Task A is worth $200, is 100% complete, should have been done on day 1, and actually cost $200. Task B is worth $75, is 90% complete, should have been done on day 2, and actually cost $120 so far. Task C is worth $200, is 75% complete and should have been done on day 3, and has cost $175 so far. The total budget is $1000. What is the planned value as of day 1?
Select one of the following: