The RIBA Plan of Work 2013 Unit 5 M1 Preparation

Description

To complete this test you will need to refer to the following links. http://www.ribaplanofwork.com/Default.aspx http://www.youtube.com/watch?v=98UGXi0nUbs
Tom Jones7007
Quiz by Tom Jones7007, updated more than 1 year ago
Tom Jones7007
Created by Tom Jones7007 about 10 years ago
239
3

Resource summary

Question 1

Question
How may stages are in the RIBA Plan of work 2013
Answer
  • 7
  • 5
  • 10
  • 8
  • 12

Question 2

Question
Which part of the stage of the RIBA Plan of Work 2013 is particularly relevant in the context of sustainability.
Answer
  • Stage 4
  • Stage 1
  • Stage 0
  • Stage 7
  • Stage 5

Question 3

Question
Stage 6 is primarily concerned with?
Answer
  • Post occupancy
  • Concept design
  • Preparation and brief
  • Hand over and close out
  • Developed design maps

Question 4

Question
What does BIM stand for
Answer
  • Building Information Modelling
  • Business Information Modelling
  • Built Individual Model
  • Building In Materials

Question 5

Question
Which stage is a new stage in which a project is strategically appraised and defined before a detailed brief is created?
Answer
  • Stage 4 Technical Design
  • Stage 5 Construction
  • Stage 0 Strategic Definition
  • Stage 3 Developed Design

Question 6

Question
Which stage of the RIBA plan of Work focuses on making sure the that the initial business case matches the desired outcomes.
Answer
  • Stage 7 In use
  • Stage 0 Strategic definition
  • Stage 6 Handover and close out
  • Stage 3 Developed design
  • Stage 5 Construction

Question 7

Question
What is meant by the term procurement?
Answer
  • The design and execution of the infrastructure .
  • The construction of an object or a system.
  • The acquisition of goods, services or works from an outside external source.
  • Preparing for and forming building systems.

Question 8

Question
Is The RIBA Plan of Work 2013 itself a contractual document?
Answer
  • Yes
  • No

Question 9

Question
Within the RIBA Plan of work which task bars are fixed and always present?
Answer
  • Task Bar 1 Core Objectives, Task Bar 3 Programme & Task Bar 8 Government Gateways.
  • Task Bar 8 Government Gateways, Task Bar 6 Sustainability Checkpoints & Task Bar 3 Programme
  • Task Bar 1 Core Objectives,Task Bar 5 Key Support Tasks, & Task Bar 7 Information Exchanges
  • Task Bar 6 Sustainability Checkpoints,Task Bar 4 (Town) Planning &Task Bar 2 Procurement

Question 10

Question
Which two task-bars can be switched on or off in The RIBA Plan of Work 2013?
Answer
  • Task Bar 6 Sustainability Checkpoints & Task Bar 8 Government Gateways.
  • Task Bar 3 Programme & Task Bar 1 Core Objectives.
  • Task Bar 2 Procurement & Task Bar 5 Key Support Tasks,
  • Task Bar 8 UK Government Information Exchanges & Task Bar 6 Sustainability Checkpoints.

Question 11

Question
Which three task-bars are variable in The RIBA Plan of Work 2013?
Answer
  • Task Bar 4 (Town) Planning, Task Bar 5 Key Support Tasks & Task Bar 1 Core Objectives.
  • Task Bar 2 Procurement ,Task Bar 3 Programme & Task Bar 8 Government Gateways.
  • Task Bar 3 Programme ,Task Bar 2 Procurement & Task Bar 4 (Town) Planning
  • Task Bar 6 Sustainability Checkpoints, Task Bar 1 Core Objectives & Task Bar 5 Key Support Tasks.

Question 12

Question
Why has the UK Government Information Exchanges task bar has been introduced?
Answer
  • To encourage consideration of the stages that the UK Government requires information to be exchanged.
  • To provide guidance on the information that would typically be delivered at the Information Exchanges at the end of each stage.
  • To allow for a number of forms of procurement.
  • To underline the need on every project for a Project Programme that sets out the duration of each stage and any supporting activities.

Question 13

Question
What has been a core requirement of collaborative contracts for some time as it ensures that each party is involved in the process of agreeing timescales and is fully aware of the risks that the programme generates in relation to their specific Schedule of Services?
Answer
  • Construction Programme
  • Design Programme
  • Building Contract
  • Project Programme.

Question 14

Question
On certain projects, where it is uncertain that consent will be granted, can the client appoint all of the designers or may appoint them on a restricted Stage 2 Schedule of Services?
Answer
  • Yes
  • No

Question 15

Question
The Sustainability Checkpoints task bar is selectable and can be switched off?
Answer
  • True
  • False

Question 16

Question
Where detailed circumstances specific to a given project require an alternative approach, what should used to deal with this?
Answer
  • Building Contract
  • Health and Safety Strategy
  • Project Programme.
  • Design Responsibility Matrix

Question 17

Question
What does the UK Government recognise that a client does not need to be involved in?
Answer
  • Every Information Exchange
  • Data-rich information that can be used post- occupancy to manage its entire estate and to allow stringent benchmarking activities to occur.

Question 18

Question
Which task-bar sets out key tasks in relation to statutory requirements, such as those relating to Building Regulations submissions and project and design management protocols, roles and responsibilities?
Answer
  • Task Bar 7 Information Exchanges
  • Task Bar 5 Key Support Tasks
  • Task Bar 1 Core Objectives
  • Task Bar 8 Government Gateways

Question 19

Question
It is also acknowledged that on certain projects (conservation projects, for example) other planning matters may have to be concluded during which other stage?
Answer
  • Task Bar 5 Key Support Tasks
  • Task Bar 4 (Town) Planning
  • Task Bar 3 Programme
  • Task Bar 2 Procurement

Question 20

Question
The RIBA Plan of Work 2013 does all of the following Acts across the full range of sectors and project sizes: Provides straight-forward mapping for all forms of procurement. Integrates sustainable design processes. Maps Building Information Modelling (BIM) processes and provides flexible around (town) planning procedures.
Answer
  • True
  • False
Show full summary Hide full summary

Similar

A-Level Biology: Cell Division
cian.buckley+1
Geography Coastal Zones Flashcards
Zakiya Tabassum
Chemistry Module C2: Material Choices
James McConnell
Biology 1 Keeping Healthy Core GCSE
Chloe Roberts
AQA GCSE Physics Unit 2.3
Matthew T
GCSE AQA Chemistry Atomic Structure and Bonding
Joseph Tedds
Business Studies GCSE
phil.ianson666
Input, output and storage devices
Mr A Esch
1PR101 2.test - Část 12.
Nikola Truong
Diseño de Software
Verny Fernandez