EVM Quiz

Description

this is a sample test quiz
venkatram_vasi
Quiz by venkatram_vasi, updated more than 1 year ago
venkatram_vasi
Created by venkatram_vasi almost 9 years ago
609
0

Resource summary

Question 1

Question
BAC=300; PV=200;AC=220;EV=100 If the future work is assumed to be performed at an efficiency rate that considers both the cost and schedule performance indices what is the EAC (Estimate At Completion).
Answer
  • 660
  • 500
  • 745
  • 1109

Question 2

Question
BAC=300; PV=200;AC=220;EV=100. If you future work is assumed that it will be similar to current variance , the VAC (variance At Ccompletion) is.
Answer
  • -300
  • -360
  • +360
  • +445

Question 3

Question
In a project, Earned Value is half of the Planned Value. Actual cost is double the Planned Value. Comment on the cost and schedule performance of the project.
Answer
  • on schedule, on cost
  • ahead of schedule, under cost
  • behind schedule, over cost
  • behind schedule, on cost

Question 4

Question
You are a Project manager for a road construction project to lay a road of length 20km. The budget for 1km road is $4000. half way down 10km road has been laid but the actual cost is $60,000. Assuming the current variance will continue in the future what is the Estimate At Completion(EAC)?
Answer
  • $120,000
  • $100,000
  • $40,000
  • $60,000

Question 5

Question
A project's PV,EV and AC values are shown in this picture. What is the cost and schedule performance of the project?
Answer
  • behind schedule, over cost
  • behind schedule, on cost
  • on schedule, on cost
  • ahead of schedule, under cost

Question 6

Question
A project's estimated VAC = -$10,000. The BAC of the project = $50,000 and the ETC pending works = $15,000. What is AC till date?
Answer
  • $25,000
  • $45,000
  • $40,000
  • $35,000

Question 7

Question
In your project, currently there are variances, which are not expected to occur in the future. What is the EAC of your project? BAC = $400,000; AC = $250,000; EV = $200,000; CPI = 1.25
Answer
  • $320,000
  • $750,000
  • $450,000
  • $600,000

Question 8

Question
CPI = 1.5, SPI = 0.8 What about the cost and schedule performance of the project?
Answer
  • on schedule, on cost
  • behind schedule, over cost
  • behind schedule, under cost
  • ahead of schedule, on cost

Question 9

Question
SV = 4000 and CV = 0. What is the cost and schedule performance of the project?
Answer
  • ahead of schedule, under cost
  • behind schedule, on cost
  • ahead of schedule, over cost
  • ahead of schedule, on cost

Question 10

Question
In a project , PV > EV and AC > EV. Which of the following is true?.
Answer
  • Cost performance alone is good
  • Schedule performance alone is not good
  • Both cost and schedule performance are good
  • Both cost and schedule performance are not good
Show full summary Hide full summary

Similar

Summary of Definitions/Key Terms for the PMP Exam
Andrea Leyden
PMP Prep quiz
Andrea Leyden
Project Scope Management Process
neeshar
PMP Formulas
Krunk!
PMP® Pre-Test by Coursefountain.com
Team Coursefountain
06 PROJECT TIME MANAGEMENT
miguelabascal
Project Management Integration
craigmag
How well do you know GoConqr?
Sarah Egan
PMP Executing, Monitoring and Controlling Processes
myrdenafrancis
PMP Certification Journey 1
myrdenafrancis
Translations and transformations of functions
Christine Laurich