Question 1
Question
1. Definition of “Done” is
Answer
-
a) Initially defined per product by Scrum Team, but may change throughout the product development duration
-
b) Initially defined per Scrum Team, and doesn’t change
-
c) Defined after first Sprint based on the new insights obtained from first Sprint Review
Question 2
Question
2. Which of the following statements are true? Select all that apply
Answer
-
a) After Sprint Planning, a sprint cannot proceed without complete requirement specification
-
b) After Sprint Planning, a sprint cannot proceed without a Sprint Goal
-
c) After Sprint Planning, a sprint can proceed without complete Sprint Backlog
-
d) After Sprint Planning, a sprint cannot proceed without complete architecture
Question 3
Question
3. A Development Team is self-organized and empowered. It is also the authority on deciding what business needs are required to be developed
Question 4
Question
4. Who decides the duration of the Sprint?
Answer
-
a) Product manager
-
b) Scrum Master
-
c) Development Team
-
d) Scrum Team
Question 5
Question
5. A Product Owner is not available for Scrum events and not supportive enough for Development Team. The next immediate accountability is with
Answer
-
a) Development Team that needs to cancel the Sprint
-
b) Stakeholders that need to get a written commitment from Product Owner
-
c) Product Owner’s manager who needs to engage the Development Team and understand their problems
-
d) Scrum Master, who needs to educate Product Owner on his role
Question 6
Question
6. When a Product Backlog is retired?
Answer
-
a) When the Product Owner retires
-
b) When all the Sprints are over
-
c) When the Product retires
-
d) When the Customer provides the sign-off on completion of the project
Question 7
Question
7. A Product Owner cannot send a representative (delegate) to the Sprint Review.
Question 8
Question
8. A Product Owner is also knowledgeable on technology. In addition to product requirements, they also impose some technical conditions that the product should meet. These conditions must be added to
Answer
-
a) Product Backlog
-
b) Sprint Backlog
-
c) Definition of “Done”
Question 9
Question
9. An increment is
Answer
-
a) The sum of the value of all increments from previous iterations integrated with the Product Backlog Items “done” in latest Sprint
-
b) The sum of Product Backlog Items selected into Sprit Backlog
-
c) The sum of Product Backlog Items “done” in latest Sprint
Question 10
Question
10. What are the true statements?
Answer
-
a) Scrum Team is responsible for formulating a Sprint Goal
-
b) When existing Product Backlog Items in the Sprint Backlog are modified, the Sprint Goal is bound to become invalid
-
c) The coherence between Product Backlog items is made transparent by Sprint Goal. Lack of coherence will lead to them working individually