project manager, your BEST use of the project cost baseline would be to:?
Antworten
-
a. Measure and monitor cost performance on the project.
-
b. Track approved changes.
-
c. Calculate team performance bonuses.
-
d. Measure and report on variable project costs.
Frage 6
Frage
An activity cost estimate includes all of the following resource categories EXCEPT:?
Antworten
-
a. Labor
-
b. Materials
-
c. Equipment
-
d. Time shortages.
Frage 7
Frage
All of the following are true about estimate costs, EXCEPT:?
Antworten
-
a. Are generally expressed in units of currency (dollars, euro, yen, etc.), although in some instances other units of measure, such as staff hours or staff days ares used.
-
b. The costs are estimated for all resources that will be charged to the project.
-
c. Information in the risk register should not be used to adjust cost estimates.
-
d. Cost estimates are quantitative assessments of the likely costs for resources required to complete project activities.
Frage 8
Frage
The Project Manager is in the process of estimate costs. What will he get?
Antworten
-
a. The budget of the project
-
b. Basis of estimates, cost estimates and project documents updates
-
c. Cost estimates of the work packages
-
d. Entire costs of the deliverables
Frage 9
Frage
Analogous estimating:?
Antworten
-
a. Integrated bottom-up estimating techniques with relevant statistical relationship to estimate the cost of the current project
-
b. Relies on the actual cost of previous, similar projects as the basis for estimating the cost of the current project.
-
c. Is used most frequently in the later stages of a project.
-
d. Summarizes estimates for individual work packages to estimate the cost of the current project.
Frage 10
Frage
All of the following are required to establish cost baseline EXCEPT:?