Frage 1
Frage
What are tasks of the Production Cutover deliverable?
(More than one answer is correct. Please choose the correct answers.)
Antworten
-
Initiate Solution Manager Update - Solution Documentation
-
Execute Go Live Simulations 1 - n
-
Conduct Data Quality Readiness Check
-
Final Check of Production Readiness and Sign-Off
-
Provide Post Go Live Support
Frage 2
Frage
What is the purpose of the Cut Over work stream in the Realisation phase?
(One answer)
Antworten
-
To simulate the cut over procedure in the development environment and to provide support for the solution during the period immediately following production cutover.
-
To execute the SAP Going Live Check service
-
To begin documenting the timing, steps, and logistics for moving from the as-is solution to the to-be solution and to complete the Technical Integration Check service.
-
To execute the functional testing and performance testing.
-
To plan the production cutover weekend party
Frage 3
Frage
What is the purpose of the preliminary cutover plan?
(One answer)
Antworten
-
To setup the schedule transfer of data from the SAP development system and legacy systems to the SAP production system.
-
To document the strategy, scope and timelines for moving from the as-is solution to the to-be solution and the hyper care period immediately following go-live.
-
To identify which named users from the customer organisation that will drive the cutover process according to the working schedule.
-
To execute communication activities to project stakeholders during cut-over and go live.
-
To document the instructions on how to slice the cake after a successful go-live.