PMP Formulas

Beschreibung

PMP Formulas
Krunk!
Karteikarten von Krunk!, aktualisiert more than 1 year ago
Krunk!
Erstellt von Krunk! vor mehr als 9 Jahre
425
37

Zusammenfassung der Ressource

Frage Antworten
BAC - Budget At Completion Σ(PV) at project completion
EV - Earned Value % complete x BAC
CV - Cost Variance EV – AC (>0 is good)
SV - Schedule Variance EV – PV (>0 is good)
CPI - Cost Performance Index EV / AC (>1 is good)
SPI - Schedule Performance Index EV / PV (>1 is good)
EAC - Estimate At Completion AC / % Complete or BAC / CPI
ETC - Estimate To Completion EAC—AC
VAC - Variance At Completion BAC—EAC
TCPI - To Complete Performance Index Remaining Work / Remaining Budget (BAC—EV) / (BAC—AC) or (BAC—EV) / (EAC—AC)
AC - Actual Cost CV / (CPI - 1)
PV - Planned Value SV / (SPI - 1)
Qualitative Risk Score Probability x (Iscope + Itime + Icost + Iquality)
EMV - Expected Monetary Value Impact x Probability
Communication Channels N (N—1) / 2 N = # of stakeholders in the project
1 Sigma = ? 68.26%
2 Sigma = ? 95.46%
3 Sigma = ? 99.73%
6 Sigma = ? 99.999%
Present Value (PV) FV --------------- (1 + r) ^ n FV = Future Value; r = Rate of Interest n = Number of Years
PERT - Program Evaluation and Review Technique (O+4M+P) / 6 O = Optimistic P = Pessimistic M = Most Likely
SD of Activity (sigma) (P-O) / 6 O = Optimistic P = Pessimistic
Variance of Activity (SD) ^ 2
Float LS—ES = LF—EF LS = Late Start; LF = Late Finish ES = Early Start; EF = Early Finish
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Summary of Definitions/Key Terms for the PMP Exam
Andrea Leyden
PMP Prep quiz
Andrea Leyden
Using GoConqr to study Economics
Sarah Egan
Economics
Emily Fenton
AN ECONOMIC OVERVIEW OF IRELAND AND THE WORLD 2015/16
John O'Driscoll
Economics - unit 1
Amardeep Kumar
Project Scope Management Process
neeshar
PMP® Pre-Test by Coursefountain.com
Team Coursefountain
Using GoConqr to teach Economics
Sarah Egan
Functions of Money
hannahcollins030
Comparative advantage
jamesofili