Frage 1

Frage
The three types of project control processes are:
Antworten
  • Easily understood because they have stayed the same for many years
  • Easily understood by all levels in the project team.
  • Cybernetic, go/no-go, and postcontrol
  • Not well-understood.

Frage 2

Frage
The project manager’s primary function includes managing human resources and:
Antworten
  • Following orders from top management.
  • Project Management software.
  • Guarding physical and financial assets of the company
  • Charting and graphing project task completion.

Frage 3

Frage
Because project milestones may not occur at periodic intervals, go/no-go controls should be linked to the __________; not simply to the calendar.
Antworten
  • corporate budgeting process
  • actual plans and to the occurrence of real events
  • capital budgeting process
  • portfolio management review process

Frage 4

Frage
Go/no-go controls operate __________.
Antworten
  • only at phase gate reviews
  • only when exceptions are detected
  • only when and if the controller uses them
  • continuously

Frage 5

Frage
Identify the item that is NOT one of the three types of control processes described by the authors.
Antworten
  • cybernetic control
  • robotic control
  • postcontrol
  • go/no-go control

Frage 6

Frage
In order to control creative projects the project manager must adopt one or some combination of three general approaches to the problem. Which of the following is NOT one of these approaches?
Antworten
  • creativity check
  • personnel reassignments
  • process review
  • control of input resources

Frage 7

Frage
Control is focused on three elements of a project. They are __________.
Antworten
  • scope, quality, and customer satisfaction
  • scope, cost, and time
  • cost, time, and customer satisfaction
  • performance, delivery, and cost

Frage 8

Frage
The two fundamental objectives of control are the regulation of results and the __________.
Antworten
  • refurbishing of organizational assets
  • distribution of organizational assets
  • procurement of organizational assets
  • stewardship of organizational assets

Frage 9

Frage
An automatic control system containing a negative feedback loop is referred to as
Antworten
  • cybernetic
  • postcontrol
  • go/no-go
  • critical ratio

Frage 10

Frage
Cybernetic control is reported to be the most common type of control system, and consists of:
Antworten
  • Upper management weekly approvals
  • Automated reports to top management when the project goes out of control
  • An automatic adjustment of processes when deviations are detected
  • Cybernetic loops of feedback to the PM.

Frage 11

Frage
Project control systems are very valuable to successful projects, and the typical cost of the control systems is in the range of _________ percent of total project cost.
Antworten
  • 10 to 15%
  • 5 to 10%
  • 15-20%
  • 1 – 5%

Frage 12

Frage
Cybernetic control systems are:
Antworten
  • Positive feedback loops
  • Negative feedback loops
  • Very difficult to implement
  • Relatively expensive and difficult to use.

Frage 13

Frage
The stewardship of human resources requires __________ the growth and development of people.
Antworten
  • mandating
  • controlling and maintaining
  • demolition
  • flattening

Frage 14

Frage
When a client wants to increase the scope or functionality of a project, what should the project design engineer reply?
Antworten
  • Of course it’s OK. The client is always right.
  • Upper management will decide.
  • We can probably do that for you, and I can prepare a new schedule and cost analysis to fit your new plan/goals.
  • OK and it will not cost you any more.

Frage 15

Frage
The most common reason for scope creep is:
Antworten
  • Natural tendency of the client and project team to try to improve the original plan.
  • Engineering’s natural tendency to be perfectionists
  • Client’s unrealistic expectations for the design
  • Errors and omissions in the original project design

Frage 16

Frage
Project Management control of physical assets includes
Antworten
  • Scheduling of maintenance and repair of all project equipment
  • PMs do not control physical assets, they schedule work.
  • Scheduling of maintenance, repair, and/or replacement of project equipment
  • Planning, scheduling, and graphing of project tasks & equipment

Frage 17

Frage
Control systems commonly become out of balance because of:
Antworten
  • Too many project managers
  • Too few workers
  • Putting too much weight on easy-to-measure factors
  • Overemphasizing the seriousness of cost overruns

Frage 18

Frage
In a cybernetic control system using a negative feedback loop, the speed or force with which the control operates is, in general, __________ to the size of the deviation from standard
Antworten
  • double
  • customary
  • reciprocal
  • proportional

Frage 19

Frage
In order to gain user acceptance, the control system should appear to be __________.
Antworten
  • sensible
  • firm
  • enforced with sanctions
  • lenient

Frage 20

Frage
When performing control, project managers need to be attentive to __________.
Antworten
  • avoiding directive behaviors
  • regulation and conservation equally
  • regulation more than conservation
  • maintaining laissez faire leadership
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Das Leben von Nelson Mandela
AntonS
Grundbegriffe der Gedichtanalyse
mirjam.schlaepfe
Streite/Gesetzliche Schuldverhältnisse
myJurazone
Sachversicherungen
Christine Zehnder
Unfallversicherung
Christine Zehnder
Englisch Lernwortschatz A1-C1 Teil 1
Chiara Braun
Forschungs- und Anwendungsfelder der Soziologie Teil 1
stelly Welly
Quiz MS-4.2 Foliensatz II_Teil 1
Bernd Leisen
Vetie Para Morphologie Protozoen
Kristin E
Vetie: Geflügelkrankheiten: Fragen aus dem Zyklus
Johanna Tr
Vetie - Milch 2017
Kim Langner