Which is NOT an objective of the Initiating a project process?
Ensure there is a common understanding of who will take significant project management roles within the project.
Ensure there is a common understanding of how and when the project's products will be achieved and at what cost.
Ensure there is a common understanding of the reasons for doing the project, the benefits expected and the associated risks.
Which of the following is NOT a PRINCE2 management product?
Risk Management Strategy
Configuration Management Strategy
Communication Management Strategy
Cost Management Strategy
The Business Case will contain a summary of key risks, where will the details of all the risks be stored?
Issues Register.
Configuration Item Records
Risk Register
Which of the following is defined as part of setting up controls for the project?
Tolerances for delegated authority.
Quality management procedure.
Tools and techiques for managing risks
How information from outside of the project environment will be sent or received.
Information on project controls is included in which management product?
Project Brief
Business Case
Stage Quality Plan
Project Initiation Documentation
The Outline Business Case is prepared as part of which process?
Controlling a Stage
Starting up a Project
Initiating a Project
Directing a Project
The information gathered in the Starting Up a Project process should answer what basic uestions?
Do we have a viable and worthwhile project?
Do we know who thought of this idea?
Do we care about the outcome at this stage?
Do we solve the problem now or later?
What management product produced in Starting Up a Project is submitted to the Project Board with a request to initiate a Project?
Refined Business Case
Project Initiation Document (PID)
Project Plan
How does the Starting up a Project process support the defined roles and responsibilities principle?
By nominating the project manager responsible for project assurance.
By appointing the executive, the project manager and the project management team.
It doesn't.
By ensuring lessons from previous projects are captured and analyzed.
Who is responsible for creating the Initiation Stage Plan?
Project Manager
Project Board
Team Manager
Project Assurance