Zusammenfassung der Ressource
Frage 1
Frage
The degree to which a particular stakeholder may be able to positively or negatively affect a Project is his or her:?
Antworten
-
a. Level of engagement.
-
b. Level of interest.
-
c. Level of commitment.
-
d. Level of influence.
Frage 2
Frage
A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage the situation?
Antworten
-
a. Say NO to the stakeholder a few times to dissuade him for submitting more changes.
-
b. Get the stakeholders involved in the project as early as possible.
-
c. Talk to stakeholder´s boss to find ways of directing the stakeholder´s activities to another project.
-
d. Ask that the stakeholder not be included in the stakeholder listing.
Frage 3
Frage
Stakeholders can be identified in which project management process group?
Antworten
-
a. Initiating, planning, executing and monitoring and controlling.
-
b. Initiating and planning.
-
c. Planning, and monitoring and controlling.
-
d. Monitoring and controlling, and closing.
Frage 4
Frage
In considering project stakeholders, the project management team must do all of the following EXCEPT:?
Antworten
-
a. As much as possible, create conflicts among stakeholders to allow the project team to get its work done.
-
b. Identify the stakeholders.
-
c. Determine stakeholders´ requirements and expectations.
-
d. To the extent possible, manage stakeholders´influence in relation to the requirements to ensure a successful project.
Frage 5
Frage
In the use of the communications model, all of the following would be considered by the Project Manager except:
Antworten
-
a. Sender
-
b. Receiver
-
c. Language
-
d. Message
Frage 6
Frage
All of the following are responsibilities of the project manager EXCEPT:?
Antworten
-
a. Carefully select the appropriate stakeholders for the project.
-
b. Get stakeholders’ sign-off that the requirements are finalized
-
c. Figure out when stakeholders will be involved in the project and how extensively.
-
d. Ask stakeholders to let you know about problems in project communication and relationships.
Frage 7
Frage
Project stakeholders should be classified according to their interest, influence, and involvement in the project because:
Antworten
-
a. Such a classification makes it easier to assign responsibilities to stakeholders.
-
b. Project manager has limited time and it must be used efficiently.
-
c. Stakeholders need to know which group they belong to in terms of interest, influence, and involvement in the project.
-
d. Stakeholders usually have very little time to spend on the project.
Frage 8
Frage
A project coordinator is distinguished from a project manager in that:?
Antworten
-
a. A project coordinator has no decision-making power.
-
b. A project coordinator has less decision-making power.
-
c. A project coordinator has no authority to assign work.
-
d. A project coordinator takes on larger projects than a project manager.
Frage 9
Frage
A stakeholders engagement assessment matrix can be used to identify:?
Antworten
-
a. Communication gaps.
-
b. Additional stakeholders.
-
c. Key relationships between stakeholders.
-
d. Skill levels of stakeholders.
Frage 10
Frage
A Project Manager wants to more extensively involve the stakeholders on the Project. Which of the following would be the best way to accomplish this?
Antworten
-
a. Have a stakeholders periodically review the list of project requirements.
-
b. Invite the stakeholders to attend project status meetings.
-
c. Send status reports to the stakeholders.
-
d. Update the stakeholders on the status of all project changes.