What are tasks of the Production Cutover deliverable?
(More than one answer is correct. Please choose the correct answers.)
Initiate Solution Manager Update - Solution Documentation
Execute Go Live Simulations 1 - n
Conduct Data Quality Readiness Check
Final Check of Production Readiness and Sign-Off
Provide Post Go Live Support
What is the purpose of the Cut Over work stream in the Realisation phase?
(One answer)
To simulate the cut over procedure in the development environment and to provide support for the solution during the period immediately following production cutover.
To execute the SAP Going Live Check service
To begin documenting the timing, steps, and logistics for moving from the as-is solution to the to-be solution and to complete the Technical Integration Check service.
To execute the functional testing and performance testing.
To plan the production cutover weekend party
What is the purpose of the preliminary cutover plan?
To setup the schedule transfer of data from the SAP development system and legacy systems to the SAP production system.
To document the strategy, scope and timelines for moving from the as-is solution to the to-be solution and the hyper care period immediately following go-live.
To identify which named users from the customer organisation that will drive the cutover process according to the working schedule.
To execute communication activities to project stakeholders during cut-over and go live.
To document the instructions on how to slice the cake after a successful go-live.