A customers business needs are best understood by answering the question _________.
Answer
What problem does our customer want to solve by using the final deliverable?
What specific service or product will be delivered at the end of the project?
What will not be done or addressed by the project?
Why don't you make me a sandwich?
Question 2
Question
What is the formula that Microsoft Project uses to calculate work, duration and units?
Answer
Units = Work * Duration
Duration = Work * Units
Work = Units / Duration
Duration = Work / Units
Question 3
Question
You have a fixed duration task of 4 days. It has a single user at full time assigned to the task. If you assign another full time worker to the task how many days will it take?
Answer
1 day
2 days
4 days
8 days
Question 4
Question
In which stage of a project would you develop the project success criteria?
Answer
Initiating
Planning
Execution
Monitoring/Controlling
Question 5
Question
Which two of the following occur during the "Performing" stage of Tuckman's team model?
Answer
Unclear purpose
Agreement and consensus
Focus on goal achievement
Power Struggles
Clear roles and responsibility
Clear Vision and purpose
Question 6
Question
Who initiates a project and what document do they create?
Answer
The group/organization who will be receiving the final deliverable initiates and creates a SOW
The vendor initiates and creates a SOW.
The vendor initiates and creates a WBS.
The group/organization who will be receiving the final deliverable initiates and creates a WBS.
Question 7
Question
S - S[blank_start]pecific[blank_end]
M - M[blank_start]easurable[blank_end]
A - A[blank_start]ction[blank_end] O[blank_start]riented[blank_end]
R - R[blank_start]elevant[blank_end] & [blank_start]Realis[blank_end]tic
T - T[blank_start]ime[blank_end] B[blank_start]ased[blank_end]