Question 1
Question
An advantage of using CAD programs, over traditional hand drawing methods is that
Question 2
Question
Which of the following is true about traditional hand produced drawings compared to using a CAD package?
Answer
-
Initial set up costs are high
-
Drawings are more accurate
-
Editing can take longer
-
Drawings can be produced quicker
Question 3
Question
Which one of the following projection types is most likely to show room dimensions for a house?
Answer
-
Isometric
-
Axonometric
-
Photographic
-
Orthographic
Question 4
Question
Orthographic projections are required when applying for
Question 5
Question
Door and window schedules can be produced from a
Answer
-
table
-
drawing
-
programme
-
specification
Question 6
Question
Isometric drawings show objects in
Answer
-
two dimension
-
three dimension
-
two point perspective
-
three point perspective
Question 7
Question
A 30° / 60° set square is required to draw an
Answer
-
elliptical axis
-
isometric axis
-
elevational axis
-
orthographic axis
Question 8
Question
Which of the following is the most suitable thermal insulating material for a conservatory roof?
Answer
-
Perspex
-
Double glazing
-
Twin wall plastic
-
Polyisocyanurate
Question 9
Question
Whish one of the following thermal insulation materials can be cut with a pair of scissors and fixed with a staple gun?
Answer
-
Multi foil
-
Mineral wool
-
Polyvinyl butyl
-
Polyisocyanurate
Question 10
Question
Insulation is positioned within a brick cavity wall to
Answer
-
prevent damp rising
-
minimise capillary attraction
-
conform to fire safety legislation
-
conform to building regulations
Question 11
Question
When insulation is inserted between the rafters in a roof, care must be taken to ensure air flow is
Answer
-
limited
-
adjustable
-
prevented
-
maintained
Question 12
Question
Whish of the following walling construction methods has the best thermal value?
Answer
-
Stone
-
Concrete
-
Timber frame
-
Solid brick work
Question 13
Question
Energy's certificate rating A-G determine a building's
Answer
-
water usage
-
gas pressure
-
thermal efficiency
-
electrical resistance
Question 14
Question
When timber is imported into the United Kingdom it must be from
Answer
-
Europe
-
America
-
a local source
-
a managed source
Question 15
Question
What are sustainable materials?
Answer
-
Materials that do not destroy or deplete natural resources
-
Materials made only of timber
-
Materials that do not contain any plastic
-
Materials that are manufactured from recycled materials only
Question 16
Question
Which of the following formula's is used for calculating the area of a wall?
Answer
-
L x H
-
L x H³
-
L ÷ H³
-
L ÷ H
Question 17
Question
Which formula is used to find the area of a circular platform?
Answer
-
π r² v²
-
π dh
-
4/3 π r³
-
M 1/3 π r²h
Question 18
Question
Which of the following are both shown on a schedule?
Answer
-
Location and size
-
Tools and position
-
Density and porosity
-
Joint size and adhesive
Question 19
Question
When ordering supplies, an approved supplier list would be used, as they have proved in the past to be
Answer
-
friendly
-
reliable
-
expensive
-
available
Question 20
Question
A contract would be priced up using the drawings and the
Answer
-
bill of quantities
-
requisition sheet
-
contract for payment
-
contract specification
Question 21
Question
A client would put a contract out to tender in order to compare
Answer
-
specifications
-
bill of quantities
-
installation details
-
competitive prices
Question 22
Question
A quote would give the client
Answer
-
the cost of the preambles
-
a variable price for the job
-
a bid for the work to be done
-
the cost for the work to be carried out
Question 23
Question
An estimate will give the client
Answer
-
a cost for all the labour required
-
an exact cost for the complete job
-
a cost for all the materials required
-
an approximate cost for the complete job
Question 24
Question
2600 m² of wall tiles are required for a contract.
How many additional wall tiles need to be ordered when allowing 10% waste?
Answer
-
250 m²
-
260 m²
-
2610 m²
-
2860 m²
Question 25
Question
Which of the following both need to be considered when preparing a quote?
Question 26
Question
The benefit of using a Gantt chart is to show the planning of which of the following?
Question 27
Question
The lead times required for ordering materials are planned by using a
Answer
-
schedule
-
specification
-
bill of quantities
-
method statement
Question 28
Question
Which one of the following is an advantage of purchasing plant compared to hiring it?
Answer
-
Maintenance costs are reduced
-
It is less expensive in the long term
-
No additional purchases are required
-
Portable appliance testing is not required
Question 29
Question
Which one of the following is an advantage of hiring equipment?
Answer
-
It is available at any time
-
Costs are reduced in the long term
-
It can be kept at the end of a contract
-
Spare parts do not have to be purchased
Question 30
Question
Which one of the following is not a planning method used in construction?
Answer
-
Gantt chart
-
Bill of quantities
-
Programme of work
-
Critical path analysis
Question 31
Question
Which one of the following are all required pieces of information to produce a Gantt chart?
Answer
-
Start date, end date and labour required
-
Delivery dates, specifications and bill of quantities
-
Labour required, meeting agenda and bill of quantities
-
Planned activities, meeting agenda and plant required
Question 32
Question
Which one of the following documents is used to record action points of a meeting?
Answer
-
A diary
-
An agenda
-
The memos
-
The minutes
Question 33
Question
A hot works permit is required when
Answer
-
work is carried out in a kitchen
-
working in air-conditioned rooms
-
work is carried out that generates heat
-
working in confined spaces underground
Question 34
Question
An instruction from an Architect to make changes to work would be made
Answer
-
in a diary
-
on an agenda
-
on a delivery note
-
in a variation order
Question 35
Question
Which one of the following documents contains information including attendees, apologies and dates?
Answer
-
Diary
-
Agenda
-
Calendar
-
Schedule
Question 36
Question
Information about site access would be included during
Answer
-
an induction
-
a toolbox talk
-
in a safety meeting
-
an extended meeting
Question 37
Question
Safety updates and changes to working hours would be discussed during
Answer
-
an induction
-
a toolbox talk
-
a safety meeting
-
an extension meeting
Question 38
Question
Binding doors and damaged paintwork found at the end of a contract, would be identified during a
Answer
-
land survey
-
toolbox talk
-
motion study
-
defects survey
Question 39
Question
Which of the following information, other than faults found, is included on a defects schedule?
Answer
-
Programme
-
Specification
-
Remedial action
-
Contract start date
Question 40
Question
Which one of the following is required when querying an incorrect delivery of timber?
Answer
-
Total cost
-
Order number
-
Quality of timber
-