Intake9 BIM L4C BEP

Question 1 of 5

1

Who authors the BIM Execution Plan?

Select one of the following:

  • The BIM Manager

  • The Employer

  • The Principal Consultant

  • The BIM Coordinator

Explanation

Question 2 of 5

1

When should the BIM Execution Plan be authored and signed off?

Select one of the following:

  • When Documentation phase starts

  • Before Design begins

  • Before Construction begins

  • When project handed over to employer for Facilities Management

Explanation

Question 3 of 5

1

The BIM Execution Plan should include:

Select one of the following:

  • Project Goals

  • BIM Deliverables

  • Process for BIM

  • All of the above

Explanation

Question 4 of 5

1

Hardware and Software requirements should be included in the BIM Execution Plan

Select one of the following:

  • True
  • False

Explanation

Question 5 of 5

1

The "BIM Use Case Template" in Appendix A is identical to the SIngapore BIM Guide Appendix B "Objectives and Responsibilities Matrix"

Select one of the following:

  • True
  • False

Explanation