Frage 1

Frage
You are the Project Manager for a large construction project. While reviewing the expenditures, you realize that you are 20% over budget. What process group are you working in?
Antworten
  • Closure
  • Execution
  • Planning
  • Monitor & Control

Frage 2

Frage
What is the main benefit of a balanced matrix organization over a projectized organizational structure?
Antworten
  • As a Project Manager, you have a great deal of authority
  • More efficient use of resources
  • Reporting to a functional manager
  • Reporting to 2 Managers

Frage 3

Frage
As the Sponsor on a large, multi-national hydroelectric power project, during the execution phase, your primary responsibilities are to:
Antworten
  • Provide the financial resources and champion the project
  • Manage a group of interrelated projects
  • Manage the Project Team
  • Provide status updates to the customer

Frage 4

Frage
Name the 5 project management process groups.
Antworten
  • Initiating, Planning, Executing, Monitoring & Control, Closing
  • Planning, Executing, Monitoring, Integrated Change, Closing
  • Business Case, Planning, Executing, Monitoring & Control, Closing

Frage 5

Frage
You are hired to manage an exciting new project for a software development company making CRM tools. You are unfamiliar with the project management resources available in the company. Who should you go to for help identifying the resources and best practices?
Antworten
  • Project Sponsor
  • Operations Manager
  • Other Project Managers
  • Project Management Office

Frage 6

Frage
As you progress through the project life cycle:
Antworten
  • Risk increases and cost of changes increases
  • Cost of changes decreases and risk increases
  • Risk decreases and cost of changes increases
  • Cost of changes decreases and risk decreases

Frage 7

Frage
The purpose of the Closer Process Group is:
Antworten
  • Complete the work as quickly as possible
  • Analyze the project risks at the end of the project
  • Inspect the outputs to ensure the quality is as planned
  • Formally complete the project

Frage 8

Frage
In the Statement Of Work, you provide:
Antworten
  • Project charter
  • Market demand analysis
  • Change control tools you will use
  • Scope description

Frage 9

Frage
The output of the Develop Project Charter process is:
Antworten
  • Project charter
  • Project Management Plan
  • Work performance data
  • Business case

Frage 10

Frage
According to the PMBOK all the following are types of project constraints except:
Antworten
  • Scope
  • Portfolio Alignment
  • Risks
  • Schedule

Frage 11

Frage
You are the Project Manager for a project that will design and build the iPhone X, the latest in mobile phone technology. The requirements call for a new production facility in Asia. Immediately after working with Senior Management to create a business case and statement of work for the new production facility, what document will you want to produce?
Antworten
  • Project document updates
  • Lessons learned
  • Project plan
  • Project charter

Frage 12

Frage
The ideal Project Team size is?
Antworten
  • 10-15
  • 3-6, 6-9

Frage 13

Frage
Your project has been officially approved by your sponsor, what process group will you move from and which process group will you move to?
Antworten
  • Planning to execution
  • Initiation to execution
  • Planning to initiation
  • Initiation to planning

Frage 14

Frage
All the following are examples of expert judgement except:
Antworten
  • PMO
  • Tech manuals
  • PM information system
  • Professional associations

Frage 15

Frage
In Project Integration Management, as you develop the Project Management Plan, you will:
Antworten
  • Direct and manage the planning of work defined in the Project Charter and implement to achieve the project’s objectives
  • Provide the project schedule which is derived from progress against the schedule baseline.
  • Validate plans and changes from Perform Integrated Change Control and ensure that the changes are appropriately executed
  • Define, prepare, and coordinate all subsidiary plans and integrate them into a comprehensive plan.

Frage 16

Frage
The process group where you will identify if any changes to the plan are needed and initiate those plans is:
Antworten
  • Monitoring and control
  • Executing
  • Planning
  • Initiating

Frage 17

Frage
The organizational structure that gives project managers a very high degree of authority over their project is:
Antworten
  • Functional
  • Projectized
  • Weak matrix
  • Strong matrix

Frage 18

Frage
The largest portion of the projects budget will be expended in what process group?
Antworten
  • Planning
  • Execution
  • Closing
  • Monitoring and control

Frage 19

Frage
All of the following are examples of Enterprise Environmental Factors EXCEPT:
Antworten
  • Established communication channels
  • Organizational culture
  • Project management information system
  • Project charter

Frage 20

Frage
The leader of the project is working on completing a database upgrade but cannot get the additional resources she needs to be able to complete the project. The rest of the project team is working on daily operations work. The leader has not been given the authority to put additional resources on the project. What is the organizational structure this team is working in?
Antworten
  • Project team
  • Strong matrix
  • Projectized
  • Functional

Frage 21

Frage
Portfolio management refers to:
Antworten
  • Applying resource-leveling heuristics across all the organization's projects to achieve the organization's strategic objectives.
  • Managing the levels of functional authority to facilitate project decision making.
  • Managing various contents of the project file
  • The centralized management of one or more portfolios to achieve strategic objectives.

Frage 22

Frage
A project has all of the following characteristics except:
Antworten
  • Short duration
  • Unique
  • Temporary endeavor
  • Specific end

Frage 23

Frage
A program is:
Antworten
  • Project over 1$ mill
  • Group of related projects, subprograms & program activities managed in a coordinated way.
  • Sequence of steps constituting a project
  • Group of related tasks lasting one year or less

Frage 24

Frage
The project manager has the lowest level of authority in this type of organization:
Antworten
  • Projectized
  • Weak matrix
  • Strong matrix
  • Functional

Frage 25

Frage
Project Management Process Groups are:
Antworten
  • Genearlly, discrete, one-time events
  • Overlapping activities that occur throughout the project
  • Overlapping activities that generally occur at the same level of intensity within each phase of the project.
  • Discrete, repetative events that occur generally at the same level of intensity throughout each phase of the project.

Frage 26

Frage
Decomposition is:
Antworten
  • Creating subproject to ensure scope
  • Organizing and defining the complete scope
  • Subdividing project scope & deliverables into more manageable components
  • Documents planning assumptions

Frage 27

Frage
You are exactly half way through a construction project when the customer insists that you add a third entry way. What process will you need to follow to make the updates?
Antworten
  • Validate scope
  • Brainstorming
  • Control scope
  • Collect requirements

Frage 28

Frage
What process group determines how the scope is defined?
Antworten
  • Create WBS
  • Control scope
  • Plan scope management
  • Define scope

Frage 29

Frage
Requirements must be:
Antworten
  • A component of change control
  • A validated for conformity as part of the project scope statement
  • An out put of the Validate Scope process
  • Measureable

Frage 30

Frage
All of the following are tools for collecting requirements EXCEPT:
Antworten
  • Focus groups
  • Observations
  • Interviews
  • Quality assurance

Frage 31

Frage
The process that documents stakeholder needs to meet the projects objectives are:
Antworten
  • Decomposition
  • WBS
  • Validate scope
  • Collect requirements

Frage 32

Frage
Acceptance Criteria is:
Antworten
  • Part of the lessons learned
  • Unique & verifiable product, result or capability for a product
  • A set of conditions that is required to be met before deliverables are accepted.
  • Given by the PMO

Frage 33

Frage
The project scope statement is:
Antworten
  • Determining, documenting, and managing stakeholder needs and requirements.
  • Set of conditions that is required to be met before deliverables are accepted.
  • The features and functions that characterize a project.
  • Description of the project, major deliverables, assumptions and constraints

Frage 34

Frage
The WBS is:
Antworten
  • Project schedule components organized by work package
  • Work breakdown system
  • Project document updates
  • a hierarchical decomposition of the total scope of work to be carried out by the project team

Frage 35

Frage
The lowest level of WBS components are:
Antworten
  • Quality requirements
  • Acceptance criteria
  • WBS dictionary
  • Work packages

Frage 36

Frage
The project scope statement includes all of the following except:
Antworten
  • Scope baseline
  • Scope description
  • Deliverable
  • Acceptance criteria

Frage 37

Frage
One of the outputs for the validate scope process is:
Antworten
  • Acceptance criteria
  • Resources required
  • Description of work
  • Accepted deliverables

Frage 38

Frage
Which of the following provides more detailed information?
Antworten
  • Scope statement
  • Scope baseline
  • WBS
  • WBS dictionary

Frage 39

Frage
You are the leader of the Project Management Office for your company. One day, an experienced Project Manager asks why he should go to the trouble of creating a Work Breakdown Structure for his new project. The best answer would be:
Antworten
  • It is optional
  • It is a legal requirement for external projects
  • It will help you organize project deliverables & work
  • It helps to verify project quality

Frage 40

Frage
What is the purpose of the validate scope process?
Antworten
  • Collect requirements for the project
  • Make needed changes to the project charter
  • Acceptance of the project deliverables
  • Create WBS

Frage 41

Frage
Create WBS is in which process group?
Antworten
  • Execution
  • Monitoring & control
  • Initiation
  • Planning

Frage 42

Frage
Gold plating is:
Antworten
  • Decreasing risk by providing project safeguards
  • Changing requirements to improve the project
  • Giving a customer more than they want
  • Taking features away to keep costs down

Frage 43

Frage
Project scope is:
Antworten
  • Making sure there is no gold plating in the project
  • The value created by completing a project under budget and on schedule
  • Determining, documenting & managing stakeholder needs and requirements
  • Work performed to deliver a product, service or results with specified features and functions

Frage 44

Frage
What is the WBS typically used for?
Antworten
  • Defines the stakeholder list
  • Identifies the logical person to be the sponsor
  • Defines the level of reporting that the seller provides the buyer
  • Organizes & defines the work elements required to create the required deliverables

Frage 45

Frage
Which of the following processes is not an output of the control scope process?
Antworten
  • Work performance information
  • Change requests
  • Project document updates
  • Accepted deliverables

Frage 46

Frage
You are managing a global project that involves stakeholders and several international locations. You are likely to consult the WBS dictionary to find:
Antworten
  • Strengths, weaknesses, opportunities, and threats of key stakeholders and their impact upon the WBS.
  • Detail deliverable, activity, and scheduling information about each component in the WBS.
  • Accepted deliverables
  • High level task information for the schedule management plan

Frage 47

Frage
The following is an example of a constraint associated with the project scope that limits the team's options and scope definition:
Antworten
  • Threat of a strike
  • Quality of analysis
  • Predefined budget or any imposed dates/schedule milestones that are issued by the customer or performing organization.
  • Existing relationships with sellers, suppliers, or others in the supply chain

Frage 48

Frage
An output of the define scope process is:
Antworten
  • WBS
  • Scope & schedule delays control plan
  • Project scope statement
  • Resource breakdown structure

Frage 49

Frage
The difference between the Project Charter and the Project Scope Statement is:
Antworten
  • The Project Scope Statement lists high level technical requirements and regulatory constraints.
  • The Project Scope Statement provides a high level description of scope elements.
  • The Project Charter provides a high level description of scope elements.
  • The Project Charter lists project deliverables in smaller, more manageable components.

Frage 50

Frage
Control scope:
Antworten
  • Updates the WBS dictionary to ensure all tasks are accounted for
  • Ensures risks are mitigated
  • Plans how to determine scope
  • Manages changes to the scope baseline

Frage 51

Frage
Plan schedule management is:
Antworten
  • Identifying and documenting logical relationships among project activities.
  • Analyzing activity sequences to create the project schedule baseline.
  • Monitoring the status of project activities to ensure they are performing to expected specifications in regards to project constraints.
  • Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

Frage 52

Frage
The duration of a milestone is:
Antworten
  • 0 days
  • 1 days
  • 10 days

Frage 53

Frage
What is the best tool for determining the overall length of a project?
Antworten
  • WBS
  • Precedence diagram
  • Expert judgement
  • Pie chart

Frage 54

Frage
The critical path is:
Antworten
  • The shortest sequence duration
  • The sequence of activities that are determined to be key activities for successful project execution
  • The path with the highest number of activities
  • The shortest amount of time you can get the project done in

Frage 55

Frage
The maximum amount of slack in the critical path is:
Antworten
  • +1
  • -1
  • 0

Frage 56

Frage
The Critical Path has a duration of 10. There is an independent sequence, XYZ. Activity X has a duration of 2. Activity Y has a duration of 3. Activity Z has duration of 2. The EAC is 4000. The total float of XYZ is:
Antworten
  • 0
  • 3

Frage 57

Frage
To complete your project on time, you ask for additional overtime for your project team. This is an example of:
Antworten
  • Fast tracking
  • Crashing
  • Critical chain
  • Schedule network analysis

Frage 58

Frage
Lag is:
Antworten
  • The time an activity will start sooner than its dependency
  • Determined by the critical chain
  • The time when an activity is dependent on another activity to start at the same time
  • The time an activity will start later than its dependency

Frage 59

Frage
You ask your construction manager how long it will take to complete the new server room. He gives you a likely estimate of 6 weeks, but says it may take as long as 10 weeks. He may be able to get it done in 4 weeks if everything goes well. Calculate your PERT estimate of how long it will take to complete the server room.
Antworten
  • 20 weeks
  • 6.3 weeks
  • 6 weeks
  • 4.6 weeks

Frage 60

Frage
The method where buffers are added to each activity to account for resource availability is:
Antworten
  • Critical path
  • Resource leveling
  • Critical chain
  • Crashing

Frage 61

Frage
A benefit of bottom-up estimating is:
Antworten
  • Determines resources need to schedule the project
  • Ability to automate your estimate
  • Allows for what-if analysis
  • A more accurate estimate

Frage 62

Frage
One of the outputs of the Develop Schedule process group that helps create the Project Management plan is:
Antworten
  • Sequence activities
  • Work package acceptance criteria
  • Schedule baseline
  • Scope baseline

Frage 63

Frage
The minimum project duration is 6 months. Another path, series ABCD, will take 4 months to complete. In addition, series EFG will take 2 months. How much float is in ABCD?
Antworten
  • 4 months
  • 0 months
  • 2 months
  • 12 months

Frage 64

Frage
Which of the following allows you to accomplish tasks in parallel when they normally would be done in sequence?
Antworten
  • Fast tracking
  • Critical chain
  • Resource leveling
  • Crashing

Frage 65

Frage
Analogous estimating is a technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project. What is the disadvantage of this technique?
Antworten
  • More costly
  • Takes more time
  • Requires using PERT
  • Less accurate

Frage 66

Frage
Your project will run through the summer when your employees generally take vacation. To account for the risk of lower resource availability in your project plan, you could use:
Antworten
  • Critical chain
  • Crashing
  • Resource leveling
  • Fast tracking

Frage 67

Frage
You need Activity A in your project plan to start 3 days before Activity B. Activity B would be called:
Antworten
  • Lag
  • Lead
  • Critical chain

Frage 68

Frage
You are creating the Schedule Baseline for a multi-national government pipeline project that will deliver oil faster and cheaper. You need to know how long it will take to build the new capacity. Who would you consult to determine the time required?
Antworten
  • Government experts
  • Project sponsor
  • Scrum master
  • The people that will be doing the work

Frage 69

Frage
An example of a finish to finish relationship is:
Antworten
  • Rocket fuel tanks that must be filled prior to launch
  • A dinner cruise that sells tickets up until departure
  • Dinner when all of the food is ready at the same time
  • Drag racing

Frage 70

Frage
Parametric estimating:
Antworten
  • Accounts for risk
  • Is where an algorithm is used to calculate cost or duration based on historical data
  • Focuses on planning at a daily activity level

Frage 71

Frage
In rolling wave planning:
Antworten
  • Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.
  • The work to be accomplished in the near term is planned in detail, the work in the more distant future is planned at a higher level.

Frage 72

Frage
Analogous duration estimating is:
Antworten
  • Frequently used to estimate project duration when there is a limited amount of detailed information about the project
  • A bottom up estimating technique
  • Based on multiple duration estimating
  • Generally more accurate than other duration estimating methods when expert judgement is used

Frage 73

Frage
To enter logical dependencies in MS project you enter the dependency in which column:
Antworten
  • Predecessor
  • Resource
  • Linkages
  • Critical chain

Frage 74

Frage
Outputs from the Estimate Activity Resources process include:
Antworten
  • Activity resource requirements
  • Salary schedules for various project human resources
  • Risk register
  • Activity list

Frage 75

Frage
An example of a mandatory dependency is:
Antworten
  • A dependency established based on knowledge of best practices within a particular application area
  • A dependency established based on some unusual aspect of the project where a specific sequence is desired
  • On a construction project, to erect the superstructure only after the foundation has been built.
  • On a software development project, to start design only after completion and approval of all project requirements.

Frage 76

Frage
Earned Value is:
Antworten
  • Actual cost of work scheduled
  • AC / % Complete
  • Measure of work expressed in terms of budget authorized for that work

Frage 77

Frage
A SPI is 1.4 - your project is?
Antworten
  • Ahead of schedule
  • Over budget
  • Under budget

Frage 78

Frage
You are 1 month into your project. You need to determine how much your project will cost when it is done. What Earned Value metric will you use to determine the cost?
Antworten
  • BAC
  • EAC

Frage 79

Frage
Project XYZ has a Schedule Variance of -500. That means that:
Antworten
  • The SPI is 500
  • Your project is behind schedule

Frage 80

Frage
Your EAC is 4000. The PV is 1000. The AC is 400. What is the ETC?
Antworten
  • -10
  • 10
  • 2600
  • 3600

Frage 81

Frage
All of the following are processes included in Project Cost Management except:
Antworten
  • Determine budget
  • Estimate activity resources
  • Estimate costs
  • Control costs

Frage 82

Frage
Planned value is:
Antworten
  • Actual cost of work
  • Realized cost of work
  • Authorized budget assigned to the scheduled work
  • Difference btwn earned value and actual cost

Frage 83

Frage
If the earned value is 40,000, the planned value is 50,000, and the actual cost is 45,000, what is the cost performance index?
Antworten
  • 1.13
  • .88
  • 1.27

Frage 84

Frage
In class, we discussed that in Initiation, a Rough Order of Magnitude estimate should be within what percent?
Antworten
  • + - 25%
  • + - 3%
  • + - 50%

Frage 85

Frage
Your project is behind schedule and over budget. When calculating the project’s CPI, you will get:
Antworten
  • number greater than 1
  • number less than 1

Frage 86

Frage
What metric will show how efficiently the project team is using time?
Antworten
  • PV
  • SPI
  • CPI
  • SV

Frage 87

Frage
The output of the determine budget process is:
Antworten
  • Schedule
  • Cost forecasts
  • Cost management plan
  • Cost baseline

Frage 88

Frage
During a project, earned value analysis is performed. You get the following numbers: EV = 50,000 PV = 60,000 AC = 75,000 What are the correct results?
Antworten
  • CV = -25000 SV = -10000
  • CV 10000 SV= -15000

Frage 89

Frage
There are 4 activities in your project. Activity A has a planned value of 20,000. Activity B has a planned value of 30,000. Activity C has a planned value of 10,000. Activity D has a planned value of 40,000. What is the BAC?
Antworten
  • 25000
  • 37000
  • 12500
  • 100000

Frage 90

Frage
Determine the variance at completion with the following information: SV = -50,000 Estimate at completion = 100,000 Budget at completion = 200,000
Antworten
  • 50000
  • 10000
  • 2
  • 1.5

Frage 91

Frage
Direct costs are:
Antworten
  • Directly related to the project and can be controlled
  • Included in overhead costs
  • Excluded from the project budget
  • Part of activity cost estimates

Frage 92

Frage
Which of the following processes do not belong to the Project Cost Management process group?
Antworten
  • Plan cost management
  • Control cost
  • Determine budget
  • Contingency reserve

Frage 93

Frage
Cost estimation of individual work packages or activities is called:
Antworten
  • Bottom-up estimating
  • Analogous estimating
  • Three point estimation
  • Expert judgement

Frage 94

Frage
The output of determine budget is:
Antworten
  • Cost management plan
  • Activity cost estimate
  • Cost baseline

Frage 95

Frage
The earned value calculations for your project are: BAC = 10,000 EAC = 5,000 ETC = 4,000 What is the VAC and will you be over or under budget?
Antworten
  • 6000 and over budget
  • 5000 and over budget
  • 1000 and over budget
  • 6000 and under budget

Frage 96

Frage
Parametric estimating involves:
Antworten
  • Defining cost or duration parameters of the project lifecycle
  • Calculating the individual cost estimates or each work package & integrating them to obtain the total cost of the project
  • Using statistical relationship between relevant historical data and other variables to calculate a cost estimate for project work

Frage 97

Frage
The EAC is based on:
Antworten
  • The actual costs incurred for work completed (AC) and the estimate to complete (ETC) the remaining work
  • The EV and the actual cost for work completed CV
  • The cost performance index (CPI) and the cost of variance (CV).

Frage 98

Frage
Earned value management (EVM) is a commonly used:
Antworten
  • Analysis of the value of the equipment that has been installed in the project as of the status to date.
  • Analysis of the sum of the labor costs, which have been incurred on the project to date.
  • Method to assess performance management and progress for projects.
  • Method of measuring the amount of money that has been spent on the project to date.

Frage 99

Frage
You're earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much:
Antworten
  • Higher than the AC
  • Higher than the PV
  • Lower than the PV
  • Lower than the CPI

Frage 100

Frage
Item PV AC EV 1 10,000 11,000 10,000 2 9,000 8,000 7,000 3 8,000 8,000 8,000 4 7,000 7,000 5,000
Antworten
  • 1
  • 2
  • 3
  • 4

Frage 101

Frage
Plan quality management is:
Antworten
  • Process of identifying quality requirements
  • Planning the cost of precision measurement
  • Identifying project grade
  • Auditing the quality requirements and results

Frage 102

Frage
What would be the least effective tool or method to reduce quality cost?
Antworten
  • Statistical sampling
  • Inspection
  • Nominal group technique
  • Control charts

Frage 103

Frage
Quality is:
Antworten
  • Measure of exactness
  • Assessment of correctness
  • Degree to which a set of inherent characteristics fulfill requirements

Frage 104

Frage
The 3 quality processes in project quality management are:
Antworten
  • Determine quality, monitor quality, plan quality
  • Cost benefit analysis, cost of quality, cost of conformance
  • Plan quality management, control quality, perform quality assurance

Frage 105

Frage
The Ishikawa Diagram tool is used to:
Antworten
  • Gather info on the frequency of poor quality
  • Help identify the actionable root cause of the problem
  • Describe the central tendency of a process
  • Show if a process is stable and predictable

Frage 106

Frage
Grade is:
Antworten
  • Measure of exactness
  • Measure of correctness
  • Categorization of deliverables having the same functional use but different technical characteristics

Frage 107

Frage
The cost of quality includes all of the following EXCEPT:
Antworten
  • Prevention costs
  • Returns
  • Raw materials
  • Customer service

Frage 108

Frage
The quality management plan is an output of which process:
Antworten
  • Project quality management
  • Plan quality management
  • Control quality

Frage 109

Frage
Increased prevention costs should result in:
Antworten
  • Increased frequency of external failures
  • High internal failure costs
  • Decreased internal and external failure costs

Frage 110

Frage
Pareto diagrams:
Antworten
  • Are used to gather attributes data while performing inspections
  • Identify the vital few sources that are responsible for causing the most problems
  • Are used to monitor cost and schedule variances

Frage 111

Frage
Perform quality assurance is:
Antworten
  • The processes and activities that will determine quality policies, objectives & responsibilities
  • Auditing the quality requirements and results from quality control measurements
  • Process of determining project grade

Frage 112

Frage
Scatter diagrams:
Antworten
  • Show forces for and against change
  • Map operational details of procedures
  • Seek to explain changes in variable Y in relation to changes in X

Frage 113

Frage
A project manager can use a control chart to determine:
Antworten
  • The central distribution of a statistical distribution
  • If the amount of prevention costs are increasing
  • If a process is stable or predictable

Frage 114

Frage
The results of performing the control quality process are:
Antworten
  • Decreased costs
  • Stable processes
  • Verified deliverables

Frage 115

Frage
An example of appraisal costs is:
Antworten
  • Rework
  • Warranties
  • Training
  • Inspections

Frage 116

Frage
The perform quality assurance process is in:
Antworten
  • Execution
  • Planning
  • Monitor & Control

Frage 117

Frage
Checksheets are:
Antworten
  • Used to organize facts in a manner that will facilitate the effective collection of useful data about a potential quality problem
  • Used to monitor cost & schedule variances
  • Used to describe the central tendency, dispersion, and the shape of the distribution

Frage 118

Frage
Degree of quality should be:
Antworten
  • Inspected in
  • Planned in
  • SWOT

Frage 119

Frage
Control Quality is:
Antworten
  • Comparing the cost of quality to the requirements
  • Achieving project objectives of scope, time & cost
  • Process of monitoring & recording results of quality activities to asses project performance

Frage 120

Frage
Understanding, evaluating, defining & managing requirements are essential to satisfying:
Antworten
  • Customer expectations
  • The scope statement
  • Upper management
  • Functional requirements

Frage 121

Frage
The quality management plan is a component of the ________________ that describes how the organization's quality policies will be implemented.
Antworten
  • WBS
  • Project scope
  • Project management plan

Frage 122

Frage
The seven basic quality tools include all of the following EXCEPT:
Antworten
  • Calibration graphs
  • Pareto diagrams
  • Control charts

Frage 123

Frage
Inspection is:
Antworten
  • Examination of a work product to determine if it conforms to documented standards
  • Documenting results of control quality activities
  • A validated deliverable required by the project

Frage 124

Frage
Which of the following is true regarding precision and accuracy?
Antworten
  • Precision is a measure of correctness whereas accuracy is an assessment of exactness
  • Precision is a measure of exactness, whereas accuracy is an assessment of correctness.

Frage 125

Frage
Project Human Resource Management includes the following processes:
Antworten
  • Acquire project team, develop project team, HR management plan, performance assessments
  • Plan HR team, manage project team, evaluate project team, identify project roles
  • Plan HR management, acquire project team, develop project team, project team

Frage 126

Frage
The human resource management plan is an output of which process:
Antworten
  • Acquire project team
  • Plan HR management
  • Develop project team
  • Manage project team

Frage 127

Frage
The best illustrate for your project teams reporting relationships you would use:
Antworten
  • Matrix chart
  • RACI chart
  • A hierarchical chart

Frage 128

Frage
Which of the following is NOT one of toucans 5 stages of team development?
Antworten
  • Norming
  • Storming
  • Adjourning
  • Developing

Frage 129

Frage
There is a critical disagreement between two of your project team members. You need to help them resolve the issue. To help them find a solution that is a win for both sides, you would use which technique for resolving conflict?
Antworten
  • Force
  • Withdraw
  • Collaborate
  • Smooth

Frage 130

Frage
RACI stands for?
Antworten
  • Rational Accountable Creative Informed
  • Responsible Actionable Creative Independent
  • Responsible Accountable Consulted Informed

Frage 131

Frage
The project manager:
Antworten
  • Performs the work of the project
  • The person assigned to lead the team that is responsible for achieving the project objectives
  • The person who provides the resources and support for the project

Frage 132

Frage
A member of your team has broken one of the agreed upon ground rules, who should enforce the rule?
Antworten
  • PMO
  • Project Manager
  • All project team members
  • Sponsor

Frage 133

Frage
The process of developing an appropriate approach and plan for project communications based on stakeholder’s needs, requirements, and available organizational assets is:
Antworten
  • Control communications
  • Plan communications management
  • Manage communications
  • Develop communications plan

Frage 134

Frage
In addition to distributing information, the Manage Communications process is also concerned with:
Antworten
  • Making sure the information has been received and understood
  • Creating the project communications plan
  • Planning the correct channel to use to distribute the information

Frage 135

Frage
For your new project, you need to produce a simple status update for your Sponsor. What information would you not want to include?
Antworten
  • Lessons learned
  • Current status
  • Risks

Frage 136

Frage
As a Project Manager in a matrix environment, you do not have direct authority over your project team. However, your team likes you and enjoys working for you. You are relying on what type of influence?
Antworten
  • Formal
  • Referent
  • Expert
  • Reward

Frage 137

Frage
What topic would likely be covered in the kick off meeting?
Antworten
  • Procurement plan
  • Lessons learned
  • Performance evaluations
  • Roles and responsibilities

Frage 138

Frage
Mid-way through a project, your sponsor comes to you and asks for a monthly project status report to be produced that will help the executive team understand the progress being made on the project. What process are you in now?
Antworten
  • Plan communications management
  • Control communications
  • Communication models
  • Manage communications

Frage 139

Frage
You have a virtual team working on your project. What is a disadvantage of having a team that is not all located in the same place?
Antworten
  • Cannot have kick off meetings
  • Opportunity for misunderstandings
  • Easy conflict resolution

Frage 140

Frage
The PMO:
Antworten
  • Is a person/group that provides resources/support
  • Standardizes the project related governance
  • Is a collection of logically related project activities that culminates in the completion of one or more deliverables

Frage 141

Frage
Your project team is beginning to work together and adjust their habits to support the team. They are beginning to trust each other more. What development stage is your team in?
Antworten
  • Forming
  • Withdraw
  • Forcing
  • Norming

Frage 142

Frage
You are creating a weekly status update, what process are you in?
Antworten
  • Develop project team
  • Control communications
  • Manage communications
  • Plan communications management

Frage 143

Frage
Your project team is well organized, interdependent and handles issues effectively. What stage are they in?
Antworten
  • Developing
  • Norming
  • Performing

Frage 144

Frage
The HRMP should generally include all of the following EXCEPT:
Antworten
  • Staffing management plan
  • Project interfaces
  • Roles & responsibilities
  • Project organization charts

Frage 145

Frage
Techniques and considerations for effective communications management generally includes all of the following EXCEPT:
Antworten
  • Employing organizational process assets to reduce risk
  • Facilitation techniques for building consensus
  • Listening techniques

Frage 146

Frage
The acquisitions strategy for acquiring a project team consists of:
Antworten
  • Hiring consultants from the outside
  • Obtaining resources through ranking criteria
  • Acquiring members of the team from other teams within the organization

Frage 147

Frage
The Acquire Project Team is the process of confirming human resource availability and obtaining the team necessary to complete project activities. The enterprise environmental factors that can influence this process generally include all of the following EXCEPT:
Antworten
  • Organizational structure
  • Multi-criteria decision analysis
  • Competency levels, prior experience & cost rate.

Frage 148

Frage
Generally acknowledged techniques for resolving conflict include:
Antworten
  • Accept, compromise, attack & separate
  • Smooth compromise collaborate co-locate
  • Accommodate compromise force & collaborate

Frage 149

Frage
Project risk is:
Antworten
  • A condition that causes negative impact to the project
  • A threat to the success of the project
  • An uncertain event that if it occurs has a positive or negative effect

Frage 150

Frage
The strategy to address opportunities and seek to ensure the opportunity happens is:
Antworten
  • Avoid
  • Enhance
  • Exploit

Frage 151

Frage
The risk register is an output of which project risk management process?
Antworten
  • Performing qualitative risk analysis
  • Perform quantitative risk analysis
  • Plan risk management
  • Identify risks

Frage 152

Frage
The following process is in monitoring & control:
Antworten
  • Plan risk management
  • Control risks
  • Perform quant risk analysis

Frage 153

Frage
Relies on anonymous feedback from experts through questionnaires and drives toward consensus
Antworten
  • Root cause analysis
  • Probability impact matrix
  • Delphi technique
  • Risk register

Frage 154

Frage
The risk register should include:
Antworten
  • Identified risks & WBS number
  • Identified risks & potential responses
  • Risk categorization & identified risks
  • Identified risk & risk analysis

Frage 155

Frage
Is used to determine the risk rating to help prioritize risks:
Antworten
  • Risk categorization
  • Risk register
  • Expected monetary value analysis
  • Probability & impact matrix

Frage 156

Frage
Helps compare the relative importance & impact of variables that have a high degree of uncertainty to those that are more stable:
Antworten
  • Expected monetary analysis
  • Tornado diagram
  • Decision tree
  • Monte carlo technique

Frage 157

Frage
Uses a computer to produce many simulations using random sampling to obtain probable results distribution:
Antworten
  • Expected monetary analysis
  • Monte Carlo technique
  • Decision tree diagram
  • Sensitivity analysis

Frage 158

Frage
You are building a skyscraper in New York City. If the project falls behind schedule, you will lose millions of dollars in fees to the city. You want to shift the financial burden of the threat of fees to a third party. What strategy should you use?
Antworten
  • Mitigate
  • Avoid
  • Exploit
  • Transfer

Frage 159

Frage
Your software project is given very good press in The Wall Street Journal. You want to make sure the chances for success are increased so you add more resources to the project. What strategy are you using?
Antworten
  • Share
  • Accept
  • Transfer
  • Enhance

Frage 160

Frage
Qualitative risk analysis deals with:
Antworten
  • Developing options for risk responses
  • Numerically analyzing the effect of risks
  • Prioritizing risks
  • Monitoring residual risks

Frage 161

Frage
Using Expected Monetary Value Analysis, calculate the average outcome for a project that has either a $300,000 profit and 30% chance of achieving it, or a $100,000 loss and 70% chance of having that happen.
Antworten
  • 160,000
  • 20,000
  • 400,000
  • 90,000

Frage 162

Frage
Process of determining options to reduce threats and enhance opportunities:
Antworten
  • Identify risks
  • Control risks
  • Plan risk response
  • Perform qualitative risk analysis

Frage 163

Frage
Your Risk Register calls out several risks, including not having enough resources available to complete the software in time to ship it. You check in weekly with the developers to make sure the software will be completed in time. What process are you in?
Antworten
  • Plan risk management
  • Control risks
  • Plan risk response
  • Identify risks

Frage 164

Frage
When using the Delphi technique, you should:
Antworten
  • Have a unanimous decision
  • Encourage brainstorming
  • Not share the responses through the entire process
  • Make sure the participants are experts

Frage 165

Frage
In the plan risk responses process, an accept strategy for a negative risk or threat indicates that the project team has decided:
Antworten
  • To agree with the PM
  • To eliminate a specific threat or risk
  • Not to change the project management plan to deal with a risk, or is unable to identify any other suitable response strategy

Frage 166

Frage
As an update of the control risks process, an updated risk register generally includes some or all of the following EXCEPT:
Antworten
  • The WBS
  • Actual outcomes of the projects risks
  • Outcomes of risk reassessments

Frage 167

Frage
To be successful, an organization should be committed to addressing risk management:
Antworten
  • Proactively throughout the entire project
  • As soon as time & cost estimates are ready
  • As early as possible in the execution phase

Frage 168

Frage
The primary output of the identify risks process is the:
Antworten
  • Risk register
  • Risk mitigation plan
  • List of the corrective actions

Frage 169

Frage
The mitigate risk response strategy:
Antworten
  • Reduces the probability of occurrence or impact of a threat
  • Seeks to make sure the risk negative response happens
  • Seeks to eliminate the threat or protect the project from its impact

Frage 170

Frage
The probability and impact risk assessment thresholds:
Antworten
  • Show quantitative risk results for the project
  • Are determined by the # of threats
  • Are unique for each organization

Frage 171

Frage
Sensitivity analysis helps determine which risks have the most potential impact on the project. How is that info shown?
Antworten
  • Probability and impact matrix
  • Cost/probability chart
  • Tornado diagram

Frage 172

Frage
Expected monetary value (EMV) analysis has all of the following characteristics except:
Antworten
  • It is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen.
  • The EMV of opportunities are generally expressed as positive values, whereas those of threats are expressed as negative values.
  • EMV analysis cannot be used effectively in decision tree analysis unless a risk-averse assumption is made.

Frage 173

Frage
An output of perform qualitative risk analysis is:
Antworten
  • Project documents updates
  • Risk management plan
  • Risk register
  • Meetings

Frage 174

Frage
Identify stakeholders is a part of which process group?
Antworten
  • Initiation
  • Execution
  • Planning

Frage 175

Frage
You are evaluating various bids to determine which vendor you will purchase your building materials from. What process are you in?
Antworten
  • Plan procurement management
  • Conduct procurements
  • Planning

Frage 176

Frage
You are a Project Manager constructing a large building to store your company’s work vehicles. You know exactly what you want built. It will only take 3 weeks to build. In this case, what type of contract would you want to use?
Antworten
  • Hybrid
  • Time & material
  • Fixed price
  • Cost reimbursable

Frage 177

Frage
You a working on a project that will augment the staff in grade schools by providing temporary substitute teachers for the school district. To account for fixed overhead costs and hourly wages, the best contract type would be:
Antworten
  • Fixed cost
  • Cost reimbursable
  • Time & material

Frage 178

Frage
The stakeholder register is an output of which process?
Antworten
  • Stakeholder analysis
  • Plan stakeholder management
  • Manage stakeholder engagement
  • Identify stakeholders

Frage 179

Frage
In the Power/Interest stakeholder grid, which quadrant should you spend the most time on and provide the most attention?
Antworten
  • Low p low I
  • High p low I
  • High p high I

Frage 180

Frage
The stake holder register should contain at least the following:
Antworten
  • Identification information, risk analysis, assessment matrix
  • Stakeholder engagement data flow diagram, risk analysis, assessment matrix
  • Identification information, assessment information, stakeholder classification
  • Stakeholder management plan, stakeholder classification, risk analysis

Frage 181

Frage
Lessons learned:
Antworten
  • Collects project performance data
  • Shows how events were addressed or should be addressed in the future with the purpose of improving future performance
  • An event to plan organize and direct work

Frage 182

Frage
If a contract has an incentive fee, financial incentives are dependent on:
Antworten
  • Inflation
  • Legal penalties
  • Agreed upon metrics

Frage 183

Frage
During closing, you should hand off the project to:
Antworten
  • PMO
  • Exec Sponsor
  • End User
  • The group that will own or be responsible on a daily basis

Frage 184

Frage
In the agile framework, individuals and interactions are valued more than:
Antworten
  • Deliverables
  • Methodology
  • Processes & tools

Frage 185

Frage
You are a Project Manager for Apple and your latest project is developing the new iPhone 6Z. You need to build a solar battery that will enable the phone to go without charging for 2 weeks at a time. Critical to this project is the new chip design that requires a special assembly line to produce. This new assembly line is not a core competency of Apple. You need to decide what type of contract will work best to acquire the new chip. What procurement process are you in?
Antworten
  • Conduct procurements
  • Identify stakeholders
  • Plan procurement management

Frage 186

Frage
Which type of contract is the riskiest for a contractor?
Antworten
  • Cost plus fee
  • Time & materials
  • Firm fixed price

Frage 187

Frage
The output of the conduct procurements process is:
Antworten
  • Procurement management plan
  • Closed procurements
  • Signed contract agreement
  • Work performance info

Frage 188

Frage
Your project Sponsor is actively engaged in your project and understands the benefits and impacts. How would you classify the Sponsor as a stakeholder?
Antworten
  • Resistant
  • Expert
  • Leading

Frage 189

Frage
During the Closing process, you should do all of the following except
Antworten
  • Conduct lessons learned
  • Gain approval to close
  • Classify stakeholders

Frage 190

Frage
Enterprise environ factors are:
Antworten
  • Outputs
  • Project management systems
  • Conditions that influence or constrain

Frage 191

Frage
Who represents the customer in SCRUM?
Antworten
  • PM
  • PT
  • Product Owner
  • Scrum master

Frage 192

Frage
Procurement is:
Antworten
  • Acquiring goods & services
  • Reviewing contracts
  • Obtaining the resources you need for the project

Frage 193

Frage
The best measure for progress in agile is:
Antworten
  • Design
  • Working software
  • Technical excellence

Frage 194

Frage
Cost plus fixed fee contracts (CPFF) have all of the following characteristics except:
Antworten
  • Seller receives a fixed-fee payment calculated as the initial estimated project cost.
  • The fee is paid only for completed work and does not change due to seller performance unless the project scope changes.

Frage 195

Frage
You are involved in the process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle. This is known as:
Antworten
  • Plan stakeholder management
  • Communicate with stakeholders
  • Control stakeholders
  • Manage stakeholder engagement

Frage 196

Frage
Manage Stakeholder Engagement involves all of the following activities except:
Antworten
  • Managing stakeholder expectations through negotiation and communication
  • Avoiding potential concern that have not yet become issues
  • Anticipating future problems
  • Clarifying & resolving identified issues

Frage 197

Frage
Control Stakeholder Engagement tools and techniques include all of the following except:
Antworten
  • Behavior modification analysis
  • Expert judgement
  • Meetings
  • Information management systems

Frage 198

Frage
Outputs from the Close Procurements Process generally include all of the following except:
Antworten
  • Deliverable acceptance
  • Closed procurements
  • Lessons learned
  • The contractors working proposal
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Lern-Fitness-Test aus der Bestnote
Studienstrategie
LEK 1-1
tobifant
Die deutsche Romantik in der Literatur
Roland Baumann
Gute Gewohnheiten erfolgreicher Schüler
Laura Overhoff
Euro-FH // Zusammenfassung PEPS3
Robert Paul
Vetie - Biochemie
Fioras Hu
Vetie - Tierzucht & Genetik - S II
Fioras Hu
Vetie - Pathologie 2017
Fioras Hu
Grundzüge soziologischer Theorien
Salome Jeong
Vetie Para Morphologie Entomologie
Kristin E
Vetie Reprospaß2
Tropsi B