SAB9# 63 Analysis Diagram Red

Description

pm Curso PM Mind Map on SAB9# 63 Analysis Diagram Red, created by Juan Garcia on 25/02/2016.
Juan Garcia
Mind Map by Juan Garcia, updated more than 1 year ago
Juan Garcia
Created by Juan Garcia almost 9 years ago
30
0

Resource summary

SAB9# 63 Analysis Diagram Red
  1. Definition
    1. A diagramming technique to visualize the dependencies of the activities and calculate the total duration of the project.
    2. Dependence
      1. • (FS) Finish to Start: The start of the activity thus successor to the completion of the predecessor activity
        1. • (FF) Final Final: The completion of the successor activity depends upon the completion of the predecessor activity.
          1. • (SS) Star to Start The initiation of the successor activity depends upon the initiation of the predecessor activity.
            1. • (SF) Start to Finish: The completion of the successor activity depends upon the initiation of the predecessor activity.
            2. Characteristics:
              1. Each activity is represented by a box and only one
                1. Each frame has a number of unique activities
                  1. The activities are arranged in the order of the presidency to know when you start first
                    1. You can start an activity to finish the preceding
                      1. There may be concurrent activities
                      2. Concepts
                        1. • Predecessor Activity: Activity that precedes the successor activity
                          1. • successor Activity: Activity happens predecessor activities
                            1. • Critical Path: Path or going from start to finish and also takes longer compared to other routes
                              1. • Full Clearance: The additional time available to complete an activity, if all the above activities as early as possible and start the following latest
                                1. • free float; Is the additional time that may extend an activity without affecting the next start of any subsequent activity
                                  1. the critical chain is the sequence of precedences and dependent on resources that prevent a project, which is given limited resources, can be completed in less time terminal elements . If the resources of a project were always available in unlimited quantities , then the critical chain of a project would be equal to its critical path.
                                  2. Steps
                                    1. Define the project and prepare the work breakdown structure
                                      1. Development of relations between activities
                                        1. Draw the network connecting all activities
                                          1. Calculate the time of the longest path
                                            1. Using the network to help plan your schedule, you supervise and control the project
                                    2. Activities list
                                      Show full summary Hide full summary

                                      Similar

                                      Study Planner
                                      indibharat
                                      OCR GATEWAY CHEMISTRY C1 TEST
                                      Olivia Farrow
                                      Models For Explaining Human Memory
                                      Matthew Li
                                      Chemistry 3 Extracting Metals Core GCSE
                                      Chloe Roberts
                                      C1 B1 & P1 Test
                                      jodie00
                                      GCSE AQA Chemistry Atomic Structure and Bonding
                                      Joseph Tedds
                                      Physics P1
                                      Phoebe Drew
                                      GCSE REVISION TIMETABLE
                                      haameem1999
                                      Geography AQA Revison topics Migration, Population Change, Youthful Populations and more
                                      dburns8731
                                      The Tempest
                                      Dirk Weibye
                                      AS English language terminology revision
                                      Caitlin Hadfield