dabbler c
Quiz by , created more than 1 year ago

BCM BOK2

15
0
0
dabbler c
Created by dabbler c over 4 years ago
Close

BCM BOK2

Question 1 of 29

1

Select from the dropdown lists to complete the text.

( Residual Risk, Risk Acceptance, Risk Treatment, Risk Tolerance ) is the ( remaining, total ) risk which cannot be defined in more detail after elimination or inclusion of all conceivable quantified risks in a risk consideration. Residual risk is the level of uncontrolled risk remaining after the risk treatment.

Explanation

Question 2 of 29

1

Select from the dropdown lists to complete the text.

( Risk Acceptance, Risk Treatment, Risk Tolerance, Residual Risk ) is to make an informed decision to accept the ( likelihood, total ) and ( impact, probability ) of a particular risk. Risk Acceptance depends on risk criteria and the risk appetite of Top Management.

Explanation

Question 3 of 29

1

Select from the dropdown lists to complete the text.

( Key Planing Scenario (KPS), Risk Appetite, Worst Case Disaster Scenario ) provides the ( BC Team, BCP Team ) with a perspective of the ( magnitude, level ) of disaster that an organization is willing to commit the ( resources, human resources ) to mitigate and is acceptable to the organisation. This organisation includes the Executive Management, Organization BCM Coordinator, BCP team, DRP team and the Crisis Management Team.

Explanation

Question 4 of 29

1

Select from the dropdown lists to complete the text.

A Man-made Threat is an event resulting from ( human intent, sabotage ), negligence, or error. It is divided into into two category: ( human, management ) or ( technology, financial ).

Explanation

Question 5 of 29

1

Select from the dropdown lists to complete the text.

( Natural Threat, Technology Threat ) is a threat resulting from the effect of ( nature, environment ) that may cause a disruptive ( impact, effect ) to an organization.

Explanation

Question 6 of 29

1

Select from the dropdown lists to complete the text.

( Period of Disruption, Key Planning Scenario ) is the expected ( residual, existing ) disruption resulting from each identified threats, taking into consideration existing controls. The period of disruption is an estimated duration during which the organization’s operations are disrupted (( operationally, intentionally )), or access to the primary location is denied (( infrastructure, premise )).

Explanation

Question 7 of 29

1

Select from the dropdown lists to complete the text.

A ( Threat, Disaster, Hazard ) is an indication or warning of probable man-made or natural situation that can cause ( disruption, disturbance ) to an organization’s operations or services.

Explanation

Question 8 of 29

1

Select from the dropdown lists to complete the text.

The disruption caused by the occurrence of the ( threat, disaster ). It can be operational in nature, causing disruption to the ( functionality, revenue ) of the organization, or infrastructure in nature which will deny access to or usage of the primary ( location, site ).

Explanation

Question 9 of 29

1

Select from the dropdown lists to complete the text.

( Worst Case Scenario, Key Planning Scenario ) is the worst possible ( condition, situation ) or outcome out of the several ( possibilities, alternatives ) in planning for a ( disaster, crisis ).

Explanation

Question 10 of 29

1

Select from the dropdown lists to complete the text.

( Risk Analysis, Risk Rating, Risk Assessment ) is the process to evaluate and determine the risk rating, which is the product of ( risk likelihood, likelihood ) and ( risk impact, impact ).

Explanation

Question 11 of 29

1

Select from the dropdown list to complete the text.

( Risk Appetite, Risk Impact, Risk Level ) is amount and the type of risks that an organization is willing to take in or absorb.

Explanation

Question 12 of 29

1

Select from the dropdown lists to complete the text.

( Risk Assessment, Risk Appetite, Risk Likelihood, Risk Impact ) is the overall process of ( risk identification, risk determination ), ( risk analysis, risk assessment ) and risk evaluation.

Explanation

Question 13 of 29

1

Select from the dropdown list to complete the text.

( Risk Avoidance, Risk Treatment ) is to make an informed decision not to become involved in or to withdraw from a risk situation.

Explanation

Question 14 of 29

1

Select from the dropdown list to complete the text.

( Risk Evaluation, Risk Appetite, Risk Assessment, Risk Level ) is the process used to compare the estimated risk against the given risk criteria so as to determine the significance of the risk.

Explanation

Question 15 of 29

1

Select from the dropdown list to complete the text.

( Risk Impact, Risk Appetite, Risk Likelihood, Risk Rating, Impact ) is an outcome resulting from a threat that will impact an organization objectives or assets.

Explanation

Question 16 of 29

1

Select from the dropdown list to complete the text.

( Risk Level, Risk Appetite, Risk Likelihood, Risk Impact ) is the overall level of assessed risk to the risk rating.

Explanation

Question 17 of 29

1

Select from the dropdown list to complete the text.

( Risk Likelihood, Risk Appetite, Risk Impact, Risk Rating ) is the state of being probable or chance of a threat occurring.

Explanation

Question 18 of 29

1

Select from the dropdown list to complete the text.

( Risk Mitigation, Risk Reduction ) is to implement measures so as to lower the exposure to the risk.

Explanation

Question 19 of 29

1

Select from the dropdown lists to complete the text.

( Risk Rating, Risk Level ) is the result of the multiplication of the assigned value for Risk Likelihood against the assigned value of ( Risk Impact, Risk Appetite ).

Explanation

Question 20 of 29

1

Select from the dropdown list to complete the text.

( Risk Reduction, Risk Treatment, Risk Mitigation, Risk Transference ) is to take appropriate actions to lessen the likelihood, negative consequences or both, associated with a risk.

Explanation

Question 21 of 29

1

Select from the dropdown list to complete the text.

( Risk Tolerance, Risk Acceptance, Residual Risk ) is the amount if risk that an organization is willing to accept or be exposed to.

Explanation

Question 22 of 29

1

Select from the dropdown list to complete the text.

( Risk Transference, Risk Treatment ) refers to the shifting of the burden of loss for a risk to another party through legislation, contract, insurance or other means.

Explanation

Question 23 of 29

1

Select from the dropdown list to complete the text.

( Risk Treatment, Risk Management, Risk Tolerance, Residual Risk ) is the selection and implementation of appropriate options for dealing with risk.

Explanation

Question 24 of 29

1

Select from the dropdown list to complete the text.

A ( Crisis Event, Crisis Scenario ) is an event (or occurrences that happen over a period of time) leading up to the crisis can pertain to people or human resources.

Explanation

Question 25 of 29

1

Select from the dropdown list to complete the text.

A ( Crisis Scenario, Crisis ) describes a situation that might disrupt the business.

Explanation

Question 26 of 29

1

Select from the dropdown list to complete the text.

( Impact, Risk Impact ) is an evaluated consequence of a particular effect due to the cause, such as a threat.

Explanation

Question 27 of 29

1

Select from the dropdown list to complete the text.

( Hazard, Threat, Risk ) is potential harm or damage, or a situation which poses a level of threat to life, health, property or environment.

Explanation

Question 28 of 29

1

What is the biggest benefit of a successfuly Risk Analysis and Review phase

Select one of the following:

  • Improved cost-effective controls

  • Threat reduction

Explanation

Question 29 of 29

1

Which of the following is NOT the responsibility of the an organization's BCM Coordinator during the Business Impact Analysis phase

Select one or more of the following:

  • Determine data collection process and format

  • Identify critical business function

Explanation