In which process is the initiation of the project authorised?
Starting up a Project
Initiating a Project
Directing a Project
Managing a Stage Boundary
When does the process of Directing a Projectformally begin?
Before Starting up a Project
After Starting up a Project
After Initiating a Project
After Managing a Stage Boundary
Which of the following products is NOT reviewed by the Project Board when authorising project closure?
Project Initiation Document (PID)
Project Brief
End Project Report
Benefits Review Plan
Which role recommends the project closure?
The Executive
The Senior User
The Senior Supplier
The Project Manager
Which management product is provided to the Project Board with a request to authorise initiation?
Project Mandate
Draft Project Initiation Document
Issues Register
What is the purpose of an Exception Report?
Where there is a forecast to exceed tolerance, it is prepared to inform the Project board of the situation.
It provides the Project Board with a summary of stage staus at intervals defined by them.
It contains the description, impact assessment and recommendations for a request for change or off-specification.
When there is a forecast to exceed tolerance, it replaces the plan which is no longer valid.
How often is the Managing Stage Boundary process invoked?
At the end of the Starting Up a Project process.
At the end of each project.
At the end of each stage, except the final one.
At the end of each Work Package.
Who needs the information gathered in Managing a Stage Boundary to assess the continuing viability of a project?
Corporate/Programme Manager
Project Board
Project Manager
Stakeholders
Which of the following plans listed below is NOT produced or updated in the Managing a Stage Boundary process?
Exception Plan
Next Stage Plan
Team Plan
Project Plan
The Project Board may request that the current stage is replanned, and the output from replanning is... which is submitted for Project Board approval?
a Stage Plan
a Project Plan
a Team Plan
an Exception Plan
What is a purpose of the Closing a Project process?
Enable the Project Manager to review whether the project has anything further to contribute.
Enable the Project Board to make the decision about whether or not to close the project.
Enable the Project Manager to manage the final delivery report.
Enable the delivery team to create the specialist products of the final stage.
How might the Project Manager use the Project Plan during the Closing a Project process?
To update with actuals from the final stage.
To update with forecasts for the final stage.
To plan the work to review the post-project benefits.
To control and monitor the work of the final stage.
Which of the following statements represents how the Closing a Project process helps to implement the Risk theme?
Describes the activity where the procedure for managing threats for the project is defined.
Describes the activity where ongoing opportunities for the project's products are passed on to the operational and maintenance teams.
Describes the activity where the delivery team report risks to the Project Manager
Describes the activity where risks are captured in the Risk Register.