Zusammenfassung der Ressource
Frage 1
Frage
Which is NOT an objective of the Initiating a project process?
Antworten
-
Ensure there is a common understanding of who will take significant project management roles within the project.
-
Ensure there is a common understanding of how and when the project's products will be achieved and at what cost.
-
Ensure there is a common understanding of the reasons for doing the project, the benefits expected and the associated risks.
Frage 2
Frage
Which of the following is NOT a PRINCE2 management product?
Frage 3
Frage
The Business Case will contain a summary of key risks, where will the details of all the risks be stored?
Frage 4
Frage
Which of the following is defined as part of setting up controls for the project?
Antworten
-
Tolerances for delegated authority.
-
Quality management procedure.
-
Tools and techiques for managing risks
-
How information from outside of the project environment will be sent or received.
Frage 5
Frage
Information on project controls is included in which management product?
Frage 6
Frage
The Outline Business Case is prepared as part of which process?
Antworten
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
-
Directing a Project
Frage 7
Frage
The information gathered in the Starting Up a Project process should answer what basic uestions?
Antworten
-
Do we have a viable and worthwhile project?
-
Do we know who thought of this idea?
-
Do we care about the outcome at this stage?
-
Do we solve the problem now or later?
Frage 8
Frage
What management product produced in Starting Up a Project is submitted to the Project Board with a request to initiate a Project?
Frage 9
Frage
How does the Starting up a Project process support the defined roles and responsibilities principle?
Antworten
-
By nominating the project manager responsible for project assurance.
-
By appointing the executive, the project manager and the project management team.
-
It doesn't.
-
By ensuring lessons from previous projects are captured and analyzed.
Frage 10
Frage
Who is responsible for creating the Initiation Stage Plan?
Antworten
-
Project Manager
-
Project Board
-
Team Manager
-
Project Assurance