Cody McLaughlin
Quiz by , created more than 1 year ago

Business/Economics Quiz on 7 Level CDC, created by Cody McLaughlin on 28/08/2020.

97
1
0
Cody McLaughlin
Created by Cody McLaughlin about 4 years ago
Close

7 Level CDC

Question 1 of 82

1

Which Air Force instruction (AFI) provides additional information on requirements approval documents (RAD)?

Select one of the following:

  • AFI 63–101.

  • AFI 63–104.

  • AFI 63–138.

  • AFI 64–101.

Explanation

Question 2 of 82

1

Which Defense Federal Acquisition Regulation (DFARS) part governs commercial item determination (CID)?

Select one of the following:

  • DFARS Part 212.

  • DFARS Part 213.

  • DFARS Part 233.

  • DFARS Part 242.

Explanation

Question 3 of 82

1

Above what price threshold should one conduct a commercial item determination (CID)?

Select one of the following:

  • $250,000.

  • $500,000.

  • $1 million.

  • $6.5 million.

Explanation

Question 4 of 82

1

For small business set asides, what percentage of the cost to manufacture a particular product is the prime contractor required to cover?

Select one of the following:

  • 30 percent.

  • 50 percent.

  • 75 percent.

  • 100 percent.

Explanation

Question 5 of 82

1

When the total cost of the contract is below $10 million, when do you create an acquisition plan?

Select one of the following:

  • During routine buys.

  • When there are no incentives to be included.

  • When the acquisition was well researched and there is minimal risk to award and completion.

  • Where there is a history of protests or performance problems.

Explanation

Question 6 of 82

1

Who is responsible for managing the quality assurance surveillance plan (QASP) quality controls?

Select one of the following:

  • Customer.

  • Contractor.

  • Contracting office.

  • Contracting officer representative.

Explanation

Question 7 of 82

1

What part of the quality assurance surveillance plan (QASP) lists performance objectives and standards that must be performed by the contractor?

Select one of the following:

  • Surveillance matrix.

  • Sampling guide.

  • Decision tables.

  • Checklists.

Explanation

Question 8 of 82

1

When developing the request for proposal (RFP), the Department of Defense (DOD) source selection procedures are required for

Select one of the following:

  • orders under multiple award contracts.

  • acquisitions using Federal Acquisition Regulation (FAR) Part 13.

  • acquisitions using FAR Part 15.

  • architect and engineer services solicited and awarded using FAR Part 36.

Explanation

Question 9 of 82

1

The lowest price technically acceptable (LPTA) source selection method

Select one of the following:

  • permits the use of tradeoffs between price and nonprice factors.

  • may include nonprice factors such as technical and past performance.

  • allows the government to accept other than the lowest priced proposal.

  • requires the relative importance of all evaluation factors to be identified in the solicitation.

Explanation

Question 10 of 82

1

Which section of a request for proposal (RFP) provides offerors with instructions for proposal preparation?

Select one of the following:

  • Section C.

  • Section K.

  • Section L.

  • Section M.

Explanation

Question 11 of 82

1

What action must be taken if a proposal exceeds established page limitations stated in the solicitation?

Select one of the following:

  • Determine the contractor non-responsive.

  • Eliminate the offeror from the competitive range.

  • Remove pages in excess of the maximum allowed from the back of the proposal.

  • Accept the proposal “as is” only if determined to be one of the most highly rated proposals.

Explanation

Question 12 of 82

1

Solicitation evaluation factors are used to distinguish one proposal from another by

Select one of the following:

  • using discriminators.

  • using non-commercial specifications.

  • including as many evaluation factors as possible.

  • tailoring the evaluation criteria contained in Section K.

Explanation

Question 13 of 82

1

Lowest price technically acceptable (LPTA) source selections are evaluated according to

Select one of the following:

  • price only.

  • the acceptability of a product or service only.

  • the acceptability of non-price evaluation factors or subfactors.

  • the rankings of non-price factor/subfactors and the acceptability of a product or service.

Explanation

Question 14 of 82

1

A proposal that meets requirements and indicates an exceptional approach and understanding of the requirements is given which rating?

Select one of the following:

  • Good.

  • Marginal.

  • Outstanding.

  • Acceptable.

Explanation

Question 15 of 82

1

One common aspect of past performance relevancy is

Select one of the following:

  • the number of contracts performed.

  • financial condition.

  • small business type.

  • dollar value.

Explanation

Question 16 of 82

1

When considering how many D type contracts to award from one request for proposal (RFP), the contracting officer should consider the

Select one of the following:

  • total cost of the contract.

  • small business type of the contractors.

  • expected duration and frequency of the task or delivery orders.

  • ability to alleviate competition among the awardees throughout the contract’s period of performance.

Explanation

Question 17 of 82

1

Which method is a preferred technique in support of price analysis?

Select one of the following:

  • Comparison of proposed price received in response to the solicitation.

  • Analysis of data other than certified cost or pricing data provided by the offeror.

  • Comparison with competitive published price lists.

  • Use of weighted guidelines.

Explanation

Question 18 of 82

1

Which factor affects comparability during price analysis?

Select one of the following:

  • Type of funding being used.

  • Differences in quantities or size.

  • Use of federal supply schedules.

  • Differences in contractor business size.

Explanation

Question 19 of 82

1

Technical analysis of offeror proposals should

Select one of the following:

  • analyze each offeror’s profit margin.

  • only be conducted by the contract officer.

  • review each offeror’s experience on similar projects.

  • examine the types and quantities of materials proposed.

Explanation

Question 20 of 82

1

Communications between the government and contractors are held after receipt of proposals to

Select one of the following:

  • negotiate prices with only those offerors who are in the competitive range.

  • determine whether or not a proposal should be placed in the competitive range.

  • identify proposal deficiencies and allow offerors to revise its proposal accordingly.

  • discuss aspects of an offeror’s proposal that could, in the opinion of the CO, be altered to materially enhance the proposal’s potential for award.

Explanation

Question 21 of 82

1

The overall objective of negotiations is to

Select one of the following:

  • obtain the lowest price possible.

  • never settle on a price that is outside of the government’s minimum and maximum objective.

  • negotiate a contract type with a price providing the greatest incentive for efficient and economical performance.

  • negotiate a contract below what the government believes is reasonable for a particular contract requirement while still allowing the contractor to make a profit.

Explanation

Question 22 of 82

1

In noncompetitive negotiations, which price position supports the price believed to be most reasonable based on the government’s analysis?

Select one of the following:

  • Minimum.

  • Objective.

  • Median.

  • Maximum.

Explanation

Question 23 of 82

1

What profit analysis method assigns values to various profit factors, resulting in a calculated profit objective?

Select one of the following:

  • Price analysis.

  • Weighted guidelines.

  • Profit application guidelines.

  • Contractor cost/risk analysis.

Explanation

Question 24 of 82

1

When conducting negotiations, the inability to compromise may be avoided by

Select one of the following:

  • using concessions to split any differences.

  • threatening to cancel and resolicit the requirement.

  • using other non-price factors to take the focus off price alone.

  • establishing an opening position that allows room to compromise.

Explanation

Question 25 of 82

1

It may become necessary to walk away from negotiations when

Select one of the following:

  • a reasonable person would consider it to be a bad deal.

  • the government will exceed its maximum price position.

  • the negotiations begin to exceed a reasonable amount of time.

  • the parties cannot agree on price alone, although it is known that a better deal does not exist.

Explanation

Question 26 of 82

1

When a deficiency is found in an offeror’s proposal, the government must

Select one of the following:

  • not further consider the offeror for award.

  • provide suggestions on how to correct the deficiency.

  • identify it and provide the offeror an opportunity to improve the proposal.

  • discuss every aspect of the proposal that received less than the maximum possible rating.

Explanation

Question 27 of 82

1

What may the contracting officer request during discussions to clarify the offeror’s position for further discussion?

Select one of the following:

  • Proposal revision.

  • Counteroffer.

  • Revised quote.

  • Determination and finding.

Explanation

Question 28 of 82

1

When evaluating proposal revisions in a lowest price technically acceptable (LPTA) source selection

Select one of the following:

  • compare proposals against each other.

  • the government may not request final proposal revisions from any offerors.

  • the evaluation criteria established in the request for proposal (RFP) must be used.

  • the government may only make tradeoffs between cost/price and non-cost/price factors.

Explanation

Question 29 of 82

1

A comparative analysis must be completed for

Select one of the following:

  • all offerors.

  • all offerors in the competitive range.

  • only the offerors outside of the competitive range.

  • only the offerors that source selection authority (SSA) has identified.

Explanation

Question 30 of 82

1

The source selection decision document (SSDD) represents the source selection authority’s

Select one of the following:

  • independent judgment.

  • dependent judgment.

  • comparative assessment.

  • selection of best value proposal

Explanation

Question 31 of 82

1

The source selection decision document (SSDD) should

Select one of the following:

  • be written as a stand-alone document.

  • be signed and posted on the government point of entry (GPE).

  • strictly focus on lowest price and why other offerors were excluded.

  • only identify the factors and subfactors that help sell the authorities’ decision.

Explanation

Question 32 of 82

1

When preparing an award notice letter, what should be provided?

Select one of the following:

  • Award amount.

  • Ranking of other proposals.

  • Date of expected notice to proceed.

  • Amount of offerors and the awarded offeror.

Explanation

Question 33 of 82

1

Within how many days after receipt of a written request should a post-award debriefing be provided to an unsuccessful offeror?

Select one of the following:

  • 3.

  • 5.

  • 7.

  • 10.

Explanation

Question 34 of 82

1

Post-award debriefings must include

Select one of the following:

  • the overall evaluated cost or price and technical ratings of all offerors.

  • the government’s evaluation of the signification weaknesses in the offeror’s proposal.

  • names of individuals providing reference information about the offeror’s past performance.

  • a point by point comparison of the debriefed offeror’s proposal with those of other offerors.

Explanation

Question 35 of 82

1

Upon completion of a debriefing, offerors must be notified that

Select one of the following:

  • no further questions are permissible.

  • debriefings may be reopened at the discretion of the contract officer (CO).

  • only the most highly rated offers will be retained for use in future acquisitions.

  • requests for additional information must be submitted in writing with three days after conclusion of the debriefing.

Explanation

Question 36 of 82

1

If an untimely request for a debriefing was received, a contract officer

Select one of the following:

  • may decline to provide the debriefing.

  • must limit the debriefing to who received the award and the award amount.

  • must provide a complete debriefing to all offerors who request one regardless of timeliness.

  • is required to provide a debriefing in accordance with the Freedom of Information Act.

Explanation

Question 37 of 82

1

What may contractors receive when site conditions differ from what was indicated in the specifications and drawings?

Select one of the following:

  • Time.

  • Money.

  • Time, money or both.

  • Cancelling of the contract.

Explanation

Question 38 of 82

1

Contractor progress schedules are required

Select one of the following:

  • for all construction contracts.

  • for only architect and engineering contracts.

  • when contracts exceed the simplified acquisition threshold (SAT) and the performance period is greater than 30 days.

  • when contracts exceed the SAT and the performance period is greater than 60 days.

Explanation

Question 39 of 82

1

Why is the site visit conducted so quickly after issuing the solicitation?

Select one of the following:

  • So that interested contractors have time to submit requests for information for clarifications.

  • So that interested contractors have time to submit a protest.

  • Because the site visit is only conducted when contractors request one.

  • Because the site visit allows civil engineering to verify the requirements.

Explanation

Question 40 of 82

1

What should the contracting officer or contract specialist do when there are discrepancies found during the post-award site visit?

Select one of the following:

  • Forward them to contracting officer representative or contractor so they can be addressed.

  • Tell the contractor that payment is being withheld.

  • Document the file and address later.

  • Tell the customer.

Explanation

Question 41 of 82

1

What type of Contractor Performance Assessment Reporting System (CPARS) report is used at the end of the first 12-month option period on a 5-year contract?

Select one of the following:

  • Final.

  • Interim.

  • Addendum.

  • Annual interim.

Explanation

Question 42 of 82

1

The Truthful Cost or Pricing Data statue requires contractors to submit cost or pricing data when the procurement is expected to be valued over

Select one of the following:

  • the simplified acquisition threshold.

  • $750,000.

  • $2 million.

  • the micro purchase threshold.

Explanation

Question 43 of 82

1

Certification of cost or pricing data states that

Select one of the following:

  • to the best of the contractor’s knowledge, the cost or pricing data is accurate and complete at the date of the agreement.

  • to the best of the contractor’s knowledge, the cost or pricing data is verified by the suppliers.

  • the contractor agrees to the cost or price of the contract.

  • the contractor’s estimates of cost or pricing data is correct.

Explanation

Question 44 of 82

1

What type of change improperly exceeds the scope of a procurement and is one which could not have been reasonably anticipated by offerors?

Select one of the following:

  • Cardinal change.

  • Unilateral change.

  • Restrictive change.

  • Constructive change.

Explanation

Question 45 of 82

1

A contractor is required to certify any claim

Select one of the following:

  • exceeding the micro-purchase threshold.

  • exceeding $100,000.

  • exceeding $1,000,000.

  • when the contract is subject to the Truthful Cost or Pricing Data statue.

Explanation

Question 46 of 82

1

What Air Force instruction (AFI) governs the use of the government purchase card (GPC)?

Select one of the following:

  • AFI 64–105.

  • AFI 64–102.

  • AFI 64–117.

  • AFI 36–2903.

Explanation

Question 47 of 82

1

The agency/organization program coordinator (A/OPC) is responsible for

Select one of the following:

  • for oversight of all cardholders under his or her control.

  • initiating government purchase card (GPC) accounts, issuing delegation letters, and providing mandatory training.

  • staying aware of GPC rules, following those rules, and making purchases within their limits.

  • providing training, distributing cards, replacing lost or stolen cards, and providing customer service.

Explanation

Question 48 of 82

1

Which is not one of the phases of strategic sourcing?

Select one of the following:

  • Standup phase.

  • Execution phase.

  • Source selection strategy phase.

  • Management performance phase.

Explanation

Question 49 of 82

1

What strategic sourcing tool assesses data such as money spent, type of contracts used, size of purchase, item(s) purchased, and so forth?

Select one of the following:

  • Cost analysis.

  • Price analysis.

  • Spend analysis.

  • Portfolio management.

Explanation

Question 50 of 82

1

Two-step sealed bidding is especially useful in

Select one of the following:

  • contracts that have a short lead time and need to be award quickly.

  • acquisitions requiring complex technical proposals.

  • cost-plus-fixed fee contracts.

  • construction contracts.

Explanation

Question 51 of 82

1

One condition why two-step sealed bidding may be used in preference to negotiations is when

Select one of the following:

  • definite criteria exist for evaluating technical proposals.

  • only one technically qualified source is expected to be available.

  • there is not sufficient time available for use of the two-step sealed bidding method.

  • a cost-reimbursement contract will be used.

Explanation

Question 52 of 82

1

The purpose of contract financing is to

Select one of the following:

  • assist the contractor in paying costs incurred during the performance of the contract.

  • assist the contractor in getting their business started.

  • help the contractor with lease or rental payments.

  • help the contractor with the cost-type contract.

Explanation

Question 53 of 82

1

Which is a type of noncommercial contract financing payment?

Select one of the following:

  • Lien.

  • Letter of credit.

  • Loan guarantees.

  • Progress payments based on insurance.

Explanation

Question 54 of 82

1

Commercial advance and interim payments may be made when the

Select one of the following:

  • form of contract financing is in the best interest of the contractor.

  • contract item being financed is a commercial supply or service.

  • contract being awarded is under sole-source procedures.

  • contract price is below the SAT.

Explanation

Question 55 of 82

1

What type of financing has the least amount of risk to the government?

Select one of the following:

  • Advance.

  • Private.

  • Partial

  • Cost.

Explanation

Question 56 of 82

1

Which task falls under contract support integration?

Select one of the following:

  • Planning, validating and prioritizing requirements.

  • Contracting support planning and coordinating common contracting actions.

  • Translating requirements into contract terms, and developing, soliciting, executing, and closing out contracts.

  • Planning contractor management, preparing for contractor deployment, deploying or redeploying contractors.

Explanation

Question 57 of 82

1

Which is Phase III of the operational phase?

Select one of the following:

  • Deter.

  • Stabilize

  • Dominate.

  • Reinforce.

Explanation

Question 58 of 82

1

What is the purpose of the Joint Requirements Review Board (JRRB)?

Select one of the following:

  • Review, validate, approve, and prioritize contract support requirements.

  • Ensure contract support actions support the joint force commanders command guidance.

  • Maximize contracting capabilities while minimizing the competition for limited vendor capabilities.

  • Ensure that contracting and other related logistics efforts are properly coordinated across the entire area of responsibility.

Explanation

Question 59 of 82

1

International agreements between two or more governments that address various privileges, immunities, and responsibilities and enumerate the rights and responsibilities of individual members of a deployed force are known as

Select one of the following:

  • status of forces agreements (SOFA).

  • law of armed conflict (LOAC).

  • wartime agreements.

  • host nation laws.

Explanation

Question 60 of 82

1

Contractors authorized to accompany the force (CAAF)

Select one of the following:

  • is a term given to describe local national contractors.

  • is a term used to describe all Department of Defense civilian contractors no matter the location.

  • is a term given to describe local national contractors and third country nationals.

  • are contractor employees who are authorized to accompany the force in applicable foreign contingency operations.

Explanation

Question 61 of 82

1

Contractors authorized to accompany the force (CAAF) are

Select one of the following:

  • subject to all local laws, regardless of status.

  • exempt from all host nation laws during a contingency.

  • exempt from all laws in a contingency environment unless stated in the contract.

  • subject to local laws unless specifically exempted by Status of Forces Agreements (SOFA) security agreements.

Explanation

Question 62 of 82

1

What is a major element of the air expeditionary force (AEF) structure?

Select one of the following:

  • Deployment force.

  • Noninstitutional force.

  • Expeditionary force.

  • Readily available force.

Explanation

Question 63 of 82

1

What is the purpose of the reclama process?

Select one of the following:

  • To request relief from the deployment tasking by asking the authority to reconsider its decision.

  • To guarantee that the unit will be relieved from the deployment tasking.

  • To ensure a unit will not be tasked with a deployment.

  • To ensure the commander can control if his or her Airmen can deploy.

Explanation

Question 64 of 82

1

When should the contracting officer conduct the mission brief?

Select one of the following:

  • As soon as possible.

  • Once you have your office established.

  • Once the rest of your staff arrive on location.

  • Once the deployed commander seeks you out and asks for one.

Explanation

Question 65 of 82

1

Who is the second person to receive contract authority?

Select one of the following:

  • Senior contracting official (SCO).

  • Secretary of Defense (SecDef).

  • President.

  • Head of contracting authority (HCA).

Explanation

Question 66 of 82

1

Which form explicitly documents a contracting officer’s warrant?

Select one of the following:

  • Standard Form (SF) 1400.

  • SF 1401.

  • SF 1402.

  • SF 1403.

Explanation

Question 67 of 82

1

Which of the following is a main contracting-related option?

Select one of the following:

  • Defense Contract Management Agency.

  • Functional Contracting Command.

  • Defense Logistics Agency.

  • Lead service component responsible for theater support contracting.

Explanation

Question 68 of 82

1

Which contracting-related organizational structure is best suited for long-term missions and missions beyond the capability of a single service?

Select one of the following:

  • Service component support to own forces.

  • Geographic contracting command (GCC).

  • Joint theater support contracting command (JTSCC).

  • Lead service component responsible for theater support contracting.

Explanation

Question 69 of 82

1

Which type of funds will a contingency contracting officer (CCO) mainly use?

Select one of the following:

  • Procurement.

  • Military construction (MILCON).

  • Operations and maintenance (O&M).

  • Morale, welfare, and recreation (MWR)/non-appropriated funds (NAF).

Explanation

Question 70 of 82

1

The primary goal of Defense Base Act insurance is to cover

Select one of the following:

  • workers on military bases outside the United States.

  • workers on military bases outside and inside the United States.

  • military personnel on military bases outside the United States.

  • military personnel on coalition bases outside the United States.

Explanation

Question 71 of 82

1

Which regulation(s) cover expedited contracting procedures?

Select one of the following:

  • Air Force Instruction (AFI) 64–105.

  • AFI 64–102.

  • Federal Acquisition Regulation (FAR) Part 18.

  • FAR Part 18 and Defense Federal Acquisition Regulation Supplement (DFARS) Part 218.

Explanation

Question 72 of 82

1

Who normally fulfills the field ordering officer (FOO) role?

Select one of the following:

  • Army soldiers.

  • Resource advisors (RA).

  • Contracting officers (CO).

  • Contracting officer representatives (COR).

Explanation

Question 73 of 82

1

Who appoints field ordering officers (FOO)?

Select one of the following:

  • Contractor chief executives.

  • Squadron commanders.

  • Contingency contracting officers (CCO).

  • Contracting officer representatives (COR).

Explanation

Question 74 of 82

1

What must field ordering officers (FOO) maintain when keeping track of their purchases?

Select one of the following:

  • Copy of the purchase request document.

  • Copy of purchase receipt.

  • Appointment letter.

  • Standard Forms 44.

Explanation

Question 75 of 82

1

Which is a field ordering officer (FOO) violation?

Select one of the following:

  • Authorized commitments.

  • Purchases at authorized limits.

  • Purchases outside the purpose of the appropriated funds.

  • Ensuring competition in contracting act requirements (CICA) are met.

Explanation

Question 76 of 82

1

Who is responsible for determining contractors authorized to augment the force (CAAF)/non-CAAF status?

Select one of the following:

  • Contracting officer (CO).

  • Contract specialist.

  • Host-nation liaison.

  • Base commander.

Explanation

Question 77 of 82

1

In-theater management of contractor personnel is maintained in

Select one of the following:

  • security forces.

  • System for Award Management (SAM).

  • Defense Biometric Identification System (DBIDS).

  • Synchronized predeployment operational tracker (SPOT).

Explanation

Question 78 of 82

1

Which is a tool that a contingency contracting officer (CCO) can use to research an area of responsibility (AOR)?

Select one of the following:

  • Comprehensive emergency management plan (CEMP).

  • Lessons learned plan.

  • Physically flying to the location.

  • The respective combatant command (CCMD) operational contract support integration cell (OCSIC).

Explanation

Question 79 of 82

1

What is a category of defense support of civil authorities (DSCA)?

Select one of the following:

  • Undesignated law enforcement support.

  • International emergencies.

  • Domestic emergencies.

  • Space activities.

Explanation

Question 80 of 82

1

Humanitarian assistance is the Department of Defense (DOD) term

Select one of the following:

  • for relief and development activities that take place in the context of an overseas military exercise, training event, or operation.

  • for domestic emergencies that affect the public welfare, endanger life and property, or disrupt the usual process of government.

  • that allows the DOD to provide aid whenever a military accident happens on a DOD installation.

  • that authorizes the DOD to help state and local governments alleviate the suffering and damage caused by disasters.

Explanation

Question 81 of 82

1

Which act authorizes the federal government to help state and local governments alleviate the suffering and damage caused by disasters?

Select one of the following:

  • Disaster Relief Act of 1974.

  • Department of Defense Disaster Response Act.

  • Overseas Humanitarian, Disaster and Civic Aid Act (OHDACA).

  • Robert T. Stafford Disaster Relief and Emergency Assistance Act.

Explanation

Question 82 of 82

1

If unable to exercise contingency contracting officer (CCO) skills in a base exercise, who prepares CCOs with unit specific exercises?

Select one of the following:

  • Contracting commander.

  • Unit training manager. (UTM).

  • Unit deployment manager. (UDM.)

  • Installation’s wing inspection team (WIT).

Explanation