Frage 1
Frage
Which of the following would NOT be contained in the risk management plan?
Antworten
-
a. A risk breakdown structure.
-
b. A description of the overall approach to risk on the project.
-
c. Risk roles and responsibilities.
-
d. A list of identified risks.
Frage 2
Frage
The risk register is not an input to which of the following processes?
Frage 3
Frage
Which of the following is NOT a tool or technique for gaining expert opinion as it relates to risk?
Antworten
-
a. Brainstorming.
-
b. Checklists
-
c. Monte Carlo analysis.
-
d. Expert interviews.
Frage 4
Frage
Which of the following is not a type of risk attitude of organizations?
Antworten
-
a. Risk appetite.
-
b. Risk tolerance.
-
c. Risk response.
-
d. Risk intolerance.
Frage 5
Frage
Which of the following statements about risk analysis is false?
Antworten
-
a. Quantitative risk analysis can only be performed on the risks on which a qualitative risk analysis has already been performed.
-
b. Qualitative risk analysis is usually performed before quantitative risk analysis.
-
c. An updated risk report is the output of both qualitative risk analysis and quantitative risk analysis.
-
d. The risk register is an input to both qualitative risk analysis and quantitative risk analysis.
Frage 6
Frage
What is the output of a decision tree analysis?
Antworten
-
a. List of decisions that can be made.
-
b. Expected monetary value of each option.
-
c. Recommended corrective actions.
-
d. Cost of managing the risk that was analyzed.
Frage 7
Frage
Which of the following is a correct statement about secondary risks?
Antworten
-
a. These are the residual risks.
-
b. These are the risks that have medium or low priority
-
c. These are the risks that have been transferred
-
d. These are the risks that can result from responses to the identified risks.
Frage 8
Frage
Which of the following statements is TRUE regarding risk?
Antworten
-
a. All risk events must be threats
-
b. All risk events are uncertain.
-
c. All risk events are negative.
-
d. All risk events should be covered by a contingency budget amount.
Frage 9
Frage
Which of the following is not an output of the quantitative risk analysis??
Antworten
-
a. Probabilities of meeting the project objectives, such as cost and schedule
-
b. Estimate of the project cost
-
c. A list of risks prioritized based on the total effect of each risk on the overall project objectives
-
d. A risk-related contractual agreement
Frage 10
Frage
Which of the following would NOT be a strategy for dealing with negative risk?
Antworten
-
a. Avoid.
-
b. Transfer.
-
c. Share.
-
d. Mitigate.
Frage 11
Frage
Which of the following is not an information gathering or analysis technique used in the identify risks process?
Antworten
-
a. Brainstorming
-
b. Document analysis
-
c. SWOT analysis
-
d. Web browsing
Frage 12
Frage
Which of the following is not a valid risk response?
Antworten
-
a. Risk acceptance
-
b. Risk sharing
-
c. Risk mitigation
-
d. Risk rejection
Frage 13
Frage
What is the BEST source of information about potential risk on your project?
Antworten
-
a. Computer risk analysis.
-
b. Interviews with team members from other projects.
-
c. Historical records from similar projects.
-
d. Your own experience in this industry.
Frage 14
Frage
Which of the following is not a common constraint to all the projects?
Antworten
-
a. Resources
-
b. Scope
-
c. Time
-
d. Skill set
Frage 15
Frage
Which of the following is an output of Identify Risks??
Antworten
-
a. Risk register.
-
b. Probabilistic analysis.
-
c. Risk-related contractual agreements.
-
d. Recommended cash reserves.