Pregunta 1

Pregunta
Control is focused on three elements of a project. They are
Respuesta
  • scope, quality, and customer satisfaction
  • performance, delivery, and cost
  • scope, cost, and time
  • cost, time, and customer satisfaction

Pregunta 2

Pregunta
Which of the following is the key feature of cybernetic control systems?
Respuesta
  • Manual operations
  • Directional controls
  • Automatic operation
  • Specific preconditions

Pregunta 3

Pregunta
Most control systems used in project management today fall into this category of control system.
Respuesta
  • cybernetic control
  • robotic control
  • go/no-go control
  • postcontrol

Pregunta 4

Pregunta
Because project milestones may not occur at periodic intervals, go/no-go controls should be linked to the ____________; not simply to the calendar.
Respuesta
  • actual plans and to the occurrence of real events
  • corporate budgeting process
  • portfolio management review process
  • capital budgeting process

Pregunta 5

Pregunta
The critical ratio control chart uses a ratio made up of two parts -- the ratio of actual progress to scheduled progress, and the
Respuesta
  • ratio of earned value to planned cost
  • ratio of budgeted cost to actual cost
  • ratio of actual cost to budgeted cost
  • ratio of planned cost to earned value

Pregunta 6

Pregunta
The two fundamental objectives of control are the regulation of results and the
Respuesta
  • procurement of organizational assets
  • distribution of organizational assets
  • stewardship of organizational assets
  • refurbishing of organizational assets

Pregunta 7

Pregunta
The __________ process controls the project at various points in the life cycle to make sure that the project remains on course. This is opposed to waiting until the project is completed and then finding out it doesn't meet the objectives of the organization
Respuesta
  • portfolio
  • phased-step
  • phased-gate
  • overarching

Pregunta 8

Pregunta
The ___________ controls take the form of testing to see if some specific precondition has been met.
Respuesta
  • postcontrol
  • go/no-go
  • cybernetic
  • monitoring

Pregunta 9

Pregunta
______________ are directed towards improving chances for future projects to meet their goals.
Respuesta
  • postcontrols
  • Go/no-go decisions
  • cybernetics
  • negative feedback loops

Pregunta 10

Pregunta
___________ controls are usually viewed as helpful rather than as a source of unwelcome pressure if the controlees perceive themselves as able to perform inside the prescribed limits.
Respuesta
  • steering
  • negative feedback
  • postcontrols
  • cybernetic

Pregunta 11

Pregunta
Change control systems, in some industries, are part of a firm's
Respuesta
  • configuration management system
  • internal IDC system
  • cybernetic system
  • early warning system

Pregunta 12

Pregunta
A majority of uncertainty has its source in systems that lie outside the project, in its
Respuesta
  • environment
  • stakeholder area
  • sourcing model
  • control zone

Pregunta 13

Pregunta
The _____________ is calculated as (actual progress/scheduled progress) x (budgeted cost/actual cost)
Respuesta
  • critical ratio
  • highlighted ratio
  • cybernetic ratio
  • efficiency ratio

Pregunta 14

Pregunta
Scope creep can be caused by the
Respuesta
  • customer
  • team members
  • audit team
  • customer and team members

Pregunta 15

Pregunta
_______________ is a management approach that may be used to make comparisons to "best in class" practices across organizations
Respuesta
  • processing
  • benchmarking
  • leveling
  • standardizing

Pregunta 16

Pregunta
Thamhain (2013) found that ___________ was/were not only the most frequent risk class but also had the most impact on project performance.
Respuesta
  • increasing stakeholder involvement
  • changing leadership
  • decreasing costs
  • changing project requirements

Pregunta 17

Pregunta
A(n) _______________ is a monitoring system that forewarns the project manager if trouble arises.
Respuesta
  • configuration management system
  • internal IDC system
  • cybernetic system
  • early warning system

Pregunta 18

Pregunta
______________ are seen as much the same as a report card.
Respuesta
  • postcontrols
  • WBSs
  • cybernetics
  • critical ratios

Pregunta 19

Pregunta
The cybernetic control system that acts to reduce deviations from standard is called a
Respuesta
  • nonautomatic modification
  • critical ratio
  • positive feedback loop
  • negative feedback loop

Pregunta 20

Pregunta
20. For all but __________changes, a risk identification and analysis should be performed.
Respuesta
  • minor
  • major
  • most
  • few

Pregunta 21

Pregunta
The project audit covers
Respuesta
  • only financial matters
  • everything except operating matters
  • only ethical and financial matters
  • any specified scope of importance to management

Pregunta 22

Pregunta
The dimension of project success includes the obvious factors of meeting the project's technical and operational specifications. It also includes factors relating to loyalty and repurchase.
Respuesta
  • project efficiency
  • customer impact/satisfaction
  • business/direct success
  • future potential

Pregunta 23

Pregunta
The __________ dimension of project success includes factors relating to opening a new market, developing a new line of products or services. Alternatively, if an internal project, success factors include developing new technologies, skills, or competencies
Respuesta
  • project efficiency
  • customer impact/satisfaction
  • business/direct success
  • future potential

Pregunta 24

Pregunta
Identification of the direct goals of a project requires
Respuesta
  • a reading of the project structure
  • a reading of the project proposal
  • a reading of the budget
  • a reading of the WBS

Pregunta 25

Pregunta
Two of the most common limits on the depth of an investigation and level of detail presented in an audit report are
Respuesta
  • the personality of the auditor and cooperation received
  • scope and objectives
  • word processing support and existing documentation
  • money and time

Pregunta 26

Pregunta
The accumulation, storage, and maintenance of auditable data are important cost elements. Such storage may be critically important in meeting the legal test of
Respuesta
  • completeness
  • accuracy
  • due diligence
  • capacity

Pregunta 27

Pregunta
Audits done early in the project lifecycle are often focused on
Respuesta
  • technical issues
  • management issues
  • financial issues
  • personnel issues

Pregunta 28

Pregunta
For audits made late in the project's life, ____________ are major matters of interest
Respuesta
  • technical issues
  • management issues
  • financial issues
  • personnel issues

Pregunta 29

Pregunta
In the audit report, negative comments about individuals or groups associated with the project should be
Respuesta
  • avoided
  • included
  • highlighted
  • disguised

Pregunta 30

Pregunta
An evaluation of the likely outcomes of a policy and their probability of occurrence, usually conducted to compare two or more scenarios or policies is known as
Respuesta
  • technical evaluation
  • project evaluation
  • risk analysis
  • profit estimation

Pregunta 31

Pregunta
___________ is defined as a standard for performance, commonly established early on for later comparisons
Respuesta
  • audit
  • baseline
  • evaluation
  • summary

Pregunta 32

Pregunta
____________tries to capture the essence of project successes and failures so that future projects can benefit from past experiences.
Respuesta
  • auditing
  • postcontrols
  • baselining
  • ruling

Pregunta 33

Pregunta
The most immediate dimension of project success is the project's _____________ in meeting both budget and schedule
Respuesta
  • timing
  • delay
  • totality
  • effectiveness

Pregunta 34

Pregunta
A typical detailed audit is conducted when _______________ is required
Respuesta
  • a follow-up to the general audit
  • effectiveness
  • an ethical audit
  • full disclosure

Pregunta 35

Pregunta
The stated project objectives, including customer satisfaction, are part of the project's ________ goals
Respuesta
  • indirect
  • ancilliary
  • secondary
  • direct

Pregunta 36

Pregunta
The ____________ section of an audit report contains a description of the project to provide a framework of understanding for the reader. Project objectives are clearly delineated.
Respuesta
  • current status
  • future project status
  • introduction
  • risk management

Pregunta 37

Pregunta
In the current status section of an audit report, the subheading labeled ____________ will compare the work completed with the resources expended.
Respuesta
  • scope
  • cost
  • schedule
  • quality

Pregunta 38

Pregunta
The _______________ section of the audit report contains the auditor's conclusions regarding progress together with recommendations for any changes in technical approach, schedule, or budget that should be made in the remaining tasks
Respuesta
  • introduction
  • current project status
  • future project status
  • risk management

Pregunta 39

Pregunta
In the Future Project Status section of the audit report, no assumptions should be made about _________ that are still under investigation at the time of the audit.
Respuesta
  • financial problems
  • ethical problems
  • efficiency problems
  • technical problems

Pregunta 40

Pregunta
Contact between the a/e team and the _______________ are not made without clearance from senior management
Respuesta
  • CIO
  • ethics board
  • customer
  • project manager

Pregunta 41

Pregunta
The termination stage of the project rarely has much impact on
Respuesta
  • residual attitudes of the client towards the project
  • technical success or failure of the project
  • residual attitudes of senior management towards the project
  • the preparedness of the project team for the project

Pregunta 42

Pregunta
When a decision is made to terminate a project by extinction, the most noticeable event is that
Respuesta
  • all activity on the substance of the project ceases
  • all organizational activity related to the project ceases
  • all further expenditures related to the project are immediately blocked
  • all activity on the project ceases

Pregunta 43

Pregunta
In termination by addition, project assets are
Respuesta
  • transferred from a dying project to a new division
  • assumed to have been exhausted
  • liquidated
  • retained in the existing project

Pregunta 44

Pregunta
When an in-house project is a major success and it is terminated by institutionalizing it as a formal part of the parent organization; this is termination by
Respuesta
  • addition
  • starvation
  • integration
  • extinction

Pregunta 45

Pregunta
According to research by Pinto, the two most important critical success factors are
Respuesta
  • project mission and top-management support
  • trouble-shooting and communication
  • communication and personnel
  • project mission and communication

Pregunta 46

Pregunta
The fundamental purpose of the final project report is to
Respuesta
  • devote more resources to the project
  • finish the work so that payment can be collected
  • improve future projects
  • document the errors in the project

Pregunta 47

Pregunta
A common mistake in project management is to appoint as project manager an individual with excellent ________ skills but weak ___________ skills.
Respuesta
  • technical; managerial
  • managerial; technical
  • technical; social
  • social; managerial

Pregunta 48

Pregunta
Most studies have shown that the factors associated with project success or failure
Respuesta
  • are similar across different industries and the various types of projects
  • are different across different industries and the various types of projects
  • are similar across different industries but different for the various types of projects
  • are different across different industries but similar for the various types of projects

Pregunta 49

Pregunta
The project performance section of the final report
Respuesta
  • analyzes the impact of organizational structure on the project
  • offers solutions to technical problems that may have occurred
  • reviews the administrative practices used during the project
  • compares what the project achieved with what it aimed for

Pregunta 50

Pregunta
The techniques of project management section of the final report
Respuesta
  • analyzes the impact of organizational structure on the project
  • offers solutions to technical problems that may have occurred
  • reviews the administrative practices used during the project
  • scrutinizes the methods of planning, control, and risk management

Pregunta 51

Pregunta
The special case of termination by extinction wherein the project experiences a sudden demise even though it was lacking obvious signals that death was imminent is known as
Respuesta
  • termination by integration
  • termination by addition
  • termination by murder
  • termination by starvation

Pregunta 52

Pregunta
Special ___________ managers are sometimes useful in completing the long and involved process of shutting down the project.
Respuesta
  • close-out
  • starvation
  • shut-down
  • termination

Pregunta 53

Pregunta
The ___________ section of the final project report is a comparison of what the project achieved with what the project tried to achieve.
Respuesta
  • project performance
  • administrative performance
  • organizational structure
  • personnel suggestions

Pregunta 54

Pregunta
Cutting a project's budget sufficiently to stop progress without actually killing the project is referred to as
Respuesta
  • termination by addition
  • termination by extinction
  • termination by starvation
  • termination by subtraction

Pregunta 55

Pregunta
The primary criterion for project _____________ is whether or not the organization is willing to invest the estimated time and cost required to complete the project, given the project's current status and current expected outcome.
Respuesta
  • continuance
  • termination
  • continuance or termination
  • extinction

Pregunta 56

Pregunta
Bringing the project into the organization as a separate, ongoing entity is called
Respuesta
  • termination by starvation
  • termination by integration
  • termination by extinction
  • termination by addition

Pregunta 57

Pregunta
According to the text, a _________ cost is generally not relevant to current investment decisions. Rather, decision-makers should focus on the time and cost required to complete the project.
Respuesta
  • high
  • fixed
  • sunk
  • variable

Pregunta 58

Pregunta
If a project is a major success and it is terminated, by institutionalizing it as a formal part of the parent organization, this is an example of termination by
Respuesta
  • termination by integration
  • termination by addition
  • termination by murder
  • termination by starvation

Pregunta 59

Pregunta
Which of the following is not a common task for a termination manager?
Respuesta
  • ensuring completion of the work
  • redistributing personnel materials, and equipment
  • communicating with all stakeholders why the project was terminated
  • overseeing the closing of the project's books

Pregunta 60

Pregunta
In termination by integration, project assets are
Respuesta
  • liquidated
  • reassigned to another project
  • transferred from the dying project to the newly born division
  • distributed among the existing elements of the parent organization
Mostrar resumen completo Ocultar resumen completo

Similar

Test de Nombres de Alimentos en Inglés
maya velasquez
Anatomía del Sistema Respiratorio
edonoso
Consecuencias de la guerra civil
ignaciobll
Oftalmología - ENARM
Emilio Alonsooo
Novedades: Mapas Mentales de ExamTime
maya velasquez
Fechas clave de la Historia de España
maya velasquez
Conceptos Generales De Robótica
Diego Santos
Ventajas y Desventajas del Uso de las TIC en la Educacion
brayandavidscene
GoConQr. EJEMPLOS...
Ulises Yo
LA LEYENDA DEL SEÑOR SAN ANTONIO
Javier Pareja