Bates City's municipal solid waste landfill (MSWLF) is accounted for as an enterprise fund. The estimated total closure and postclosure costs are $375,000. At the beginning of the current reporting period the landfill was estimated to be 40 percent filled and the MSWLF had recognized expenses totaling $150,000 (40 percent of $375,000). The city's sanitation engineers have estimated at the end of the current fiscal year that total closure and postclosure costs remain at $375,000 and the landfill is now 45 percent filled. The current year expense, referred to as provision for closure and postclosure costs, should be debited for:
Select one of the following: