Question 1

Question
Suggested BIM uses for tender phase (for contractor) are:
Answer
  • Cost Estimation

  • Site Planning (Logistic Planning)

Question 2

Question
Suggested BIM uses for Pre-Construction phase (for contractor) are:
Answer
  • Reviewing Consultant Models

  • Model-based Project Planning and Scheduling

Question 3

Question
Suggested BIM uses for Construction phase (for contractor) are:
Answer
  • Construction Coordination

  • Modelling and Shop Drawings

  • Sequence Complex Construction
  • Setting Out and Verification on Site
  • Prefabrication
 Proposal
  • As-Built models

  • Model for Facility Management

Question 4

Question
The contractor use site model to
Answer
  • Model the site topography
  • Add hoardings along the boundary 
with site access (gates)
  • Plan and model construction access and 
pedestrian access inside the site
  • Model the site offices, storage areas and utilities
  • Plan the vehicle movements and mobile crane movements
  • Plan locations of Tower Cranes

Question 5

Question
Once the site plan model is developed, the main contractor could communicate the site plan to his sub-contractors/workers using: 3D model walk-through 4D simulations or animation videos
Answer
  • True
  • False
Show full summary Hide full summary

Similar

Accounting Definitions
Tess Morris
Prueba de Aptitud Académica - Lenguaje
Teresa Nadal
Atomic Structure
Jenni
Geography - Restless Earth
pip.kaley
Urbanisation
Jess Molyneux
PMP Formulas
Krunk!
Different types of transitions that can affect children and young people's development.
302778
W.B. Yeats
Éimear Buggy
Types of Learning Environment
Brandon Tuyuc
Macbeth Key Quotes
Draco Malfoy
1.11 Core Textiles
T Andrews