Question 1
Question
[blank_start]Residual Risk[blank_end] is the [blank_start]remaining[blank_end] risk which cannot be defined in more detail after elimination or inclusion of all conceivable quantified risks in a risk consideration. Residual risk is the level of uncontrolled risk remaining after the risk treatment.
Answer
-
remaining
-
total
-
Residual Risk
-
Risk Acceptance
-
Risk Treatment
-
Risk Tolerance
Question 2
Question
[blank_start]Risk Acceptance[blank_end] is to make an informed decision to accept the [blank_start]likelihood[blank_end] and [blank_start]impact[blank_end] of a particular risk. Risk Acceptance depends on risk criteria and the risk appetite of Top Management.
Answer
-
likelihood
-
total
-
impact
-
probability
-
Risk Acceptance
-
Risk Treatment
-
Risk Tolerance
-
Residual Risk
Question 3
Question
[blank_start]Key Planing Scenario (KPS)[blank_end] provides the [blank_start]BC Team[blank_end] with a perspective of the [blank_start]magnitude[blank_end] of disaster that an organization is willing to commit the [blank_start]resources[blank_end] to mitigate and is acceptable to the organisation. This organisation includes the Executive Management, Organization BCM Coordinator, BCP team, DRP team and the Crisis Management Team.
Question 4
Question
A Man-made Threat is an event resulting from [blank_start]human intent[blank_end], negligence, or error. It is divided into into two category: [blank_start]human[blank_end] or [blank_start]technology[blank_end].
Answer
-
human intent
-
sabotage
-
technology
-
financial
-
human
-
management
Question 5
Question
[blank_start]Natural Threat[blank_end] is a threat resulting from the effect of [blank_start]nature[blank_end] that may cause a disruptive [blank_start]impact[blank_end] to an organization.
Answer
-
nature
-
environment
-
impact
-
effect
-
Natural Threat
-
Technology Threat
Question 6
Question
[blank_start]Period of Disruption[blank_end] is the expected [blank_start]residual[blank_end] disruption resulting from each identified threats, taking into consideration existing controls. The period of disruption is an estimated duration during which the organization’s operations are disrupted ([blank_start]operationally[blank_end]), or access to the primary location is denied ([blank_start]infrastructure[blank_end]).
Answer
-
residual
-
existing
-
operationally
-
intentionally
-
infrastructure
-
premise
-
Period of Disruption
-
Key Planning Scenario
Question 7
Question
A [blank_start]Threat[blank_end] is an indication or warning of probable man-made or natural situation that can cause [blank_start]disruption[blank_end] to an organization’s operations or services.
Answer
-
Threat
-
Disaster
-
disruption
-
disturbance
-
Hazard
Question 8
Question
The disruption caused by the occurrence of the [blank_start]threat[blank_end]. It can be operational in nature, causing disruption to the [blank_start]functionality[blank_end] of the organization, or infrastructure in nature which will deny access to or usage of the primary [blank_start]location[blank_end].
Answer
-
functionality
-
revenue
-
location
-
site
-
threat
-
disaster
Question 9
Question
[blank_start]Worst Case Scenario[blank_end] is the worst possible [blank_start]condition[blank_end] or outcome out of the several [blank_start]possibilities[blank_end] in planning for a [blank_start]disaster[blank_end].
Answer
-
condition
-
situation
-
possibilities
-
alternatives
-
disaster
-
crisis
-
Worst Case Scenario
-
Key Planning Scenario
Question 10
Question
[blank_start]Risk Analysis[blank_end] is the process to evaluate and determine the risk rating, which is the product of [blank_start]risk likelihood[blank_end] and [blank_start]risk impact[blank_end].
Answer
-
Risk Analysis
-
Risk Rating
-
Risk Assessment
-
risk likelihood
-
likelihood
-
risk impact
-
impact
Question 11
Question
[blank_start]Risk Appetite[blank_end] is amount and the type of risks that an organization is willing to take in or absorb.
Answer
-
Risk Appetite
-
Risk Impact
-
Risk Level
Question 12
Question
[blank_start]Risk Assessment[blank_end] is the overall process of [blank_start]risk identification[blank_end], [blank_start]risk analysis[blank_end] and risk evaluation.
Answer
-
Risk Assessment
-
Risk Appetite
-
Risk Likelihood
-
Risk Impact
-
risk identification
-
risk determination
-
risk analysis
-
risk assessment
Question 13
Question
[blank_start]Risk Avoidance[blank_end] is to make an informed decision not to become involved in or to withdraw from a risk situation.
Answer
-
Risk Avoidance
-
Risk Treatment
Question 14
Question
[blank_start]Risk Evaluation[blank_end] is the process used to compare the estimated risk against the given risk criteria so as to determine the significance of the risk.
Answer
-
Risk Evaluation
-
Risk Appetite
-
Risk Assessment
-
Risk Level
Question 15
Question
[blank_start]Risk Impact[blank_end] is an outcome resulting from a threat that will impact an organization objectives or assets.
Answer
-
Risk Impact
-
Risk Appetite
-
Risk Likelihood
-
Risk Rating
-
Impact
Question 16
Question
[blank_start]Risk Level[blank_end] is the overall level of assessed risk to the risk rating.
Answer
-
Risk Level
-
Risk Appetite
-
Risk Likelihood
-
Risk Impact
Question 17
Question
[blank_start]Risk Likelihood[blank_end] is the state of being probable or chance of a threat occurring.
Answer
-
Risk Likelihood
-
Risk Appetite
-
Risk Impact
-
Risk Rating
Question 18
Question
[blank_start]Risk Mitigation[blank_end] is to implement measures so as to lower the exposure to the risk.
Answer
-
Risk Mitigation
-
Risk Reduction
Question 19
Question
[blank_start]Risk Rating[blank_end] is the result of the multiplication of the assigned value for Risk Likelihood against the assigned value of [blank_start]Risk Impact[blank_end].
Answer
-
Risk Rating
-
Risk Level
-
Risk Impact
-
Risk Appetite
Question 20
Question
[blank_start]Risk Reduction[blank_end] is to take appropriate actions to lessen the likelihood, negative consequences or both, associated with a risk.
Answer
-
Risk Reduction
-
Risk Treatment
-
Risk Mitigation
-
Risk Transference
Question 21
Question
[blank_start]Risk Tolerance[blank_end] is the amount if risk that an organization is willing to accept or be exposed to.
Answer
-
Risk Tolerance
-
Risk Acceptance
-
Residual Risk
Question 22
Question
[blank_start]Risk Transference[blank_end] refers to the shifting of the burden of loss for a risk to another party through legislation, contract, insurance or other means.
Answer
-
Risk Transference
-
Risk Treatment
Question 23
Question
[blank_start]Risk Treatment[blank_end] is the selection and implementation of appropriate options for dealing with risk.
Answer
-
Risk Treatment
-
Risk Management
-
Risk Tolerance
-
Residual Risk
Question 24
Question
A [blank_start]Crisis Event[blank_end] is an event (or occurrences that happen over a period of time) leading up to the crisis can pertain to people or human resources.
Answer
-
Crisis Event
-
Crisis Scenario
Question 25
Question
A [blank_start]Crisis Scenario[blank_end] describes a situation that might disrupt the business.
Question 26
Question
[blank_start]Impact[blank_end] is an evaluated consequence of a particular effect due to the cause, such as a threat.
Question 27
Question
[blank_start]Hazard[blank_end] is potential harm or damage, or a situation which poses a level of threat to life, health, property or environment.
Question 28
Question
What is the biggest benefit of a successfuly Risk Analysis and Review phase
Question 29
Question
Which of the following is NOT the responsibility of the an organization's BCM Coordinator during the Business Impact Analysis phase